ADD MASTER BEDROOM, MASTER BATHROOM AND CLOSET AT THE REAR OF THE RESIDENCE 405 SQFT.
Permit Issued
Issued on 3/10/2022
Issuing Office
Current Status
CofO Issued on 2/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/20/2021 APPLICANT
Assigned to Plan Check Engineer 10/26/2021 RAHEL BEYENE
Corrections Issued 10/27/2021 RAHEL BEYENE
Plan Check Approved 1/28/2022 ADAM HEGAZI
Issued 3/10/2022 APPLICANT
Building Plans Picked Up 3/15/2022 APPLICANT
CofO in Progress 11/18/2022 TROY SANDERS
Permit Finaled 2/18/2023 DANIEL ORRANTE
CofO Issued 2/18/2023 DANIEL ORRANTE
Permit Finaled 2/18/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/4/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 1/4/2022 CARLOS AGUILERA
Sewer availability Cleared 1/4/2022 CARLOS AGUILERA
Grading Pre-Inspection Cleared 1/11/2022 VASIL MIHALEV

Contact Information

Contractor American Home Improvement Inc; Lic. No.: 835537-B 20335 VENTURA BLVD #422      WOODLAND HILLS, CA 91364

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/22/2022 Approved TROY SANDERS
Deputy Drilled-In Anchors 4/14/2022 Conditional Approval KRISTEN CAUSEY
BUILDING-Rough-Frame 4/15/2022 Not Ready for Inspection DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 4/15/2022 Approved DAVID SCANTLIN
Green Building Rough 4/15/2022 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 4/27/2022 Approved TROY SANDERS
ELECTRICAL-Rough 4/27/2022 Approved TROY SANDERS
Green Building Rough 4/27/2022 Not Ready for Inspection TROY SANDERS
PLUMBING-Rough 4/27/2022 Approved TROY SANDERS
Green Building Rough 5/5/2022 Approved TROY SANDERS
Insulation 5/5/2022 Approved TROY SANDERS
Interior/Exterior Lathing 5/5/2022 Partial Approval TROY SANDERS
Drywall Nailing 5/11/2022 Approved TROY SANDERS
Interior/Exterior Lathing 5/18/2022 Approved TROY SANDERS
Shower Pan 5/18/2022 Approved TROY SANDERS
Final 11/9/2022 Corrections Issued TROY SANDERS
Green Building Final 11/9/2022 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 11/9/2022 SGSOV Approved TROY SANDERS
Smoke Detectors 11/9/2022 Approved TROY SANDERS
Final 11/17/2022 OK to Issue CofO TROY SANDERS
HVAC-Final 11/17/2022 Approved TROY SANDERS