1836 S HI POINT ST 90035
Certificate Information: 1836 S HI POINT ST 90035
- Application / Permit
- 21014-10000-05265
- Plan Check / Job No.
- B21LA19673
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND REMODEL OF EXISTING SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 1/28/2022
- Issuing Office
- Current Status
- CofO Issued on 9/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/26/2021 | DANIEL SANJUAN |
| Corrections Issued | 10/26/2021 | DANIEL SANJUAN |
| Applicant returned to address corrections | 1/1/2022 | KHUONG TRUONG |
| Plan Check Approved | 1/12/2022 | SINA KHOSRAVI |
| Issued | 1/28/2022 | APPLICANT |
| Building Plans Picked Up | 2/1/2022 | APPLICANT |
| CofO in Progress | 8/25/2023 | JOSE AVILA |
| Permit Finaled | 9/5/2023 | DEROLD HAUFF |
| CofO Issued | 9/5/2023 | DEROLD HAUFF |
| Permit Finaled | 9/5/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 12/20/2021 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 12/20/2021 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 12/21/2021 | ABEL CASILLAS |
Contact Information
| Contractor | Builders & Son'S Inc; Lic. No.: 961171-B | 8720 VENICE BLVD STE 208 LOS ANGELES, CA 90034 |
| Engineer | Hoerner,, John Brent; Lic. No.: S2145 | 24024 VIA CANDELA VALENCIA, CA 91355 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/11/2022 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 5/19/2022 | Corrections Issued | JOSE AVILA |
| Special/Order Compliance | 6/8/2022 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 6/13/2022 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 12/1/2022 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 12/1/2022 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 12/1/2022 | Conditional Approval | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 12/8/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 12/14/2022 | Approved | JOSE AVILA |
| Green Building Rough | 12/14/2022 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 12/20/2022 | Corrections Issued | JOSE AVILA |
| Shower Pan | 12/20/2022 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 1/3/2023 | Partial Approval | JOSE AVILA |
| Drywall Nailing | 1/17/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 1/17/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 7/5/2023 | Corrections Issued | JOSE AVILA |
| Service/Power Release | 7/5/2023 | Approved | JOSE AVILA |
| HVAC-Final | 7/11/2023 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 7/11/2023 | Corrections Issued | JOSE AVILA |
| Final | 8/25/2023 | OK to Issue CofO | JOSE AVILA |
| Footing/Foundation/Slab | 8/25/2023 | Approved | JOSE AVILA |
| Green Building Final | 8/25/2023 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 8/25/2023 | SGSOV Approved | JOSE AVILA |
| Service/Power Release | 8/25/2023 | Approved | JOSE AVILA |
| Smoke Detectors | 8/25/2023 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 8/28/2023 | Approved | JOSE AVILA |
| Green Building Final | 8/28/2023 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 8/28/2023 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 8/28/2023 | Approved | JOSE AVILA |