750 N DETROIT ST 90046
Certificate Information: 750 N DETROIT ST 90046
- Application / Permit
- 21014-10000-05347
- Plan Check / Job No.
- B21LA20003
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 2ND FLOOR ADDITION AND GARAGE CONVERSION TO ADU PER 12.22 A 33 C & D
- Permit Issued
- Issued on 10/13/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2021 | STARR CHEN |
| Corrections Issued | 12/8/2021 | STARR CHEN |
| Quality Review Completed | 12/16/2021 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 12/20/2021 | APPLICANT |
| Applicant returned to address corrections | 5/25/2022 | STARR CHEN |
| Applicant returned to address corrections | 6/16/2022 | STARR CHEN |
| Applicant returned to address corrections | 6/24/2022 | STARR CHEN |
| Applicant returned to address corrections | 7/14/2022 | STARR CHEN |
| Plan Check Approved | 10/13/2022 | STARR CHEN |
| Issued | 10/13/2022 | APPLICANT |
| CofO in Progress | 12/4/2025 | JOSH MEISTER |
| Permit Finaled | 12/6/2025 | DEROLD HAUFF |
| CofO Issued | 12/6/2025 | DEROLD HAUFF |
| Permit Finaled | 12/6/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/17/2021 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 12/17/2021 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 12/20/2021 | CINDY QI |
| Sewer availability | Cleared | 12/20/2021 | CINDY QI |
| Hydrant and Access approval | Cleared | 3/1/2022 | CINDY JOSSELYN |
| Construction near power lines | Cleared | 10/3/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Sqs Contractors Inc; Lic. No.: 1068870-B | PO BOX 482 LYNWOOD, CA 90262 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/13/2023 | Partial Inspection | MICHAEL LEWIS |
| Footing/Foundation/Slab | 3/3/2023 | Approved | MICHAEL LEWIS |
| METHANE-Barrier | 3/3/2023 | Approved | MICHAEL LEWIS |
| METHANE-Subgrade | 3/3/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 3/31/2023 | Not Ready for Inspection | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2023 | Partial Approval | MICHAEL LEWIS |
| Green Building Rough | 3/31/2023 | Not Ready for Inspection | MICHAEL LEWIS |
| METHANE-Rough | 3/31/2023 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2023 | Partial Approval | JOSEPH MCGARRY |
| HVAC-Rough | 10/23/2023 | Corrections Issued | JOSEPH MCGARRY |
| HVAC-Rough | 11/2/2023 | Corrections Issued | LILIANA PORTILLO |
| Shower Pan | 11/2/2023 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 11/2/2023 | Partial Approval | LILIANA PORTILLO |
| HVAC-Rough | 11/7/2023 | Partial Approval | LILIANA PORTILLO |
| Wood Frame | 11/30/2023 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 1/10/2024 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 1/22/2024 | Conditional Approval | LILIANA PORTILLO |
| Green Building Rough | 1/22/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Interior/Exterior Lathing | 1/24/2024 | Corrections Issued | AMIR NAZARIAN |
| Interior/Exterior Lathing | 1/26/2024 | Partial Approval | AMIR NAZARIAN |
| Special/Order Compliance | 1/26/2024 | Partial Approval | JOAQUIN GREENOUGH |
| Insulation | 4/25/2024 | Corrections Issued | AMIR NAZARIAN |
| Wood Frame | 4/25/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Insulation | 5/10/2024 | Approved | AMIR NAZARIAN |
| HVAC-Rough | 5/13/2024 | Approved | AMIR NAZARIAN |
| HVAC-Rough | 5/15/2024 | Approved | AMIR NAZARIAN |
| Drywall Nailing | 7/29/2024 | Approved | AMIR NAZARIAN |
| Interior/Exterior Lathing | 8/2/2024 | Approved | AMIR NAZARIAN |
| Wood Frame | 11/1/2024 | Corrections Issued | JOSE MACIAS |
| Gas Test | 9/8/2025 | Approved | JOSH MEISTER |
| BUILDING-Rough-Frame | 9/11/2025 | Corrections Issued | JOSE MACIAS |
| Final | 9/11/2025 | Corrections Issued | JOSE MACIAS |
| Green Building Final | 9/11/2025 | Approved | JOSE MACIAS |
| Green Building Rough | 9/11/2025 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 9/11/2025 | SGSOV Approved | JOSE MACIAS |
| Smoke Detectors | 9/11/2025 | Not Ready for Inspection | JOSE MACIAS |
| BUILDING-Rough-Frame | 9/17/2025 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 9/17/2025 | Not Ready for Inspection | RAUL BARAJAS |
| Smoke Detectors | 9/17/2025 | Not Ready for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 9/19/2025 | Approved | JOSE MACIAS |
| Final | 9/19/2025 | Conditional Approval | JOSE MACIAS |
| Smoke Detectors | 9/19/2025 | Approved | JOSE MACIAS |
| Final | 9/25/2025 | Corrections Issued | JOSE MACIAS |
| Final | 9/26/2025 | Corrections Issued | JOSE MACIAS |
| Final | 12/3/2025 | OK to Issue CofO | JOSH MEISTER |