514 E 46TH ST 90011
Certificate Information: 514 E 46TH ST 90011
- Application / Permit
- 21014-10000-05082
- Plan Check / Job No.
- B21LA18919
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING 1 CAR GARAGE (280 SQFT) INTO NEW ADU AND NEW 1 STORY ADDITION. TOTAL ADU AREA (351.50 SQFT).
- Permit Issued
- Issued on 8/1/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/8/2021 | JOSEPH RAFOLS |
| Corrections Issued | 10/8/2021 | JOSEPH RAFOLS |
| Building Plans Picked Up | 10/12/2021 | APPLICANT |
| Plan Check Approved | 7/28/2022 | JOSEPH RAFOLS |
| Issued | 8/1/2022 | APPLICANT |
| CofO in Progress | 7/13/2023 | BRENDAN MORELLI |
| Permit Finaled | 7/23/2023 | DEROLD HAUFF |
| CofO Issued | 7/23/2023 | DEROLD HAUFF |
| Permit Finaled | 7/23/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/15/2022 | CHRISTOPHER ROCHA |
| Roof/Waste drainage to street | Cleared | 3/15/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 3/29/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 3/29/2022 | CHRISTOPHER ROCHA |
| Tenant Habitability Plan | Cleared | 3/31/2022 | RICHARD BRINSON |
| Construction near power lines | Cleared | 4/23/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/7/2022 | Partial Inspection | SHAVONNE ESPINOZA |
| Excavation/Setback/Form/Re-Bar | 10/27/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 10/27/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 11/22/2022 | Corrections Issued | JULIAN AMAYA |
| Footing/Foundation/Slab | 11/22/2022 | Corrections Issued | JULIAN AMAYA |
| PLUMBING-Rough | 11/22/2022 | Corrections Issued | JULIAN AMAYA |
| Underground Mechanical | 11/22/2022 | Corrections Issued | JULIAN AMAYA |
| Excavation/Setback/Form/Re-Bar | 12/5/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 12/5/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Gas Test | 12/5/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 12/5/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Sewer | 12/5/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 12/8/2022 | Approved | JULIAN AMAYA |
| Underground Mechanical | 12/8/2022 | Approved | JULIAN AMAYA |
| BUILDING-Rough-Frame | 1/24/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| Green Building Rough | 1/24/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| Rough-Elec/Plmb/HVAC | 1/24/2023 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Rough | 2/24/2023 | Approved | BRENDAN MORELLI |
| Gas Test | 2/24/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 2/24/2023 | Partial Approval | BRENDAN MORELLI |
| PLUMBING-Rough | 2/24/2023 | Approved | BRENDAN MORELLI |
| Sewer | 2/24/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 3/7/2023 | Approved | BRENDAN MORELLI |
| Green Building Rough | 3/7/2023 | Approved | BRENDAN MORELLI |
| HVAC-Rough | 3/7/2023 | Approved | BRENDAN MORELLI |
| Insulation | 3/15/2023 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 4/5/2023 | Approved | BRENDAN MORELLI |
| Final | 5/9/2023 | Corrections Issued | BRENDAN MORELLI |
| Green Building Final | 5/9/2023 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 5/9/2023 | SGSOV Approved | BRENDAN MORELLI |
| Smoke Detectors | 5/9/2023 | Approved | BRENDAN MORELLI |
| Final | 5/16/2023 | Corrections Issued | BRENDAN MORELLI |
| Final | 7/13/2023 | OK to Issue CofO | BRENDAN MORELLI |