752 N DETROIT ST 90046
Certificate Information: 752 N DETROIT ST 90046
- Application / Permit
- 21014-10000-05346
- Plan Check / Job No.
- B21LA20003
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2ND FLOOR ADDITION TO EXISTING 1 STORY SFD
- Permit Issued
- Issued on 8/5/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2021 | STARR CHEN |
| Corrections Issued | 12/8/2021 | STARR CHEN |
| Quality Review Completed | 12/16/2021 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 12/20/2021 | APPLICANT |
| Applicant returned to address corrections | 5/25/2022 | STARR CHEN |
| Applicant returned to address corrections | 6/16/2022 | STARR CHEN |
| Applicant returned to address corrections | 6/24/2022 | STARR CHEN |
| Plan Check Approved | 7/14/2022 | STARR CHEN |
| Issued | 8/5/2022 | APPLICANT |
| CofO in Progress | 9/29/2025 | JOSE MACIAS |
| Permit Finaled | 10/4/2025 | DEROLD HAUFF |
| CofO Issued | 10/4/2025 | DEROLD HAUFF |
| Permit Finaled | 10/4/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/17/2021 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 12/20/2021 | CINDY QI |
| Sewer availability | Cleared | 12/20/2021 | CINDY QI |
Contact Information
| Contractor | Sqs Contractors Inc; Lic. No.: 1068870-B | PO BOX 482 LYNWOOD, CA 90262 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/15/2022 | Approved | MICHAEL LEWIS |
| Deputy Drilled-In Anchors | 10/24/2022 | Conditional Approval | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 10/27/2022 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 10/27/2022 | Approved | MICHAEL LEWIS |
| METHANE-Barrier | 10/27/2022 | Approved | MICHAEL LEWIS |
| METHANE-Subgrade | 10/27/2022 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2022 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2023 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 12/14/2023 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2023 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 12/14/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 12/14/2023 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 12/14/2023 | Approved | LILIANA PORTILLO |
| Shower Pan | 12/14/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 12/15/2023 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 12/15/2023 | Approved | JOAQUIN GREENOUGH |
| METHANE-Rough | 12/15/2023 | Approved | JOAQUIN GREENOUGH |
| Green Building Final | 1/8/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Insulation | 1/8/2024 | Approved | JEFFREY MEAD |
| Drywall Nailing | 2/27/2024 | Approved | AMIR NAZARIAN |
| Interior/Exterior Lathing | 8/2/2024 | Approved | AMIR NAZARIAN |
| Wood Frame | 11/1/2024 | Corrections Issued | JOSE MACIAS |
| Final | 9/3/2025 | Corrections Issued | BRENDAN MORELLI |
| Green Building Final | 9/3/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 9/3/2025 | SGSOV Gas Company | BRENDAN MORELLI |
| Smoke Detectors | 9/3/2025 | Corrections Issued | BRENDAN MORELLI |
| Final | 9/11/2025 | Corrections Issued | JOSE MACIAS |
| Green Building Final | 9/11/2025 | Approved | JOSE MACIAS |
| Smoke Detectors | 9/11/2025 | Approved | JOSE MACIAS |
| Final | 9/17/2025 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 9/19/2025 | OK to Issue CofO | JOSE MACIAS |