1551-1551 3/4 E 106TH ST 90002
Certificate Information: 1551-1551 3/4 E 106TH ST 90002
- Application / Permit
- 21014-10000-05021
- Plan Check / Job No.
- B21LA18647
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT GARAGE TO ADU
- Permit Issued
- Issued on 4/5/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 10/26/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 11/5/2021 | GARO TELMI |
| Building Plans Picked Up | 11/23/2021 | APPLICANT |
| Plan Check Approved | 6/29/2022 | ARSALAN SHABESTARI |
| Issued | 4/5/2023 | APPLICANT |
| CofO in Progress | 7/18/2024 | ANSON MAGLASANG |
| CofO Issued | 7/18/2024 | ANSON MAGLASANG |
| Permit Finaled | 7/18/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 12/7/2021 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 12/9/2021 | CINDY QI |
| Sewer availability | Cleared | 2/14/2022 | CINDY QI |
| Low Impact Development | Cleared | 3/4/2022 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 3/15/2022 | CINDY QI |
Contact Information
| Contractor | Ebenezer Construction; Lic. No.: 657529-B | 9214 MANZANAR AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 12/14/2023 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 4/1/2024 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Rough | 4/1/2024 | Corrections Issued | BEN MOLSTAD |
| Gas Test | 4/1/2024 | Approved | BEN MOLSTAD |
| Green Building Rough | 4/1/2024 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Rough | 4/1/2024 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Rough | 4/1/2024 | Corrections Issued | BEN MOLSTAD |
| Sewer | 4/1/2024 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 4/11/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 4/11/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Green Building Rough | 4/11/2024 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Rough | 4/11/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Insulation | 4/11/2024 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Rough | 4/11/2024 | Not Ready for Inspection | BEN MOLSTAD |
| BUILDING-Rough-Frame | 4/24/2024 | Approved | BEN MOLSTAD |
| ELECTRICAL-Rough | 4/24/2024 | Approved | BEN MOLSTAD |
| Green Building Rough | 4/24/2024 | Approved | BEN MOLSTAD |
| Insulation | 4/24/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Rough | 4/24/2024 | Approved | BEN MOLSTAD |
| Drywall Nailing | 5/7/2024 | Approved | BEN MOLSTAD |
| Final | 6/5/2024 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 6/5/2024 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 6/5/2024 | SGSOV Approved | BEN MOLSTAD |
| Smoke Detectors | 6/5/2024 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 6/20/2024 | Approved | BEN MOLSTAD |
| Final | 6/20/2024 | Corrections Issued | BEN MOLSTAD |
| HVAC-Final | 6/20/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Final | 6/20/2024 | Approved | BEN MOLSTAD |
| Final | 7/3/2024 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Final | 7/10/2024 | Approved | BEN MOLSTAD |
| Final | 7/10/2024 | OK to Issue CofO | BEN MOLSTAD |
| Green Building Final | 7/10/2024 | Approved | BEN MOLSTAD |
| HVAC-Final | 7/10/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Final | 7/10/2024 | Approved | BEN MOLSTAD |
| Pre-Inspection | 7/10/2024 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 7/10/2024 | SGSOV Approved | BEN MOLSTAD |