454 S SOTO ST 90033

Certificate Information: 454 S SOTO ST 90033

Application / Permit
21014-10000-05319
Plan Check / Job No.
B21LA19887
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED MAJOR REMODEL TO (E) SFD (DEMO 99%, ONLY 8'7" EXTERIOR WALL TO REMAIN ) ADDITION 361 SQ.FT. ON FIRST FLOOR. AND NEW PORCH AND NEW SECOND FLOOR 1,055 SQ.FT.
Permit Issued
Issued on 8/8/2023
Issuing Office
Metro
Current Status
CofO Issued on 4/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/3/2021 APPLICANT
Assigned to Plan Check Engineer 12/9/2021 JAD BASMA
Corrections Issued 12/21/2021 JAD BASMA
Quality Review Completed 12/21/2021 MICHAEL PEREZ
Building Plans Picked Up 12/27/2021 APPLICANT
Applicant returned to address corrections 6/2/2022 JAD BASMA
Applicant returned to address corrections 4/24/2023 JAD BASMA
Applicant returned to address corrections 5/31/2023 JAD BASMA
Plan Check Approved 8/8/2023 JAD BASMA
Issued 8/8/2023 APPLICANT
CofO in Progress 4/13/2026 FREDDIE RIVERA
Permit Finaled 4/13/2026 DEROLD HAUFF
CofO Issued 4/13/2026 DEROLD HAUFF
Permit Finaled 4/13/2026 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/22/2022 WALLIE JONG
Sewer availability Cleared 6/22/2022 WALLIE JONG
Grading Pre-Inspection Cleared 8/11/2022 JAD BASMA
Low Impact Development Cleared 3/2/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 3/21/2023 JENSON LEE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/25/2024 Partial Approval FREDDIE RIVERA
Deputy Methane Barrier 4/30/2024 Conditional Approval FREDDIE RIVERA
PLUMBING-Rough 5/1/2024 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 5/23/2024 Conditional Approval FREDDIE RIVERA
METHANE-Barrier 5/23/2024 Conditional Approval FREDDIE RIVERA
METHANE-Subgrade 5/23/2024 Corrections Issued FREDDIE RIVERA
Deputy Methane Barrier 5/24/2024 Conditional Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 7/9/2024 Partial Approval FREDDIE RIVERA
Green Building Rough 7/9/2024 Partial Inspection FREDDIE RIVERA
METHANE-Rough 7/9/2024 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 9/5/2024 Partial Approval JOHN QUINTANILLA
ELECTRICAL-Rough 9/5/2024 Corrections Issued JOHN QUINTANILLA
Green Building Rough 9/5/2024 Not Ready for Inspection JOHN QUINTANILLA
HVAC-Rough 9/5/2024 Partial Approval JOHN QUINTANILLA
METHANE-Rough 9/5/2024 Partial Approval JOHN QUINTANILLA
PLUMBING-Rough 9/5/2024 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 9/11/2024 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Rough 9/11/2024 Approved FREDDIE RIVERA
Green Building Rough 9/11/2024 Approved FREDDIE RIVERA
HVAC-Final 9/11/2024 Approved FREDDIE RIVERA
Interior/Exterior Lathing 9/11/2024 Approved FREDDIE RIVERA
METHANE-Rough 9/11/2024 Approved FREDDIE RIVERA
Insulation 9/17/2024 Conditional Approval JUSTIN HAWLEY
Pre-Inspection 9/17/2024 Approved JUSTIN HAWLEY
Drywall Nailing 11/14/2024 Approved LUIS CASTRO
Interior/Exterior Lathing 11/18/2024 Approved ANTHONY RAMOS
Shower Pan 11/18/2024 Approved ANTHONY RAMOS
ELECTRICAL-Final 12/23/2024 Partial Inspection FREDDIE RIVERA
Service/Power Release 12/23/2024 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 1/13/2025 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Final 1/13/2025 Corrections Issued FREDDIE RIVERA
Final 1/13/2025 Partial Inspection FREDDIE RIVERA
Footing/Foundation/Slab 1/13/2025 Partial Inspection FREDDIE RIVERA
Green Building Final 1/13/2025 Partial Inspection FREDDIE RIVERA
METHANE-Subgrade 1/13/2025 Partial Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 1/13/2025 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 1/13/2025 Partial Inspection FREDDIE RIVERA
Special/Order Compliance 1/13/2025 Approved OSVALDO PARAMO
Verify Sprinkler Sign Off 1/13/2025 Partial Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 1/21/2025 SGSOV Not Ready FREDDIE RIVERA
Service/Power Release 1/24/2025 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 2/19/2025 Approved FREDDIE RIVERA
Final 2/19/2025 Partial Inspection FREDDIE RIVERA
Footing/Foundation/Slab 2/19/2025 Approved FREDDIE RIVERA
Green Building Final 2/19/2025 Approved FREDDIE RIVERA
METHANE-Barrier 2/19/2025 Approved FREDDIE RIVERA
METHANE-Subgrade 2/19/2025 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 2/19/2025 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 2/19/2025 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 2/19/2025 Approved FREDDIE RIVERA
Final 2/27/2025 OK to Issue CofO FREDDIE RIVERA