1555-1555 3/4 E 106TH ST 90002

Certificate Information: 1555-1555 3/4 E 106TH ST 90002

Application / Permit
21014-10000-05033
Plan Check / Job No.
B21LA18676
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT GARAGE TO ADU PER LAMC 12.22 A.33(c) AND (d) and PER WFPP
Permit Issued
Issued on 4/5/2023
Issuing Office
Metro
Current Status
CofO Issued on 4/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/5/2021 APPLICANT
Assigned to Plan Check Engineer 10/21/2021 CRYSTEL MAALOUF
Corrections Issued 10/27/2021 CRYSTEL MAALOUF
Quality Review Completed 10/28/2021 KEN GILL
Building Plans Picked Up 11/2/2021 APPLICANT
Applicant returned to address corrections 3/16/2022 CRYSTEL MAALOUF
Applicant returned to address corrections 4/13/2022 CRYSTEL MAALOUF
Plan Check Approved 5/2/2022 CRYSTEL MAALOUF
Issued 4/5/2023 APPLICANT
CofO in Progress 4/15/2024 BEN MOLSTAD
CofO Issued 4/15/2024 ANSON MAGLASANG
Permit Finaled 4/15/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 12/7/2021 CINDY QI
Eng Process Fee Ord 176,300 Cleared 12/9/2021 CINDY QI
Sewer availability Cleared 2/3/2022 CINDY QI

Contact Information

Contractor Ebenezer Construction; Lic. No.: 657529-B 9214 MANZANAR AVE      DOWNEY, CA 90240

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/20/2023 Partial Approval JOHN KLARIN
Sewer 9/20/2023 Partial Approval JOHN KLARIN
ELECTRICAL-Rough 11/15/2023 Approved JOHN KLARIN
Gas Test 11/15/2023 Approved JOHN KLARIN
PLUMBING-Rough 11/15/2023 Approved JOHN KLARIN
Wood Frame 11/15/2023 Approved JOHN KLARIN
Insulation 12/1/2023 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 2/22/2024 Approved BEN MOLSTAD
ELECTRICAL-Final 2/22/2024 Corrections Issued BEN MOLSTAD
Final 2/22/2024 Corrections Issued BEN MOLSTAD
Footing/Foundation/Slab 2/22/2024 Approved BEN MOLSTAD
Green Building Final 2/22/2024 Not Ready for Inspection BEN MOLSTAD
Green Building Rough 2/22/2024 Approved BEN MOLSTAD
HVAC-Final 2/22/2024 Corrections Issued BEN MOLSTAD
PLUMBING-Final 2/22/2024 Corrections Issued BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 2/22/2024 SGSOV Approved BEN MOLSTAD
Sewer 2/22/2024 Approved BEN MOLSTAD
Smoke Detectors 2/22/2024 Approved BEN MOLSTAD
Final 3/1/2024 Corrections Issued BEN MOLSTAD
Green Building Final 3/1/2024 Not Ready for Inspection BEN MOLSTAD
Final 3/7/2024 Corrections Issued BEN MOLSTAD
Green Building Final 3/7/2024 Not Ready for Inspection BEN MOLSTAD
Final 3/21/2024 Corrections Issued BEN MOLSTAD
Green Building Final 3/21/2024 Approved BEN MOLSTAD
Final 3/28/2024 OK to Issue CofO BEN MOLSTAD