16743 W VINTAGE ST 91343
Certificate Information: 16743 W VINTAGE ST 91343
- Application / Permit
- 21014-10000-04978
- Plan Check / Job No.
- B21LA18519
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2ND FLOOR ADDITION AND GROUND FLOOR ADDITION TO (E) SFD
- Permit Issued
- Issued on 6/16/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2021 | CARLOS MONTES |
| Corrections Issued | 11/9/2021 | CARLOS MONTES |
| Quality Review Completed | 11/10/2021 | KEN GILL |
| Building Plans Picked Up | 12/23/2021 | APPLICANT |
| Plan Check Approved | 3/3/2022 | CARLOS MONTES |
| Issued | 6/16/2022 | APPLICANT |
| CofO in Progress | 10/23/2023 | JAVIER RAMOS JR |
| CofO Issued | 12/21/2023 | RUBEN SALAS |
| Permit Finaled | 12/21/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/3/2022 | ABDULLAH SADOZAI |
| Roof/Waste drainage to street | Cleared | 1/11/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 1/11/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 1/18/2022 | ABDULLAH SADOZAI |
| Grading Pre-Inspection | Cleared | 2/17/2022 | SERGIO VALENZUELA |
| GPI Written Notices | Cleared | 3/3/2022 | CARLOS MONTES |
Contact Information
| Architect | Erlich,, Ayal; Lic. No.: C36241 | 21505 OCEAN AVENUE TORRANCE, CA 90503 |
| Contractor | En Builders Inc; Lic. No.: 977804-B | 18375 VENTURA BLVD STE 227 TARZANA, CA 91356 |
| Engineer | Southerland,, Richard Charles; Lic. No.: C88965 | 16526 BLACKHAWK ST GRANADA HILLS, CA 91344 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/7/2022 | Partial Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 11/17/2022 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 11/17/2022 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2022 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 12/5/2022 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 3/29/2023 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 3/29/2023 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2023 | Partial Approval | JAVIER RAMOS JR |
| HVAC-Rough | 3/29/2023 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 3/29/2023 | Approved | JAVIER RAMOS JR |
| Deputy Wood Construction | 4/12/2023 | Conditional Approval | MICHAEL SMITH |
| BUILDING-Rough-Frame | 4/14/2023 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2023 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 4/14/2023 | Approved | JAVIER RAMOS JR |
| Insulation | 4/25/2023 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 4/25/2023 | Approved | JAVIER RAMOS JR |
| Shower Pan | 4/25/2023 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 5/15/2023 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 8/23/2023 | Approved | JAVIER RAMOS JR |
| Final | 8/23/2023 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 8/23/2023 | Approved | JAVIER RAMOS JR |
| Green Building Final | 8/23/2023 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 8/23/2023 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 8/23/2023 | Approved | JAVIER RAMOS JR |
| Final | 10/23/2023 | OK to Issue CofO | JAVIER RAMOS JR |