6507 W 81ST ST 90045
Certificate Information: 6507 W 81ST ST 90045
- Application / Permit
- 21014-10000-05435
- Plan Check / Job No.
- B21LA20315
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REAR MASTER BEDROOM AND MASTER BATH ADDITION; PATIO LATTICE.
- Permit Issued
- Issued on 3/17/2022
- Issuing Office
- Current Status
- CofO Issued on 3/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2021 | SAMUEL GONZALEZ |
| Corrections Issued | 11/6/2021 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 2/3/2022 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 2/24/2022 | RAHEL BEYENE |
| Plan Check Approved | 3/2/2022 | RAHEL BEYENE |
| Issued | 3/17/2022 | APPLICANT |
| Building Plans Picked Up | 3/23/2022 | APPLICANT |
| CofO in Progress | 3/3/2023 | HERBERT GIRON |
| Permit Finaled | 3/7/2023 | DANIEL ORRANTE |
| CofO Issued | 3/7/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/7/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/8/2021 | HISASHI KOBAYAKAWA |
| Low Impact Development | Cleared | 1/21/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 2/15/2022 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Leigh Construction; Lic. No.: 782532-B | 6511 81ST LOS ANGELES, CA 90045 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/18/2022 | Approved | JESUS RODRIGUEZ |
| Wood Frame | 5/25/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2022 | Partial Approval | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 7/14/2022 | Conditional Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 7/14/2022 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 7/14/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Rough | 7/14/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 7/14/2022 | Approved | JESUS RODRIGUEZ |
| Insulation | 8/3/2022 | Approved | HERBERT GIRON |
| Drywall Nailing | 8/8/2022 | Partial Approval | HERBERT GIRON |
| Shower Pan | 8/8/2022 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 8/15/2022 | Approved | HERBERT GIRON |
| Drywall Nailing | 8/15/2022 | Approved | HERBERT GIRON |
| Green Building Rough | 8/15/2022 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 8/15/2022 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 2/13/2023 | Corrections Issued | HERBERT GIRON |
| Final | 2/13/2023 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 2/13/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 2/13/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 2/13/2023 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 2/13/2023 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 2/13/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 3/2/2023 | Approved | HERBERT GIRON |
| Final | 3/2/2023 | OK to Issue CofO | HERBERT GIRON |
| PLUMBING-Final | 3/2/2023 | Approved | HERBERT GIRON |
| Smoke Detectors | 3/2/2023 | Approved | HERBERT GIRON |