665 S MCCADDEN PL 90005

Certificate Information: 665 S MCCADDEN PL 90005

Application / Permit
21014-10000-05200
Plan Check / Job No.
B21LA19437
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. ADDITION TO EXISTING SFD
Permit Issued
Issued on 6/14/2022
Issuing Office
Metro
Current Status
CofO Issued on 9/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/19/2021 APPLICANT
Assigned to Plan Check Engineer 11/18/2021 CRYSTEL MAALOUF
Corrections Issued 12/7/2021 CRYSTEL MAALOUF
Quality Review Completed 12/14/2021 MICHAEL PEREZ
Applicant returned to address corrections 1/12/2022 CRYSTEL MAALOUF
Applicant returned to address corrections 2/9/2022 CRYSTEL MAALOUF
Applicant returned to address corrections 3/29/2022 CRYSTEL MAALOUF
Applicant returned to address corrections 5/3/2022 CRYSTEL MAALOUF
Applicant returned to address corrections 5/11/2022 CRYSTEL MAALOUF
Plan Check Approved 5/17/2022 CRYSTEL MAALOUF
Issued 6/14/2022 APPLICANT
CofO in Progress 7/25/2024 RONNIE MINDANAO
CofO Issued 9/7/2024 RUBEN SALAS
Permit Finaled 9/7/2024 RUBEN SALAS

Permit Application Clearance Information

CPC Cleared 1/26/2022 DANIEL CORONADO
CPC Cleared 1/26/2022 DANIEL CORONADO
Miscellaneous Cleared 1/26/2022 DANIEL CORONADO
HPOZ Cleared 2/14/2022 SUKI GERSHENHORN
Miscellaneous Cleared 2/14/2022 SUKI GERSHENHORN
Specific Plan Cleared 3/2/2022 ADRINEH MELKONIAN
Low Impact Development Cleared 4/1/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 4/5/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 4/18/2022 STEVE MELGAR
Sewer availability Cleared 4/18/2022 STEVE MELGAR

Contact Information

Architect Song,, Byung K; Lic. No.: C25500 8433 DARBY AVE      NORTHRIDGE, CA 91325
Architect Song,, Byung K; Lic. No.: NA25500       ,
Contractor Owner-Builder       ,
Engineer Kim,, Eui S; Lic. No.: S5138 37325 8TH AVE S      FEDERAL WAY, WA 98003

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/31/2023 Approved RICHARD DOCKUS
Excavation/Setback/Form/Re-Bar 8/3/2023 Corrections Issued STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 8/8/2023 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 9/5/2023 Approved ROY SPAULDING
Wood Frame 9/5/2023 Corrections Issued ROY SPAULDING
ELECTRICAL-Rough 9/11/2023 Corrections Issued JUSTIN HAWLEY
PLUMBING-Rough 9/11/2023 Approved JUSTIN HAWLEY
Wood Frame 10/19/2023 Partial Approval RICHARD DOCKUS
Wood Frame 11/17/2023 Not Ready for Inspection RICHARD DOCKUS
ELECTRICAL-Rough 12/19/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Wood Frame 12/19/2023 Partial Approval JOAQUIN GREENOUGH
ELECTRICAL-Rough 12/21/2023 Corrections Issued JEFFREY MEAD
PLUMBING-Rough 12/21/2023 Corrections Issued JEFFREY MEAD
Wood Frame 12/21/2023 Not Ready for Inspection JEFFREY MEAD
Interior/Exterior Lathing 1/4/2024 Partial Approval RICHARD DOCKUS
ELECTRICAL-Rough 1/16/2024 Approved RICHARD DOCKUS
PLUMBING-Rough 1/16/2024 Approved RICHARD DOCKUS
HVAC-Rough 1/31/2024 Not Ready for Inspection RICHARD DOCKUS
HVAC-Rough 2/2/2024 Approved RICHARD DOCKUS
HVAC-Rough 2/7/2024 Approved AMIR NAZARIAN
Wood Frame 2/7/2024 Approved AMIR NAZARIAN
Insulation 2/12/2024 Corrections Issued RICHARD DOCKUS
Insulation 2/15/2024 Approved AMIR NAZARIAN
Drywall Nailing 2/22/2024 Approved RICHARD DOCKUS
Shower Pan 3/6/2024 Corrections Issued JOAQUIN GREENOUGH
Shower Pan 3/14/2024 Approved RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 6/14/2024 SGSOV Not Ready RICHARD DOCKUS
BUILDING-Rough-Frame 6/20/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Final 6/20/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 6/20/2024 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Barrier 6/20/2024 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Final 6/20/2024 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Rough 6/20/2024 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Subgrade 6/20/2024 Not Ready for Inspection JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 6/20/2024 SGSOV Not Ready JOAQUIN GREENOUGH
Smoke Detectors 6/20/2024 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 7/11/2024 Approved RONNIE MINDANAO
Final 7/11/2024 Corrections Issued RONNIE MINDANAO
Footing/Foundation/Slab 7/11/2024 Approved RONNIE MINDANAO
METHANE-Barrier 7/11/2024 Approved RONNIE MINDANAO
METHANE-Final 7/11/2024 Approved RONNIE MINDANAO
METHANE-Rough 7/11/2024 Approved RONNIE MINDANAO
METHANE-Subgrade 7/11/2024 Approved RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 7/11/2024 SGSOV Approved RONNIE MINDANAO
Smoke Detectors 7/11/2024 Approved RONNIE MINDANAO
ELECTRICAL-Final 7/24/2024 Approved RONNIE MINDANAO
Final 7/24/2024 OK to Issue CofO RONNIE MINDANAO
HVAC-Final 7/24/2024 Approved RONNIE MINDANAO
PLUMBING-Final 7/24/2024 Approved RONNIE MINDANAO