1555-1555 3/4 E 106TH ST 90002
Certificate Information: 1555-1555 3/4 E 106TH ST 90002
- Application / Permit
- 21014-10000-05033
- Plan Check / Job No.
- B21LA18676
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT GARAGE TO ADU PER LAMC 12.22 A.33(c) AND (d) and PER WFPP
- Permit Issued
- Issued on 4/5/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2021 | CRYSTEL MAALOUF |
| Corrections Issued | 10/27/2021 | CRYSTEL MAALOUF |
| Quality Review Completed | 10/28/2021 | KEN GILL |
| Building Plans Picked Up | 11/2/2021 | APPLICANT |
| Applicant returned to address corrections | 3/16/2022 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 4/13/2022 | CRYSTEL MAALOUF |
| Plan Check Approved | 5/2/2022 | CRYSTEL MAALOUF |
| Issued | 4/5/2023 | APPLICANT |
| CofO in Progress | 4/15/2024 | BEN MOLSTAD |
| CofO Issued | 4/15/2024 | ANSON MAGLASANG |
| Permit Finaled | 4/15/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 12/7/2021 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 12/9/2021 | CINDY QI |
| Sewer availability | Cleared | 2/3/2022 | CINDY QI |
Contact Information
| Contractor | Ebenezer Construction; Lic. No.: 657529-B | 9214 MANZANAR AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/20/2023 | Partial Approval | JOHN KLARIN |
| Sewer | 9/20/2023 | Partial Approval | JOHN KLARIN |
| ELECTRICAL-Rough | 11/15/2023 | Approved | JOHN KLARIN |
| Gas Test | 11/15/2023 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 11/15/2023 | Approved | JOHN KLARIN |
| Wood Frame | 11/15/2023 | Approved | JOHN KLARIN |
| Insulation | 12/1/2023 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 2/22/2024 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 2/22/2024 | Corrections Issued | BEN MOLSTAD |
| Final | 2/22/2024 | Corrections Issued | BEN MOLSTAD |
| Footing/Foundation/Slab | 2/22/2024 | Approved | BEN MOLSTAD |
| Green Building Final | 2/22/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Green Building Rough | 2/22/2024 | Approved | BEN MOLSTAD |
| HVAC-Final | 2/22/2024 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Final | 2/22/2024 | Corrections Issued | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 2/22/2024 | SGSOV Approved | BEN MOLSTAD |
| Sewer | 2/22/2024 | Approved | BEN MOLSTAD |
| Smoke Detectors | 2/22/2024 | Approved | BEN MOLSTAD |
| Final | 3/1/2024 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 3/1/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 3/7/2024 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 3/7/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 3/21/2024 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 3/21/2024 | Approved | BEN MOLSTAD |
| Final | 3/28/2024 | OK to Issue CofO | BEN MOLSTAD |