2710-2710 3/4 E DARWIN AVE 90031
Certificate Information: 2710-2710 3/4 E DARWIN AVE 90031
- Application / Permit
- 21014-10000-04994
- Plan Check / Job No.
- B21LA18556
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- ePLAN. NEW ATTACHED ACCESSORY DWELLING UNIT TO (E) APARTMENT PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 2/3/2022
- Issuing Office
- Current Status
- CofO Issued on 4/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/22/2021 | KEVIN MORALES |
| Corrections Issued | 11/23/2021 | KEVIN MORALES |
| Applicant returned to address corrections | 11/26/2021 | KEVIN MORALES |
| Applicant returned to address corrections | 12/10/2021 | KEVIN MORALES |
| Plan Check Approved | 12/16/2021 | KEVIN MORALES |
| Issued | 2/3/2022 | APPLICANT |
| CofO in Progress | 4/11/2023 | RONALD MYRICK |
| CofO Issued | 4/11/2023 | RONALD MYRICK |
| Permit Finaled | 4/11/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 12/3/2021 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 12/3/2021 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 12/14/2021 | JEANETTE VONG |
| Sewer availability | Cleared | 12/14/2021 | JEANETTE VONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/17/2022 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 2/25/2022 | Corrections Issued | OSVALDO PARAMO |
| PLUMBING-Rough | 3/2/2022 | Partial Approval | CRAIG DAVIS |
| Deputy Drilled-In Anchors | 3/7/2022 | Approved | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 3/7/2022 | Approved | OSVALDO PARAMO |
| Footing/Foundation/Slab | 3/7/2022 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 4/4/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2022 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 4/15/2022 | Partial Approval | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 4/15/2022 | Approved | OSVALDO PARAMO |
| Insulation | 4/27/2022 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Rough | 7/27/2022 | Approved | OSVALDO PARAMO |
| Insulation | 7/27/2022 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 7/27/2022 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 8/9/2022 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 10/13/2022 | Corrections Issued | OSVALDO PARAMO |
| Gas Test | 10/13/2022 | Approved | OSVALDO PARAMO |
| PLUMBING-Final | 10/13/2022 | Corrections Issued | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 11/1/2022 | Approved | OSVALDO PARAMO |
| Final | 11/1/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| MERV13>=Final | 11/1/2022 | Approved | OSVALDO PARAMO |
| MERV13>=Rough | 11/1/2022 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 11/1/2022 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 11/1/2022 | Approved | OSVALDO PARAMO |
| Final | 2/15/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 3/29/2023 | Conditional Approval | OSVALDO PARAMO |