1041 1/2 W 57TH ST 90037
Certificate Information: 1041 1/2 W 57TH ST 90037
- Application / Permit
- 21014-10000-05159
- Plan Check / Job No.
- B21LA19259
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 24'-6"X31' 2-STORY BUILDING, INCLUDING A 2ND FLOOR ADU 558 SF ON TOP OF A 3-CAR GARAGE 468 SF. ADU PER LAMC 12.22 A.33(C) & (D).
- Permit Issued
- Issued on 12/8/2022
- Issuing Office
- Metro
- Current Status
- Issued on 12/8/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2021 | CHUNG-WEN CHUANG |
| Corrections Issued | 12/14/2021 | CHUNG-WEN CHUANG |
| Quality Review Completed | 12/22/2021 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 1/3/2022 | APPLICANT |
| Applicant returned to address corrections | 3/31/2022 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 4/6/2022 | CHUNG-WEN CHUANG |
| Plan Check Approved | 9/13/2022 | CHUNG-WEN CHUANG |
| Issued | 12/8/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/23/2021 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 1/6/2022 | JEANETTE VONG |
| Construction near power lines | Cleared | 2/17/2022 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 4/6/2022 | RUEL COLE |
| Tenant Habitability Plan | Cleared | 6/15/2022 | RICARDO BOHORQUEZ |
| Permit | Cleared | 7/8/2022 | JEANETTE VONG |
| Low Impact Development | Cleared | 8/15/2022 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 8/16/2022 | STEVE MELGAR |
Contact Information
| Contractor | Impact Construction Incorporated; Lic. No.: 671828-B | PO BOX 20286 FOUNTAIN VALLEY, CA 92728 |
| Engineer | Wu,, Harold Ping-Hung; Lic. No.: C35693 | 1168 SAN GABRIEL BLVD NO N ROSEMEAD, CA 91770 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/13/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 12/13/2022 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 12/16/2022 | Partial Approval | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 12/27/2022 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 12/27/2022 | Not Ready for Inspection | SABAS ALONSO |
| Underground Mechanical | 12/27/2022 | Partial Approval | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 1/24/2023 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 1/24/2023 | Not Ready for Inspection | SABAS ALONSO |
| Underground Mechanical | 1/24/2023 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2023 | Partial Approval | SCOTT FINNILA |
| PLUMBING-Rough | 1/26/2023 | Partial Inspection | SCOTT FINNILA |
| Underground Mechanical | 1/26/2023 | Partial Inspection | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 2/1/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 2/1/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 2/8/2023 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2023 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2023 | Partial Approval | SABAS ALONSO |
| HVAC-Rough | 4/26/2023 | Approved | SABAS ALONSO |
| Deputy Wood Construction | 5/5/2023 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2023 | Approved | SABAS ALONSO |
| Underground Mechanical | 5/15/2023 | Partial Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 5/22/2023 | Approved | SABAS ALONSO |
| Green Building Rough | 5/22/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 5/22/2023 | Approved | SABAS ALONSO |
| Underground Mechanical | 5/22/2023 | Approved | SABAS ALONSO |
| Insulation | 5/31/2023 | Conditional Approval | BRENDAN MORELLI |
| Interior/Exterior Lathing | 5/31/2023 | Partial Approval | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 7/14/2023 | Approved | SABAS ALONSO |
| Drywall Nailing | 7/14/2023 | Approved | SABAS ALONSO |
| Insulation | 7/14/2023 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 7/14/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 10/26/2023 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 10/31/2023 | Corrections Issued | CRAIG DAVIS |
| Sewer | 11/1/2023 | Approved | ENRIQUE MIRELES |
| Shower Pan | 12/15/2023 | Approved | JOAQUIN GREENOUGH |
| Pre-Inspection | 7/30/2024 | Corrections Issued | DAVID FEILER |
| Pre-Inspection | 8/15/2024 | Corrections Issued | JOSE MACIAS |
| Interior/Exterior Lathing | 9/4/2024 | Partial Approval | CRAIG DAVIS |
| Final | 10/11/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| Green Building Final | 10/11/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 10/11/2024 | SGSOV Not Ready | JOHN QUINTANILLA |
| Service/Power Release | 10/11/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| Smoke Detectors | 10/11/2024 | Conditional Approval | JOHN QUINTANILLA |
| Final | 11/6/2024 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Final | 11/6/2024 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 11/6/2024 | SGSOV Not Ready | SABAS ALONSO |
| Service/Power Release | 11/6/2024 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 11/6/2024 | Approved | SABAS ALONSO |
| Pre-Inspection | 11/12/2024 | Corrections Issued | CRAIG DAVIS |
| Protected Tree Letter | 11/12/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Final | 4/23/2025 | Corrections Issued | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 4/23/2025 | SGSOV Not Ready | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 9/24/2025 | SGSOV Not Ready | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 10/9/2025 | Approved | SABAS ALONSO |
| PLUMBING-Final | 10/9/2025 | Approved | SABAS ALONSO |
| Final | 5/11/2026 | Not Ready for Inspection | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 5/11/2026 | SGSOV Not Ready | LUIS CASTRO |
| Service/Power Release | 5/11/2026 | Not Ready for Inspection | LUIS CASTRO |
| Final | 6/26/2026 | Not Ready for Inspection | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 6/26/2026 | SGSOV Approved | BARRY HACHE |
| Service/Power Release | 6/26/2026 | Not Ready for Inspection | BARRY HACHE |