2658 N BEACHWOOD DR 90068
Certificate Information: 2658 N BEACHWOOD DR 90068
- Application / Permit
- 21014-10000-05049
- Plan Check / Job No.
- B21LA18763
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO EXISTING 1-STORY SINGLE FAMILY DWELLING PER WFPP (SEE COMMENT).
- Permit Issued
- Issued on 3/9/2022
- Issuing Office
- Current Status
- CofO Issued on 7/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2021 | ERIC WONG |
| Corrections Issued | 11/6/2021 | ERIC WONG |
| Quality Review Completed | 11/18/2021 | PETER KIM |
| Building Plans Picked Up | 11/23/2021 | APPLICANT |
| Applicant returned to address corrections | 1/21/2022 | ERIC WONG |
| Plan Check Approved | 3/9/2022 | ERIC WONG |
| Issued | 3/9/2022 | APPLICANT |
| CofO in Progress | 7/1/2024 | BRIAN SULLIVAN |
| Permit Finaled | 7/5/2024 | RONALD MYRICK |
| CofO Issued | 7/5/2024 | RONALD MYRICK |
| Permit Finaled | 7/5/2024 | RONALD MYRICK |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 11/30/2021 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 11/30/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2021 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 1/21/2022 | ERIC WONG |
Contact Information
| Architect | Thibodeau,, Robert E; Lic. No.: C25585 | 812 LINCOLN BLVD VENICE, CA 90291 |
| Contractor | Trumpower Design & Development; Lic. No.: 1016132-B | 121 OLD TOPANDA CYN RD TOPANGA, CA 90290 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/30/2022 | Conditional Approval | RUBEN SALAS |
| Footing/Foundation/Slab | 3/31/2022 | Corrections Issued | RUBEN SALAS |
| Footing/Foundation/Slab | 4/5/2022 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 4/11/2022 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 4/11/2022 | Partial Approval | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 4/26/2022 | Conditional Approval | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 4/26/2022 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 4/26/2022 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 5/4/2022 | Corrections Issued | RUBEN SALAS |
| Insulation | 5/4/2022 | Approved | RUBEN SALAS |
| Interior/Exterior Lathing | 5/4/2022 | Partial Approval | RUBEN SALAS |
| Drywall Nailing | 5/6/2022 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 5/6/2022 | Partial Approval | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 1/26/2023 | Approved | JOAQUIN GREENOUGH |
| Final | 1/26/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 1/26/2023 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 1/26/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 2/14/2023 | Corrections Issued | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 2/14/2023 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 2/14/2023 | Approved | BRIAN SULLIVAN |
| Final | 6/28/2024 | OK to Issue CofO | BRIAN SULLIVAN |