750 N DETROIT ST 90046

Certificate Information: 750 N DETROIT ST 90046

Application / Permit
21014-10000-05347
Plan Check / Job No.
B21LA20003
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
2ND FLOOR ADDITION AND GARAGE CONVERSION TO ADU PER 12.22 A 33 C & D
Permit Issued
Issued on 10/13/2022
Issuing Office
Metro
Current Status
CofO Issued on 12/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2021 APPLICANT
Assigned to Plan Check Engineer 12/2/2021 STARR CHEN
Corrections Issued 12/8/2021 STARR CHEN
Quality Review Completed 12/16/2021 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 12/20/2021 APPLICANT
Applicant returned to address corrections 5/25/2022 STARR CHEN
Applicant returned to address corrections 6/16/2022 STARR CHEN
Applicant returned to address corrections 6/24/2022 STARR CHEN
Applicant returned to address corrections 7/14/2022 STARR CHEN
Plan Check Approved 10/13/2022 STARR CHEN
Issued 10/13/2022 APPLICANT
CofO in Progress 12/4/2025 JOSH MEISTER
Permit Finaled 12/6/2025 DEROLD HAUFF
CofO Issued 12/6/2025 DEROLD HAUFF
Permit Finaled 12/6/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/17/2021 CINDY QI
Roof/Waste drainage to street Cleared 12/17/2021 CINDY QI
Eng Process Fee Ord 176,300 Cleared 12/20/2021 CINDY QI
Sewer availability Cleared 12/20/2021 CINDY QI
Hydrant and Access approval Cleared 3/1/2022 CINDY JOSSELYN
Construction near power lines Cleared 10/3/2022 RIDWAN HARDY

Contact Information

Contractor Sqs Contractors Inc; Lic. No.: 1068870-B PO BOX 482      LYNWOOD, CA 90262

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/13/2023 Partial Inspection MICHAEL LEWIS
Footing/Foundation/Slab 3/3/2023 Approved MICHAEL LEWIS
METHANE-Barrier 3/3/2023 Approved MICHAEL LEWIS
METHANE-Subgrade 3/3/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 3/31/2023 Not Ready for Inspection MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 3/31/2023 Partial Approval MICHAEL LEWIS
Green Building Rough 3/31/2023 Not Ready for Inspection MICHAEL LEWIS
METHANE-Rough 3/31/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 4/21/2023 Partial Approval JOSEPH MCGARRY
HVAC-Rough 10/23/2023 Corrections Issued JOSEPH MCGARRY
HVAC-Rough 11/2/2023 Corrections Issued LILIANA PORTILLO
Shower Pan 11/2/2023 Approved LILIANA PORTILLO
Underground Mechanical 11/2/2023 Partial Approval LILIANA PORTILLO
HVAC-Rough 11/7/2023 Partial Approval LILIANA PORTILLO
Wood Frame 11/30/2023 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 1/10/2024 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 1/22/2024 Conditional Approval LILIANA PORTILLO
Green Building Rough 1/22/2024 Not Ready for Inspection LILIANA PORTILLO
Interior/Exterior Lathing 1/24/2024 Corrections Issued AMIR NAZARIAN
Interior/Exterior Lathing 1/26/2024 Partial Approval AMIR NAZARIAN
Special/Order Compliance 1/26/2024 Partial Approval JOAQUIN GREENOUGH
Insulation 4/25/2024 Corrections Issued AMIR NAZARIAN
Wood Frame 4/25/2024 Not Ready for Inspection AMIR NAZARIAN
Insulation 5/10/2024 Approved AMIR NAZARIAN
HVAC-Rough 5/13/2024 Approved AMIR NAZARIAN
HVAC-Rough 5/15/2024 Approved AMIR NAZARIAN
Drywall Nailing 7/29/2024 Approved AMIR NAZARIAN
Interior/Exterior Lathing 8/2/2024 Approved AMIR NAZARIAN
Wood Frame 11/1/2024 Corrections Issued JOSE MACIAS
Gas Test 9/8/2025 Approved JOSH MEISTER
BUILDING-Rough-Frame 9/11/2025 Corrections Issued JOSE MACIAS
Final 9/11/2025 Corrections Issued JOSE MACIAS
Green Building Final 9/11/2025 Approved JOSE MACIAS
Green Building Rough 9/11/2025 Approved JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 9/11/2025 SGSOV Approved JOSE MACIAS
Smoke Detectors 9/11/2025 Not Ready for Inspection JOSE MACIAS
BUILDING-Rough-Frame 9/17/2025 Not Ready for Inspection RAUL BARAJAS
Final 9/17/2025 Not Ready for Inspection RAUL BARAJAS
Smoke Detectors 9/17/2025 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 9/19/2025 Approved JOSE MACIAS
Final 9/19/2025 Conditional Approval JOSE MACIAS
Smoke Detectors 9/19/2025 Approved JOSE MACIAS
Final 9/25/2025 Corrections Issued JOSE MACIAS
Final 9/26/2025 Corrections Issued JOSE MACIAS
Final 12/3/2025 OK to Issue CofO JOSH MEISTER