614-616 N SWEETZER AVE 90048
Certificate Information: 614-616 N SWEETZER AVE 90048
- Application / Permit
- 21014-10000-05457
- Plan Check / Job No.
- B21LA20407
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- ePLAN. NFPA 13 FIRE SPRINKLERS REQUIRED. CONVERT (E) RECREATION ROOM (475 SF) INTO AN ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(C)
- Permit Issued
- Issued on 3/10/2022
- Issuing Office
- Current Status
- CofO Issued on 2/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/25/2021 | KEVIN MORALES |
| Corrections Issued | 11/26/2021 | KEVIN MORALES |
| Quality Review Completed | 11/29/2021 | EUGENE BARBEAU |
| Applicant returned to address corrections | 12/28/2021 | KEVIN MORALES |
| Plan Check Approved | 3/4/2022 | KEVIN MORALES |
| Issued | 3/10/2022 | APPLICANT |
| CofO in Progress | 1/4/2024 | RAFAEL ESPINOZA |
| No Progress | 1/4/2024 | RAFAEL ESPINOZA |
| CofO in Progress | 2/2/2024 | RAFAEL ESPINOZA |
| CofO Issued | 2/2/2024 | ERNESTO CORRAL |
| Permit Finaled | 2/2/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 12/27/2021 | TREVOR QUAN |
| Sewer availability | Cleared | 12/27/2021 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/28/2021 | TREVOR QUAN |
| Fire Marshal Fire Life Safety | Cleared | 3/4/2022 | VIDAL GARCIA |
Contact Information
| Contractor | Working Hands Builders; Lic. No.: 1059742-B | 22778 CASS AVENUE WOODLAND HILLS, CA 91364 |
| Engineer | Deihimi,, Amir Hossein; Lic. No.: NA78194 | , |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 5/20/2022 | Approved | KATY RAMIREZ |
| Wood Frame | 5/20/2022 | Partial Approval | KATY RAMIREZ |
| Insulation | 5/26/2022 | Partial Inspection | SORIN CIRSTOIU |
| Interior/Exterior Lathing | 5/26/2022 | Partial Approval | SORIN CIRSTOIU |
| METHANE-Rough | 5/26/2022 | Approved | SORIN CIRSTOIU |
| Wood Frame | 5/26/2022 | Partial Inspection | SORIN CIRSTOIU |
| Insulation | 6/2/2022 | Approved | KATY RAMIREZ |
| Interior/Exterior Lathing | 6/2/2022 | Partial Approval | KATY RAMIREZ |
| Wood Frame | 6/2/2022 | Approved | KATY RAMIREZ |
| Drywall Nailing | 6/3/2022 | Approved | KATY RAMIREZ |
| Interior/Exterior Lathing | 6/3/2022 | Approved | KATY RAMIREZ |
| Final | 6/27/2022 | Conditional Approval | GREGORY POMISH |
| Green Building Final | 6/27/2022 | Approved | GREGORY POMISH |
| SGSOV-Seismic Gas S/O Valve | 6/27/2022 | SGSOV No Gas | GREGORY POMISH |
| Smoke Detectors | 6/27/2022 | Approved | GREGORY POMISH |
| Final | 1/4/2024 | OK to Issue CofO | RAFAEL ESPINOZA |