4816-4818 S 6TH AVE 90043
Certificate Information: 4816-4818 S 6TH AVE 90043
- Application / Permit
- 21014-10000-05163
- Plan Check / Job No.
- B21LA19276
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2 STORY ADDITION, INTERIOR AND EXTERIOR MAJOR REMODEL AND CONVERT 1ST FLOOR TO ADU (964 SF) PER 12.22 A33 C & E TO EXISTING 2 STORY SFD, SEE COMMENTS COMPLY WITH DEPARTMENT ORDER EFFECITVE DATE 5/14/22. PERMIT WILL EXPIRE 30 DAYS FROM ISSUACE DATE. (ZONING REQUIREMENTS FOR PREVIOUS UNPERMITTED ADDITION FOR PLANE BREAK AND ENCROACHMENT PLANE OF BUILDING HAVE BEEN WAIVED BY CITY PLANNER N. MCCOY)
- Permit Issued
- Issued on 10/6/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2021 | STARR CHEN |
| Corrections Issued | 11/24/2021 | STARR CHEN |
| Quality Review Completed | 12/7/2021 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 12/9/2021 | APPLICANT |
| Applicant returned to address corrections | 1/28/2022 | STARR CHEN |
| Applicant returned to address corrections | 2/22/2022 | STARR CHEN |
| Applicant returned to address corrections | 3/8/2022 | STARR CHEN |
| Applicant returned to address corrections | 3/25/2022 | STARR CHEN |
| Applicant returned to address corrections | 4/7/2022 | STARR CHEN |
| Applicant returned to address corrections | 4/13/2022 | STARR CHEN |
| Applicant returned to address corrections | 4/14/2022 | STARR CHEN |
| Applicant returned to address corrections | 5/17/2022 | STARR CHEN |
| Applicant returned to address corrections | 7/21/2022 | STARR CHEN |
| Applicant returned to address corrections | 9/7/2022 | STARR CHEN |
| Plan Check Approved | 10/5/2022 | STARR CHEN |
| Issued | 10/6/2022 | APPLICANT |
| CofO in Progress | 1/26/2024 | ANTHONY EGSON |
| Permit Finaled | 2/1/2024 | DEROLD HAUFF |
| CofO Issued | 2/1/2024 | DEROLD HAUFF |
| Permit Finaled | 2/1/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Miscellaneous | Cleared | 7/8/2022 | NOAH MCCOY |
| Miscellaneous | Cleared | 7/13/2022 | NOAH MCCOY |
| Address approval | Cleared | 7/23/2022 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 7/23/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 7/23/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 7/25/2022 | JEANETTE VONG |
| Hydrant and Access approval | Cleared | 9/24/2022 | GILBERT URREA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Benavides,, Jose Alexander; Lic. No.: C72968 | 644 N POPLAR ST UNIT B ORANGE, CA 92868 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 4/25/2022 | Not Ready for Inspection | HORACE FULTZ |
| BUILDING-Rough-Frame | 2/14/2023 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Rough | 2/14/2023 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 3/9/2023 | Partial Approval | ANTHONY EGSON |
| HVAC-Rough | 3/16/2023 | Partial Approval | ANTHONY EGSON |
| Underground Mechanical | 3/16/2023 | Partial Approval | ANTHONY EGSON |
| ELECTRICAL-Rough | 3/20/2023 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 3/31/2023 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 4/10/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 4/20/2023 | Approved | ANTHONY EGSON |
| Special/Order Compliance | 4/20/2023 | Partial Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2023 | Partial Inspection | ANTHONY EGSON |
| Green Building Rough | 4/26/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Deputy Wood Construction | 5/16/2023 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 5/22/2023 | Partial Approval | ANTHONY EGSON |
| Green Building Rough | 5/22/2023 | Approved | ANTHONY EGSON |
| Insulation | 5/22/2023 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 6/23/2023 | Approved | ANTHONY EGSON |
| Drywall Nailing | 7/10/2023 | Partial Approval | CHARLES BOGHOSKHAN |
| Drywall Nailing | 8/1/2023 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 12/6/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 12/6/2023 | Approved | ANTHONY EGSON |
| Final | 12/6/2023 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 12/6/2023 | Approved | ANTHONY EGSON |
| Green Building Final | 12/6/2023 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 12/6/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 12/6/2023 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 12/6/2023 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 12/6/2023 | Approved | ANTHONY EGSON |
| Final | 12/29/2023 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 12/29/2023 | Approved | STUART CHAPMAN |
| Final | 1/10/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Service/Power Release | 1/25/2024 | Approved | ANTHONY EGSON |
| Final | 1/26/2024 | OK to Issue CofO | ANTHONY EGSON |