1663-1665 W 25TH ST 90007
Certificate Information: 1663-1665 W 25TH ST 90007
- Application / Permit
- 21014-10000-05285
- Plan Check / Job No.
- B21LA19760
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New addition to rear of building and convert into Attached ADU per ordinance and LAMC 12.22 A33(c)&(d). "COMPLY WITH DEPARTMENT ORDER effective date 07/30/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". CEIS Case Number is 922549.
- Permit Issued
- Issued on 6/13/2024
- Issuing Office
- Metro
- Current Status
- Issued on 6/13/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2021 | LUKE GONZALES |
| Corrections Issued | 12/17/2021 | LUKE GONZALES |
| Applicant returned to address corrections | 12/17/2021 | LUKE GONZALES |
| Applicant returned to address corrections | 12/27/2021 | LUKE GONZALES |
| Building Plans Picked Up | 12/27/2021 | APPLICANT |
| Applicant returned to address corrections | 4/26/2023 | DANIEL SANJUAN |
| Applicant returned to address corrections | 6/27/2023 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 8/14/2023 | ZAW HAN |
| Plan Check Approved | 6/4/2024 | ALEXANDER JOO |
| Issued | 6/13/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/22/2022 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 2/22/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/23/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 2/23/2022 | JEANETTE VONG |
| CPC | Cleared | 8/15/2022 | RYAN LY |
| HPOZ | Cleared | 3/17/2023 | JONATHAN KAPLAN |
| ZI | Cleared | 4/11/2023 | CLAUDE GOODING |
| CPC | Cleared | 6/27/2023 | LOUIS ORTEGA |
| ZI | Cleared | 6/27/2023 | LOUIS ORTEGA |
| HPOZ | Cleared | 7/3/2023 | JONATHAN KAPLAN |
| Low Impact Development (LID) | Cleared | 5/20/2024 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 5/30/2024 | JILVER MAZARIEGOS |
| Sewer availability | Cleared | 5/30/2024 | JILVER MAZARIEGOS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| JOHN PARKER, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICHAEL SERETTI, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| HECTOR RODRIGUEZ, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| BRUCE TODD, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAVIER RAMOS SR, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIAN PODPORA, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/2/2024 | Approved | MICHAEL SERETTI |
| METHANE-Barrier | 8/2/2024 | Approved | MICHAEL SERETTI |
| METHANE-Subgrade | 8/2/2024 | Approved | MICHAEL SERETTI |
| BUILDING-Rough-Frame | 8/23/2024 | Not Ready for Inspection | MICHAEL SERETTI |
| Green Building Rough | 8/23/2024 | Not Ready for Inspection | MICHAEL SERETTI |
| Wood Frame | 8/23/2024 | Partial Approval | MICHAEL SERETTI |
| ELECTRICAL-Rough | 1/23/2025 | Approved | MICHAEL SERETTI |
| Insulation | 1/23/2025 | Approved | MICHAEL SERETTI |
| Drywall Nailing | 1/28/2025 | Approved | JOHN PARKER |
| BUILDING-Rough-Frame | 3/11/2025 | Approved | MICHAEL SERETTI |
| Final | 3/11/2025 | Not Ready for Inspection | MICHAEL SERETTI |
| Green Building Final | 3/11/2025 | Not Ready for Inspection | MICHAEL SERETTI |
| Green Building Rough | 3/11/2025 | Approved | MICHAEL SERETTI |
| METHANE-Final | 3/11/2025 | Not Ready for Inspection | MICHAEL SERETTI |
| SGSOV-Seismic Gas S/O Valve | 3/11/2025 | SGSOV Not Ready | MICHAEL SERETTI |
| Smoke Detectors | 3/11/2025 | Not Ready for Inspection | MICHAEL SERETTI |