10619 W CUSHDON AVE 90064
Certificate Information: 10619 W CUSHDON AVE 90064
- Application / Permit
- 21014-10000-05413
- Plan Check / Job No.
- B21LA20237
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND ALTERATION TO EXISTING 2-STORY SINGLE FAMILY DWELLING, 1ST AND 2ND FLOOR ADDITIONS
- Permit Issued
- Issued on 3/1/2022
- Issuing Office
- Current Status
- CofO Issued on 12/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2021 | CRYSTEL MAALOUF |
| Corrections Issued | 11/16/2021 | CRYSTEL MAALOUF |
| Quality Review Completed | 11/29/2021 | KEN GILL |
| Applicant returned to address corrections | 2/8/2022 | CRYSTEL MAALOUF |
| Plan Check Approved | 2/18/2022 | CRYSTEL MAALOUF |
| Issued | 3/1/2022 | APPLICANT |
| Building Plans Picked Up | 3/10/2022 | APPLICANT |
| CofO in Progress | 12/24/2022 | CHRISTOPHER WILSON |
| CofO in Progress | 12/24/2022 | CHRISTOPHER WILSON |
| Permit Finaled | 12/29/2022 | DANIEL ORRANTE |
| CofO Issued | 12/29/2022 | DANIEL ORRANTE |
| Permit Finaled | 12/29/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/16/2021 | SERGIO VALENZUELA |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2021 | SAUL GARCIA |
| Sewer availability | Cleared | 12/27/2021 | SAUL GARCIA |
| Specific Plan | Cleared | 1/18/2022 | FREDDY GARCIA |
| GPI Written Notices | Cleared | 2/16/2022 | CRYSTEL MAALOUF |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21757 DEVONSHIRE ST. SUITE 3 CANOGA PARK, CA 91311 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/12/2022 | Corrections Issued | KEVIN SARGSYAN |
| Pre-Inspection | 4/12/2022 | Partial Inspection | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 4/13/2022 | Conditional Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 4/14/2022 | Partial Approval | KEVIN SARGSYAN |
| METHANE-Barrier | 4/14/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| METHANE-Subgrade | 4/14/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 4/14/2022 | Partial Approval | KEVIN SARGSYAN |
| Structural Steel Frame | 4/14/2022 | Partial Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 4/19/2022 | Corrections Issued | KEVIN SARGSYAN |
| Pre-Inspection | 4/19/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Structural Steel Frame | 4/19/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 4/21/2022 | Partial Approval | KEVIN SARGSYAN |
| Structural Steel Frame | 4/21/2022 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 4/22/2022 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2022 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 5/2/2022 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 5/4/2022 | Partial Approval | KEVIN SARGSYAN |
| Insulation | 5/4/2022 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 5/4/2022 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2022 | Corrections Issued | KEVIN SARGSYAN |
| Deputy Wood Construction | 5/9/2022 | Conditional Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2022 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2022 | Partial Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 5/13/2022 | Approved | KEVIN SARGSYAN |
| Pre-Inspection | 6/16/2022 | Partial Inspection | KEVIN SARGSYAN |
| Deputy Wood Construction | 6/17/2022 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2022 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Special/Order Compliance | 6/24/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Rough-Elec/Plmb/HVAC | 7/25/2022 | Corrections Issued | KEVIN SARGSYAN |
| Rough-Elec/Plmb/HVAC | 7/29/2022 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 8/2/2022 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 8/4/2022 | Conditional Approval | CLAYTON GRAHAM |
| Wood Frame | 8/4/2022 | Partial Approval | CLAYTON GRAHAM |
| Insulation | 8/9/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Insulation | 8/11/2022 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 8/11/2022 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 8/15/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/17/2022 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 8/17/2022 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 8/26/2022 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 8/31/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 9/7/2022 | Approved | JOHN KIDWELL |
| ELECTRICAL-Final | 12/14/2022 | Corrections Issued | ASHLEY THOMPSON |
| Gas Test | 12/14/2022 | Approved | ASHLEY THOMPSON |
| HVAC-Final | 12/14/2022 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Final | 12/14/2022 | Conditional Approval | ASHLEY THOMPSON |
| ELECTRICAL-Final | 12/19/2022 | Approved | OGANES TARAKHCHYAN |
| Gas Test | 12/19/2022 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 12/19/2022 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 12/19/2022 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 12/23/2022 | Approved | CHRISTOPHER WILSON |
| Final | 12/23/2022 | OK to Issue CofO | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 12/23/2022 | Approved | CHRISTOPHER WILSON |
| Green Building Final | 12/23/2022 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 12/23/2022 | Approved | CHRISTOPHER WILSON |
| METHANE-Final | 12/23/2022 | Approved | CHRISTOPHER WILSON |
| METHANE-Rough | 12/23/2022 | Approved | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 12/23/2022 | SGSOV Approved | CHRISTOPHER WILSON |
| Smoke Detectors | 12/23/2022 | Approved | CHRISTOPHER WILSON |