13805 W CALVERT ST 91401
Certificate Information: 13805 W CALVERT ST 91401
- Application / Permit
- 21014-10000-05456
- Plan Check / Job No.
- B21LA20405
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION & ALTERATION TO (E) 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED TWO CAR GARAGE.
- Permit Issued
- Issued on 3/13/2022
- Issuing Office
- Current Status
- CofO Issued on 4/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2021 | KESETE HAREGOT |
| Corrections Issued | 12/8/2021 | KESETE HAREGOT |
| Quality Review Completed | 12/10/2021 | FARUK SEZER |
| Applicant returned to address corrections | 2/28/2022 | KESETE HAREGOT |
| Plan Check Approved | 3/2/2022 | KESETE HAREGOT |
| Issued | 3/13/2022 | APPLICANT |
| Building Plans Picked Up | 4/13/2022 | APPLICANT |
| CofO in Progress | 2/7/2024 | RYAN SALAZAR |
| Permit Finaled | 4/1/2024 | DANIEL ORRANTE |
| CofO Issued | 4/1/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/1/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/30/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 12/30/2021 | DAGOVERTO GUERRERO |
| Green Code | Cleared | 2/28/2022 | KESETE HAREGOT |
| Eng Process Fee Ord 176,300 | Cleared | 3/1/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Aedifice Rex Inc; Lic. No.: 695941-B | 2528 RESERVOIR ST LOS ANGELES, CA 90026 |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/27/2022 | Conditional Approval | WILLIAM WREN |
| Footing/Foundation/Slab | 7/1/2022 | Approved | RICHARD DOCKUS |
| Underground Mechanical | 7/1/2022 | Approved | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2022 | Partial Approval | RICHARD DOCKUS |
| ELECTRICAL-Rough | 2/2/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 2/2/2023 | Approved | RYAN SALAZAR |
| Deputy Wood Construction | 2/14/2023 | Conditional Approval | MICHAEL SMITH |
| BUILDING-Rough-Frame | 2/27/2023 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2023 | Approved | RYAN SALAZAR |
| Green Building Rough | 2/27/2023 | Approved | RYAN SALAZAR |
| HVAC-Rough | 2/27/2023 | Approved | RYAN SALAZAR |
| Insulation | 3/2/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 3/2/2023 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 3/10/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 4/13/2023 | Approved | RYAN SALAZAR |
| Shower Pan | 4/13/2023 | Approved | RYAN SALAZAR |
| Final | 1/29/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 1/29/2024 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/29/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 1/29/2024 | Approved | JENNIFER RABUCHIN |
| Final | 2/6/2024 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 2/6/2024 | Approved | RYAN SALAZAR |