454 S SOTO ST 90033
Certificate Information: 454 S SOTO ST 90033
- Application / Permit
- 21014-10000-05319
- Plan Check / Job No.
- B21LA19887
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED MAJOR REMODEL TO (E) SFD (DEMO 99%, ONLY 8'7" EXTERIOR WALL TO REMAIN ) ADDITION 361 SQ.FT. ON FIRST FLOOR. AND NEW PORCH AND NEW SECOND FLOOR 1,055 SQ.FT.
- Permit Issued
- Issued on 8/8/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/13/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2021 | JAD BASMA |
| Corrections Issued | 12/21/2021 | JAD BASMA |
| Quality Review Completed | 12/21/2021 | MICHAEL PEREZ |
| Building Plans Picked Up | 12/27/2021 | APPLICANT |
| Applicant returned to address corrections | 6/2/2022 | JAD BASMA |
| Applicant returned to address corrections | 4/24/2023 | JAD BASMA |
| Applicant returned to address corrections | 5/31/2023 | JAD BASMA |
| Plan Check Approved | 8/8/2023 | JAD BASMA |
| Issued | 8/8/2023 | APPLICANT |
| CofO in Progress | 4/13/2026 | FREDDIE RIVERA |
| Permit Finaled | 4/13/2026 | DEROLD HAUFF |
| CofO Issued | 4/13/2026 | DEROLD HAUFF |
| Permit Finaled | 4/13/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/22/2022 | WALLIE JONG |
| Sewer availability | Cleared | 6/22/2022 | WALLIE JONG |
| Grading Pre-Inspection | Cleared | 8/11/2022 | JAD BASMA |
| Low Impact Development | Cleared | 3/2/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 3/21/2023 | JENSON LEE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/25/2024 | Partial Approval | FREDDIE RIVERA |
| Deputy Methane Barrier | 4/30/2024 | Conditional Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 5/1/2024 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 5/23/2024 | Conditional Approval | FREDDIE RIVERA |
| METHANE-Barrier | 5/23/2024 | Conditional Approval | FREDDIE RIVERA |
| METHANE-Subgrade | 5/23/2024 | Corrections Issued | FREDDIE RIVERA |
| Deputy Methane Barrier | 5/24/2024 | Conditional Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2024 | Partial Approval | FREDDIE RIVERA |
| Green Building Rough | 7/9/2024 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Rough | 7/9/2024 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/5/2024 | Partial Approval | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 9/5/2024 | Corrections Issued | JOHN QUINTANILLA |
| Green Building Rough | 9/5/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| HVAC-Rough | 9/5/2024 | Partial Approval | JOHN QUINTANILLA |
| METHANE-Rough | 9/5/2024 | Partial Approval | JOHN QUINTANILLA |
| PLUMBING-Rough | 9/5/2024 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 9/11/2024 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Rough | 9/11/2024 | Approved | FREDDIE RIVERA |
| Green Building Rough | 9/11/2024 | Approved | FREDDIE RIVERA |
| HVAC-Final | 9/11/2024 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 9/11/2024 | Approved | FREDDIE RIVERA |
| METHANE-Rough | 9/11/2024 | Approved | FREDDIE RIVERA |
| Insulation | 9/17/2024 | Conditional Approval | JUSTIN HAWLEY |
| Pre-Inspection | 9/17/2024 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 11/14/2024 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 11/18/2024 | Approved | ANTHONY RAMOS |
| Shower Pan | 11/18/2024 | Approved | ANTHONY RAMOS |
| ELECTRICAL-Final | 12/23/2024 | Partial Inspection | FREDDIE RIVERA |
| Service/Power Release | 12/23/2024 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 1/13/2025 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Final | 1/13/2025 | Corrections Issued | FREDDIE RIVERA |
| Final | 1/13/2025 | Partial Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 1/13/2025 | Partial Inspection | FREDDIE RIVERA |
| Green Building Final | 1/13/2025 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Subgrade | 1/13/2025 | Partial Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 1/13/2025 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 1/13/2025 | Partial Inspection | FREDDIE RIVERA |
| Special/Order Compliance | 1/13/2025 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 1/13/2025 | Partial Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 1/21/2025 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 1/24/2025 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 2/19/2025 | Approved | FREDDIE RIVERA |
| Final | 2/19/2025 | Partial Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 2/19/2025 | Approved | FREDDIE RIVERA |
| Green Building Final | 2/19/2025 | Approved | FREDDIE RIVERA |
| METHANE-Barrier | 2/19/2025 | Approved | FREDDIE RIVERA |
| METHANE-Subgrade | 2/19/2025 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 2/19/2025 | SGSOV Approved | FREDDIE RIVERA |
| Smoke Detectors | 2/19/2025 | Approved | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 2/19/2025 | Approved | FREDDIE RIVERA |
| Final | 2/27/2025 | OK to Issue CofO | FREDDIE RIVERA |