7228 N CAMELLIA AVE 91605

Certificate Information: 7228 N CAMELLIA AVE 91605

Application / Permit
21014-10000-05119
Plan Check / Job No.
B21LA19015
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED (E) GARAGE CONVERTED 360 SF AND 494 SF ADDITION TO (N) DETACHED ADU PER 12.22 A.33 (c)-(d).
Permit Issued
Issued on 8/1/2022
Issuing Office
Metro
Current Status
CofO Issued on 7/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/19/2021 APPLICANT
Assigned to Plan Check Engineer 10/25/2021 ADAM HEGAZI
Corrections Issued 10/25/2021 ADAM HEGAZI
Applicant returned to address corrections 4/5/2022 RICARDO RAMIREZ
Applicant returned to address corrections 4/28/2022 FERNANDO FLORES
Building Plans Picked Up 4/29/2022 APPLICANT
Plan Check Approved 6/16/2022 KHUONG TRUONG
Issued 8/1/2022 APPLICANT
CofO in Progress 7/12/2023 JENNIFER RABUCHIN
Permit Finaled 7/19/2023 MICHAEL SMITH
CofO Issued 7/19/2023 MICHAEL SMITH
Permit Finaled 7/19/2023 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 3/11/2022 RIDWAN HARDY
Address approval Cleared 5/20/2022 JEANETTE VONG
Roof/Waste drainage to street Cleared 5/20/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 5/24/2022 JEANETTE VONG
Sewer availability Cleared 5/24/2022 JEANETTE VONG

Contact Information

Contractor Bethel Construction Co; Lic. No.: 875157-B 937 S IMPERIAL AVE      EL CENTRO, CA 92243
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/15/2022 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 8/15/2022 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 8/22/2022 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 8/22/2022 Not Ready for Inspection JOHN HAYES
Pre-Inspection 8/22/2022 Not Ready for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 8/25/2022 Corrections Issued CALEB MEISTER
PLUMBING-Rough 8/25/2022 Corrections Issued CALEB MEISTER
Deputy Drilled-In Anchors 8/26/2022 Conditional Approval CALEB MEISTER
Excavation/Setback/Form/Re-Bar 9/2/2022 Approved JOHN HAYES
Underground Mechanical 9/2/2022 Approved JOHN HAYES
Gas Test 11/23/2022 Not Ready for Inspection THOMAS FINNILA
Rough-Elec/Plmb/HVAC 11/23/2022 Not Ready for Inspection THOMAS FINNILA
Wood Frame 11/23/2022 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/5/2022 Corrections Issued CHRISTOPHE COCHRAN
Rough-Elec/Plmb/HVAC 12/5/2022 Partial Approval CHRISTOPHE COCHRAN
Sewer 12/5/2022 Approved CHRISTOPHE COCHRAN
Wood Frame 12/12/2022 Partial Approval JOHN COLEMAN
ELECTRICAL-Rough 12/19/2022 Approved JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 12/19/2022 Approved JOHN COLEMAN
PLUMBING-Rough 12/19/2022 Approved JOHN COLEMAN
Insulation 12/27/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Insulation 1/3/2023 Approved JENNIFER RABUCHIN
Drywall Nailing 1/10/2023 Approved JOHN HAYES
Green Building Rough 1/10/2023 Approved JOHN HAYES
BUILDING-Rough-Frame 2/27/2023 Approved JOHN HAYES
Final 2/27/2023 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 2/27/2023 Approved JOHN HAYES
Green Building Final 2/27/2023 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 2/27/2023 SGSOV Approved JOHN HAYES
Smoke Detectors 2/27/2023 Approved JOHN HAYES
Final 3/16/2023 Corrections Issued JOHN HAYES
Final 6/7/2023 Corrections Issued JOHN HAYES
ELECTRICAL-Final 7/11/2023 Approved JENNIFER RABUCHIN
Final 7/11/2023 OK to Issue CofO JENNIFER RABUCHIN
PLUMBING-Final 7/11/2023 Approved JENNIFER RABUCHIN