4632 N NATICK AVE 1-19 91403

Certificate Information: 4632 N NATICK AVE 1-19 91403

Application / Permit
21014-10000-05362
Plan Check / Job No.
B21LA20094
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
EPLAN. CONVERT EXISTING STORAGE AT 1ST FLOOR WITHIN 3-STORY APARTMENT BUILDING INTO ONE (1) ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 1/30/2023
Issuing Office
Current Status
CofO Issued on 8/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/26/2021 APPLICANT
Assigned to Plan Check Engineer 11/18/2021 PRANITA SHAH
Corrections Issued 12/13/2021 PRANITA SHAH
Quality Review Completed 12/14/2021 HERNAN ARREOLA
Applicant returned to address corrections 4/5/2022 PRANITA SHAH
Applicant returned to address corrections 8/2/2022 PRANITA SHAH
Plan Check Approved 1/24/2023 PRANITA SHAH
Issued 1/30/2023 APPLICANT
CofO in Progress 8/14/2024 BRIAN KELLY
CofO Issued 8/16/2024 JEFFREY DURAN
Permit Finaled 8/16/2024 JEFFREY DURAN

Permit Application Clearance Information

Address approval Cleared 1/3/2022 AMIR KASHFI
Sewer availability Cleared 1/3/2022 AMIR KASHFI
ZA Case Cleared 1/6/2022 LOUIS ORTEGA
Eng Process Fee Ord 176,300 Cleared 2/15/2022 AMIR KASHFI
DAS Clearance Cleared 6/27/2022 PRANITA SHAH
Green Code Cleared 9/27/2022 PRANITA SHAH
Fire Marshal Fire Life Safety Cleared 12/9/2022 VIDAL GARCIA

Contact Information

Contractor Cal - Quake Construction Inc; Lic. No.: 759817-B       ,
Contractor Perluss Sheldon K; Lic. No.: 759817-B       ,
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 8232 GARVEY AVE 203      ROSEMEAD, CA 91770

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/17/2023 Partial Approval BRIAN KELLY
Light Gage Steel Frame 5/17/2023 Corrections Issued ANDREW DORSO
Insulation 5/19/2023 Approved ANDREW DORSO
Special/Order Compliance 5/19/2023 Conditional Approval STEVEN LEVITT
Drywall Nailing 5/23/2023 Partial Approval BRIAN KELLY
Drywall Nailing 5/31/2023 Approved STEVEN LEVITT
Drywall Nailing 6/1/2023 Not Ready for Inspection BRIAN KELLY
Final 9/11/2023 Conditional Approval STEVEN LEVITT
Green Building Final 9/11/2023 Approved STEVEN LEVITT
Green Building Rough 9/11/2023 Approved STEVEN LEVITT
Reinforced Concrete Frame 9/11/2023 Approved STEVEN LEVITT
SGSOV-Seismic Gas S/O Valve 9/11/2023 SGSOV Approved STEVEN LEVITT
Smoke Detectors 9/11/2023 Approved STEVEN LEVITT
Wood Frame 9/11/2023 Approved STEVEN LEVITT
Final 8/13/2024 OK to Issue CofO BRIAN KELLY