16743 W VINTAGE ST 91343

Certificate Information: 16743 W VINTAGE ST 91343

Application / Permit
21014-10000-04978
Plan Check / Job No.
B21LA18519
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2ND FLOOR ADDITION AND GROUND FLOOR ADDITION TO (E) SFD
Permit Issued
Issued on 6/16/2022
Issuing Office
Metro
Current Status
CofO Issued on 12/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/3/2021 APPLICANT
Assigned to Plan Check Engineer 11/4/2021 CARLOS MONTES
Corrections Issued 11/9/2021 CARLOS MONTES
Quality Review Completed 11/10/2021 KEN GILL
Building Plans Picked Up 12/23/2021 APPLICANT
Plan Check Approved 3/3/2022 CARLOS MONTES
Issued 6/16/2022 APPLICANT
CofO in Progress 10/23/2023 JAVIER RAMOS JR
CofO Issued 12/21/2023 RUBEN SALAS
Permit Finaled 12/21/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/3/2022 ABDULLAH SADOZAI
Roof/Waste drainage to street Cleared 1/11/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 1/11/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 1/18/2022 ABDULLAH SADOZAI
Grading Pre-Inspection Cleared 2/17/2022 SERGIO VALENZUELA
GPI Written Notices Cleared 3/3/2022 CARLOS MONTES

Contact Information

Architect Erlich,, Ayal; Lic. No.: C36241 21505 OCEAN AVENUE      TORRANCE, CA 90503
Contractor En Builders Inc; Lic. No.: 977804-B 18375 VENTURA BLVD STE 227      TARZANA, CA 91356
Engineer Southerland,, Richard Charles; Lic. No.: C88965 16526 BLACKHAWK ST      GRANADA HILLS, CA 91344

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/7/2022 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 11/17/2022 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 11/17/2022 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 12/5/2022 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 12/5/2022 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 3/29/2023 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 3/29/2023 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 3/29/2023 Partial Approval JAVIER RAMOS JR
HVAC-Rough 3/29/2023 Approved JAVIER RAMOS JR
PLUMBING-Rough 3/29/2023 Approved JAVIER RAMOS JR
Deputy Wood Construction 4/12/2023 Conditional Approval MICHAEL SMITH
BUILDING-Rough-Frame 4/14/2023 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 4/14/2023 Approved JAVIER RAMOS JR
Green Building Rough 4/14/2023 Approved JAVIER RAMOS JR
Insulation 4/25/2023 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 4/25/2023 Approved JAVIER RAMOS JR
Shower Pan 4/25/2023 Approved JAVIER RAMOS JR
Drywall Nailing 5/15/2023 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 8/23/2023 Approved JAVIER RAMOS JR
Final 8/23/2023 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 8/23/2023 Approved JAVIER RAMOS JR
Green Building Final 8/23/2023 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 8/23/2023 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 8/23/2023 Approved JAVIER RAMOS JR
Final 10/23/2023 OK to Issue CofO JAVIER RAMOS JR