1907 W MELLON AVE 90039
Certificate Information: 1907 W MELLON AVE 90039
- Application / Permit
- 21014-10000-05127
- Plan Check / Job No.
- B21LA19031
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO EXISTING 1-STORY SINGLE-FAMILY DWELLING, INCLUDING MINOR REMODEL TO INTERIOR OF EXISTING DWELLING, AND NEW WINDOWS AND EXTERIOR DOORS THROUGHOUT.
- Permit Issued
- Issued on 10/2/2023
- Issuing Office
- Valley
- Current Status
- Issued on 10/2/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2021 | SERGIO GUTIERREZ |
| Corrections Issued | 11/19/2021 | SERGIO GUTIERREZ |
| Quality Review Completed | 12/2/2021 | FARUK SEZER |
| Building Plans Picked Up | 12/7/2021 | APPLICANT |
| Applicant returned to address corrections | 4/5/2023 | SERGIO GUTIERREZ |
| Plan Check Approved | 7/5/2023 | SERGIO GUTIERREZ |
| Issued | 10/2/2023 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 3/13/2022 | DWIGHT SANKEY |
| Sewer availability | Cleared | 6/16/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 6/28/2022 | CHRISTOPHER ROCHA |
| Low Impact Development | Cleared | 6/22/2023 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 6/25/2023 | AHMED AMARRAGY |
Contact Information
| Architect | Grant,, Thurman; Lic. No.: C30285 | 846 S. BROADWAY #501 LOS ANGELES, CA 90014 |
| Contractor | Sweven Remodel Inc; Lic. No.: 1052069-B | 6150 CANOGA AVENUE #231 WOODLAND HILLS, CA 91367 |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/4/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 10/4/2023 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 10/16/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 10/24/2023 | Corrections Issued | THOMAS LOGRASSO |
| Deputy Steel/Welding | 10/30/2023 | Conditional Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2023 | Approved | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 11/8/2023 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2023 | Partial Approval | THOMAS LOGRASSO |
| Deputy Steel/Welding | 12/18/2023 | Conditional Approval | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 1/31/2024 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2024 | Corrections Issued | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2024 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 2/13/2024 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 3/27/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 5/8/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 5/8/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 5/22/2024 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2024 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 5/22/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 9/17/2024 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 10/8/2024 | Corrections Issued | JOHN QUINTANILLA |
| Green Building Rough | 10/8/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| MERV13>=Rough | 10/8/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| Rough-Elec/Plmb/HVAC | 10/8/2024 | Corrections Issued | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 10/15/2024 | Corrections Issued | LUIS CASTRO |
| Green Building Rough | 10/15/2024 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Rough | 10/15/2024 | Approved | LUIS CASTRO |
| MERV13>=Rough | 10/15/2024 | Not Ready for Inspection | LUIS CASTRO |
| BUILDING-Rough-Frame | 10/17/2024 | Approved | LUIS CASTRO |
| Green Building Rough | 10/17/2024 | Approved | LUIS CASTRO |
| HVAC-Rough | 10/17/2024 | Approved | LUIS CASTRO |
| MERV13>=Rough | 10/17/2024 | Approved | LUIS CASTRO |
| Insulation | 10/22/2024 | Partial Approval | LUIS CASTRO |
| Insulation | 10/25/2024 | Approved | NICHOLAS LOPEZ |
| Drywall Nailing | 10/30/2024 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 11/22/2024 | Partial Approval | NICHOLAS LOPEZ |
| Shower Pan | 11/22/2024 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 12/17/2024 | Partial Approval | JOSH MEISTER |
| Final | 1/6/2026 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 1/6/2026 | Corrections Issued | HAMIK HARTOUNIAN |
| MERV13>=Final | 1/6/2026 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 1/6/2026 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 1/6/2026 | Approved | HAMIK HARTOUNIAN |