8108 N RADFORD AVE 91605

Certificate Information: 8108 N RADFORD AVE 91605

Application / Permit
21014-10000-05465
Plan Check / Job No.
B21LA20438
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO (E) DETACHED GARAGE TO BE CONVERT TO ADU PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 4/14/2022
Issuing Office
Metro
Current Status
CofO Issued on 12/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/31/2021 APPLICANT
Assigned to Plan Check Engineer 11/4/2021 RICARDO RAMIREZ
Corrections Issued 11/5/2021 RICARDO RAMIREZ
Plan Check Approved 3/22/2022 FERNANDO FLORES
Issued 4/14/2022 APPLICANT
Building Plans Picked Up 4/19/2022 APPLICANT
CofO in Progress 11/1/2023 DAVID ANDERSON
CofO Issued 12/19/2023 RUBEN SALAS
Permit Finaled 12/19/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/23/2021 AMAAN MALIK
Roof/Waste drainage to street Cleared 12/23/2021 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 1/19/2022 AMAAN MALIK
Sewer availability Cleared 1/19/2022 AMAAN MALIK
Construction near power lines Cleared 2/18/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

WILLIAM WREN, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/23/2022 Partial Approval CHRISTOPHER DELLEFIELD
Pre-Inspection 8/23/2022 Corrections Issued CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 9/7/2022 Partial Approval CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 9/7/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 12/1/2022 Approved MATTHEW NELSON
HVAC-Rough 12/1/2022 Not Ready for Inspection MATTHEW NELSON
Insulation 12/1/2022 Partial Approval MATTHEW NELSON
PLUMBING-Rough 12/1/2022 Approved MATTHEW NELSON
BUILDING-Rough-Frame 2/17/2023 Approved MATTHEW NELSON
Green Building Rough 2/17/2023 Approved MATTHEW NELSON
HVAC-Rough 2/17/2023 Approved MATTHEW NELSON
Insulation 3/10/2023 Approved MATTHEW NELSON
Interior/Exterior Lathing 3/10/2023 Approved MATTHEW NELSON
Drywall Nailing 3/24/2023 Approved MATTHEW NELSON
Interior/Exterior Lathing 4/11/2023 Approved MATTHEW NELSON
Shower Pan 4/11/2023 Approved MATTHEW NELSON
Gas Test 8/17/2023 Approved MATTHEW NELSON
Underground Mechanical 8/17/2023 Approved MATTHEW NELSON
ELECTRICAL-Final 10/3/2023 Not Ready for Inspection CHRISTOPHER ROJAS
Final 10/3/2023 Corrections Issued CHRISTOPHER ROJAS
Gas Test 10/3/2023 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Final 10/3/2023 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Final 10/3/2023 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Final 10/3/2023 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 10/3/2023 SGSOV Not Ready CHRISTOPHER ROJAS
Smoke Detectors 10/3/2023 Approved CHRISTOPHER ROJAS
Final 10/31/2023 OK to Issue CofO DAVID ANDERSON
Green Building Final 10/31/2023 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 10/31/2023 SGSOV Approved DAVID ANDERSON