1559 S CLUB VIEW DR 90024

Certificate Information: 1559 S CLUB VIEW DR 90024

Application / Permit
21014-10000-05326
Plan Check / Job No.
B21LA19897
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2ND FLOOR ADDITION AND REMODEL TO (E) S.F.D.
Permit Issued
Issued on 7/10/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/26/2021 APPLICANT
Assigned to Plan Check Engineer 11/18/2021 CRYSTEL MAALOUF
Corrections Issued 12/8/2021 CRYSTEL MAALOUF
Quality Review Completed 12/16/2021 KEN GILL
Plan Check Approved 6/13/2022 CRYSTEL MAALOUF
Issued 7/10/2023 APPLICANT
CofO in Progress 4/30/2024 STEPHANIE SWANSON
Permit Finaled 5/1/2024 DANIEL ORRANTE
CofO Issued 5/1/2024 DANIEL ORRANTE
Permit Finaled 5/1/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/21/2022 JOSE HERNANDEZ
Sewer availability Cleared 2/26/2022 JOSE HERNANDEZ
Specific Plan Cleared 3/1/2022 FREDDY GARCIA
Grading Pre-Inspection Cleared 4/5/2022 KIRK LINKLATER
GPI Written Notices Cleared 6/13/2022 CRYSTEL MAALOUF

Contact Information

Contractor Owner-Builder       ,
Engineer Vartanian,, Albert; Lic. No.: C39989 PO BOX 857      VERDUGO CITY, CA 91046

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/8/2023 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 8/10/2023 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 8/22/2023 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 9/7/2023 Corrections Issued CHRISTOPHER WILSON
Deputy Wood Construction 9/8/2023 Conditional Approval MICHAEL PELHAM
BUILDING-Rough-Frame 9/12/2023 Not Ready for Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 9/12/2023 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 9/18/2023 Partial Approval STEPHANIE SWANSON
ELECTRICAL-Rough 9/18/2023 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 9/28/2023 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 9/28/2023 Partial Approval STEPHANIE SWANSON
PLUMBING-Rough 9/28/2023 Corrections Issued STEPHANIE SWANSON
Insulation 10/4/2023 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 10/10/2023 Corrections Issued STEPHANIE SWANSON
Green Building Rough 10/10/2023 Not Ready for Inspection STEPHANIE SWANSON
Deputy Wood Construction 10/11/2023 Conditional Approval MICHAEL PELHAM
Deputy Wood Construction 10/13/2023 Approved STEPHANIE SWANSON
Drywall Nailing 10/13/2023 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 10/13/2023 Approved STEPHANIE SWANSON
PLUMBING-Rough 10/13/2023 Partial Approval STEPHANIE SWANSON
Interior/Exterior Lathing 10/18/2023 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 10/20/2023 Corrections Issued STEPHANIE SWANSON
Interior/Exterior Lathing 10/20/2023 Partial Approval STEPHANIE SWANSON
PLUMBING-Rough 10/20/2023 Corrections Issued STEPHANIE SWANSON
Insulation 10/26/2023 Partial Approval STEPHANIE SWANSON
Drywall Nailing 10/31/2023 Partial Approval STEPHANIE SWANSON
PLUMBING-Rough 11/7/2023 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 11/9/2023 Approved STEPHANIE SWANSON
PLUMBING-Final 11/9/2023 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 11/9/2023 Approved STEPHANIE SWANSON
Insulation 11/14/2023 Approved STEPHANIE SWANSON
Drywall Nailing 12/5/2023 Approved STEPHANIE SWANSON
Shower Pan 12/5/2023 Approved STEPHANIE SWANSON
Deputy Wood Construction 12/6/2023 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 12/6/2023 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 3/20/2024 Approved STEPHANIE SWANSON
Green Building Final 3/20/2024 Approved STEPHANIE SWANSON
Green Building Rough 3/20/2024 Approved STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 3/20/2024 SGSOV Not Ready STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 4/23/2024 SGSOV Not Ready CHRISTOPHER WILSON
ELECTRICAL-Final 4/25/2024 Corrections Issued STEPHANIE SWANSON
Final 4/25/2024 Corrections Issued STEPHANIE SWANSON
HVAC-Final 4/25/2024 Approved STEPHANIE SWANSON
PLUMBING-Final 4/25/2024 Approved STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 4/25/2024 SGSOV Approved STEPHANIE SWANSON
Smoke Detectors 4/25/2024 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Final 4/30/2024 Approved STEPHANIE SWANSON
Final 4/30/2024 OK to Issue CofO STEPHANIE SWANSON
Smoke Detectors 4/30/2024 Approved STEPHANIE SWANSON