1328 E 21ST ST 1-11 90011

Certificate Information: 1328 E 21ST ST 1-11 90011

Application / Permit
21014-10000-05109
Plan Check / Job No.
B21LA19002
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
(N) ADDITION OF 240 S.F. TO CREATE (N) ADU OF 669 SF IN EXISTING 2 STORY APARTMENT BUILDING. (Attached ADU per Ordinance LAMC 12.22 A.33(c) AND (e))
Permit Issued
Issued on 5/30/2023
Issuing Office
Metro
Current Status
CofO Issued on 4/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/8/2021 APPLICANT
Assigned to Plan Check Engineer 10/14/2021 DANIEL SANJUAN
Corrections Issued 10/14/2021 DANIEL SANJUAN
Applicant returned to address corrections 12/30/2021 AUNG SOE
Applicant returned to address corrections 5/3/2022 SHANGQIN XIE
Building Plans Picked Up 5/16/2022 APPLICANT
Plan Check Approved 6/17/2022 AUNG SOE
Issued 5/30/2023 APPLICANT
CofO in Progress 4/9/2026 RAFAEL ESPINOZA
Permit Finaled 4/9/2026 RAFAEL ESPINOZA
CofO Issued 4/9/2026 RAFAEL ESPINOZA
Permit Finaled 4/9/2026 RAFAEL ESPINOZA

Permit Application Clearance Information

Address approval Cleared 12/2/2021 JEANETTE VONG
Address approval Cleared 12/2/2021 JEANETTE VONG
Roof/Waste drainage to street Cleared 12/2/2021 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 12/3/2021 JEANETTE VONG
Sewer availability Cleared 12/3/2021 JEANETTE VONG

Contact Information

Contractor Tadeo General Contractor; Lic. No.: 984125-B 8802 OAK STREET      BELLFLOWER, CA 90706
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/14/2023 Approved JAMES POWERS
Pre-Inspection 4/15/2024 Corrections Issued RONALD JIMENEZ
Green Building Rough 5/15/2024 Not Ready for Inspection ALFREDO LOPEZ
Wood Frame 5/15/2024 Partial Inspection ALFREDO LOPEZ
Green Building Rough 5/22/2024 Not Ready for Inspection ALFREDO LOPEZ
Wood Frame 5/22/2024 Not Ready for Inspection ALFREDO LOPEZ
Pre-Inspection 5/24/2024 Not Ready for Inspection ALFREDO LOPEZ
Green Building Rough 5/29/2024 Not Ready for Inspection ALFREDO LOPEZ
Wood Frame 5/29/2024 Not Ready for Inspection ALFREDO LOPEZ
Insulation 8/7/2024 Not Ready for Inspection ALFREDO LOPEZ
Green Building Rough 2/19/2025 Not Ready for Inspection ALFREDO LOPEZ
Insulation 2/19/2025 Not Ready for Inspection ALFREDO LOPEZ
Pre-Inspection 2/19/2025 Not Ready for Inspection ALFREDO LOPEZ
Wood Frame 2/19/2025 Not Ready for Inspection ALFREDO LOPEZ
Final 12/18/2025 Not Ready for Inspection ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 12/18/2025 SGSOV Not Ready ALFREDO LOPEZ
Drywall Nailing 1/14/2026 Not Ready for Inspection ALFREDO LOPEZ
Final 1/14/2026 Not Ready for Inspection ALFREDO LOPEZ
Footing/Foundation/Slab 1/14/2026 Not Ready for Inspection ALFREDO LOPEZ
Green Building Final 1/14/2026 Approved ALFREDO LOPEZ
Green Building Rough 1/14/2026 Approved ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 1/14/2026 SGSOV Not Ready ALFREDO LOPEZ
Smoke Detectors 1/14/2026 Not Ready for Inspection ALFREDO LOPEZ
Wood Frame 1/14/2026 Not Ready for Inspection ALFREDO LOPEZ
Drywall Nailing 1/23/2026 Not Ready for Inspection DARRYL ARNOLD
Final 1/23/2026 Not Ready for Inspection DARRYL ARNOLD
Footing/Foundation/Slab 1/23/2026 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 1/23/2026 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 1/23/2026 No Access for Inspection DARRYL ARNOLD
Wood Frame 1/23/2026 Not Ready for Inspection DARRYL ARNOLD
Final 2/17/2026 Partial Inspection DARRYL ARNOLD
Drywall Nailing 3/6/2026 Approved DARRYL ARNOLD
Final 3/6/2026 OK to Issue CofO DARRYL ARNOLD
Footing/Foundation/Slab 3/6/2026 Approved DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 3/6/2026 SGSOV Approved DARRYL ARNOLD
Smoke Detectors 3/6/2026 Approved DARRYL ARNOLD
Wood Frame 3/6/2026 Approved DARRYL ARNOLD
Final 3/23/2026 Conditional Approval DARRYL ARNOLD
Final 3/25/2026 Conditional Approval DARRYL ARNOLD