11319 N GLENOAKS BLVD 91331
Certificate Information: 11319 N GLENOAKS BLVD 91331
- Application / Permit
- 21014-10000-05408
- Plan Check / Job No.
- B21LA20230
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New Attacned cover Patio Addition and addtion to expand (E) kitchen and living room with new bathroom to (E) one story SFD.
- Permit Issued
- Issued on 1/4/2022
- Issuing Office
- Current Status
- CofO Issued on 12/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/1/2021 | TSE MING HUANG |
| Corrections Issued | 11/1/2021 | TSE MING HUANG |
| Plan Check Approved | 12/1/2021 | DANIEL SANJUAN |
| Building Plans Picked Up | 12/2/2021 | APPLICANT |
| Issued | 1/4/2022 | APPLICANT |
| CofO in Progress | 11/18/2025 | MICHEL ABAJAN |
| CofO Issued | 12/2/2025 | RUBEN SALAS |
| Permit Finaled | 12/2/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 12/1/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Martirossyan,, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/11/2022 | Partial Inspection | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 3/9/2022 | No Access for Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 3/17/2022 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2022 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2022 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 4/11/2022 | Partial Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 4/11/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 4/18/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 4/18/2022 | Approved | MICHEL ABAJAN |
| Green Building Rough | 4/18/2022 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 4/18/2022 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 4/18/2022 | Approved | MICHEL ABAJAN |
| Insulation | 4/28/2022 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 5/16/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 7/18/2022 | Approved | MICHEL ABAJAN |
| Final | 7/18/2022 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 7/18/2022 | Approved | MICHEL ABAJAN |
| HVAC-Final | 7/18/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 7/18/2022 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/18/2022 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 7/18/2022 | Approved | MICHEL ABAJAN |
| Final | 11/6/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 11/17/2025 | OK to Issue CofO | MICHEL ABAJAN |