1824 S STEARNS DR 90035

Certificate Information: 1824 S STEARNS DR 90035

Application / Permit
21014-10000-05229
Plan Check / Job No.
B21LA19522
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 1-STORY ADDITION AND INTERIOR REMODEL TO (E) 1-STORY SINGLE FAMILY DWELLING.
Permit Issued
Issued on 1/19/2022
Issuing Office
Current Status
CofO Corrected on 1/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/18/2021 APPLICANT
Assigned to Plan Check Engineer 11/4/2021 DANIEL YIP
Corrections Issued 11/9/2021 DANIEL YIP
Quality Review Completed 11/18/2021 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 11/22/2021 APPLICANT
Applicant returned to address corrections 12/27/2021 DANIEL YIP
Plan Check Approved 1/12/2022 DANIEL YIP
Issued 1/19/2022 APPLICANT
CofO in Progress 6/30/2022 JOSE AVILA
CofO Issued-Status Void 7/9/2022 DEROLD HAUFF
Permit Finaled-Status Void 7/9/2022 DEROLD HAUFF
Re-Activate Permit 7/12/2022 DEROLD HAUFF
CofO Corrected 1/30/2023 DEROLD HAUFF
Permit Finaled 1/30/2023 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 11/17/2021 KHOUNG LE
Eng Process Fee Ord 176,300 Cleared 11/18/2021 KHOUNG LE
Roof/Waste drainage to street Cleared 12/30/2021 THAN WIN

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/25/2022 Corrections Issued JOSE AVILA
Deputy Reinf. Concrete 1/26/2022 Conditional Approval JOSE AVILA
Footing/Foundation/Slab 2/7/2022 Approved JOSE AVILA
Deputy Reinf. Concrete 2/8/2022 Partial Approval RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 2/10/2022 Corrections Issued JOSE AVILA
PLUMBING-Rough 2/10/2022 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 2/15/2022 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 3/7/2022 Approved JOSE AVILA
ELECTRICAL-Rough 3/14/2022 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 3/14/2022 Corrections Issued JOSE AVILA
PLUMBING-Rough 3/14/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 3/16/2022 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 3/16/2022 Approved JOSE AVILA
HVAC-Rough 3/16/2022 Not Ready for Inspection JOSE AVILA
PLUMBING-Rough 3/16/2022 Approved JOSE AVILA
Shower Pan 3/18/2022 Corrections Issued JOSE AVILA
HVAC-Rough 3/21/2022 Approved JOSE AVILA
Wood Frame 3/21/2022 Approved JOSE AVILA
Interior/Exterior Lathing 3/22/2022 Approved JOSE AVILA
Insulation 4/4/2022 Approved JOSE AVILA
Drywall Nailing 4/7/2022 Partial Approval JOSE AVILA
Green Building Rough 4/7/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 5/11/2022 Approved JOSE AVILA
Drywall Nailing 5/11/2022 Approved JOSE AVILA
ELECTRICAL-Final 5/11/2022 Approved JOSE AVILA
Final 5/11/2022 Corrections Issued JOSE AVILA
Green Building Final 5/11/2022 Approved JOSE AVILA
HVAC-Final 5/11/2022 Approved JOSE AVILA
PLUMBING-Final 5/11/2022 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 5/11/2022 SGSOV Approved JOSE AVILA
Smoke Detectors 5/11/2022 Approved JOSE AVILA
ELECTRICAL-Final 5/18/2022 Approved JOSE AVILA
Final 5/18/2022 Corrections Issued JOSE AVILA
HVAC-Final 5/18/2022 Approved JOSE AVILA
PLUMBING-Final 5/18/2022 Approved JOSE AVILA
Service/Power Release 5/18/2022 Approved JOSE AVILA
Final 6/30/2022 OK to Issue CofO JOSE AVILA