1058 N LAGOON AVE 90744

Certificate Information: 1058 N LAGOON AVE 90744

Application / Permit
21014-10000-04959
Plan Check / Job No.
B21LA18452
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO AND REMODEL OF (E) SFD. CREATE (N) THIRD BEDROOM, CLOSET AND BATHROOM.
Permit Issued
Issued on 3/25/2022
Issuing Office
Current Status
CofO Issued on 8/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/3/2021 APPLICANT
Assigned to Plan Check Engineer 10/4/2021 LAWRENCE QUIRANTE
Corrections Issued 10/5/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 1/25/2022 RAHEL BEYENE
Applicant returned to address corrections 3/4/2022 LAWRENCE QUIRANTE
Building Plans Picked Up 3/7/2022 APPLICANT
Plan Check Approved 3/23/2022 LAWRENCE QUIRANTE
Issued 3/25/2022 APPLICANT
CofO in Progress 8/18/2022 EUGENE CASSIDY
Permit Finaled 8/23/2022 DEROLD HAUFF
CofO Issued 8/23/2022 DEROLD HAUFF
Permit Finaled 8/23/2022 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/8/2021 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 11/23/2021 ERIK BEASLEY
Sewer availability Cleared 11/23/2021 ERIK BEASLEY
"Q" conditions Cleared 1/28/2022 RUBEN VASQUEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Kim,, Hong Kook; Lic. No.: C64529 3600 WILSHIRE BLVD STE 1903      LOS ANGELES, CA 90010

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/3/2022 Approved EUGENE CASSIDY
Footing/Foundation/Slab 5/3/2022 Approved EUGENE CASSIDY
METHANE-Barrier 5/3/2022 Approved EUGENE CASSIDY
METHANE-Subgrade 5/3/2022 Approved EUGENE CASSIDY
Pre-Inspection 5/3/2022 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 5/11/2022 Corrections Issued EUGENE CASSIDY
Insulation 5/11/2022 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 5/11/2022 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 5/17/2022 Corrections Issued EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 5/17/2022 Partial Approval EUGENE CASSIDY
Insulation 5/17/2022 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 5/17/2022 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 5/31/2022 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 5/31/2022 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 5/31/2022 Partial Approval EUGENE CASSIDY
Green Building Rough 5/31/2022 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 5/31/2022 Approved EUGENE CASSIDY
PLUMBING-Rough 5/31/2022 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 6/10/2022 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 6/10/2022 Approved EUGENE CASSIDY
Green Building Rough 6/10/2022 Approved EUGENE CASSIDY
HVAC-Rough 6/10/2022 Approved EUGENE CASSIDY
Insulation 6/10/2022 Approved EUGENE CASSIDY
Interior/Exterior Lathing 6/10/2022 Partial Approval EUGENE CASSIDY
Drywall Nailing 6/24/2022 Approved EUGENE CASSIDY
Interior/Exterior Lathing 6/24/2022 Approved EUGENE CASSIDY
Final 8/8/2022 Corrections Issued EUGENE CASSIDY
Green Building Final 8/8/2022 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 8/8/2022 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 8/8/2022 Approved EUGENE CASSIDY
Final 8/11/2022 Conditional Approval EUGENE CASSIDY
Green Building Final 8/11/2022 Approved EUGENE CASSIDY
ELECTRICAL-Final 8/17/2022 Approved EUGENE CASSIDY
Final 8/17/2022 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 8/17/2022 Approved EUGENE CASSIDY
PLUMBING-Final 8/17/2022 Approved EUGENE CASSIDY