1141 1/2 S RIMPAU BLVD 90019

Certificate Information: 1141 1/2 S RIMPAU BLVD 90019

Application / Permit
21014-10000-04918
Plan Check / Job No.
B21LA18312
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY ADU ATTACHED TO (E) GARAGE PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 6/28/2022
Issuing Office
Metro
Current Status
CofO Issued on 2/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/8/2021 APPLICANT
Assigned to Plan Check Engineer 11/9/2021 SERGIO GUTIERREZ
Corrections Issued 11/18/2021 SERGIO GUTIERREZ
Quality Review Completed 12/2/2021 FARUK SEZER
Building Plans Picked Up 12/6/2021 APPLICANT
Applicant returned to address corrections 6/22/2022 SERGIO GUTIERREZ
Plan Check Approved 6/27/2022 SERGIO GUTIERREZ
Issued 6/28/2022 APPLICANT
CofO in Progress 1/30/2023 RICHARD DOCKUS
Permit Finaled 2/2/2023 DEROLD HAUFF
CofO Issued 2/2/2023 DEROLD HAUFF
Permit Finaled 2/2/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/10/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 1/19/2022 CINDY QI
Sewer availability Cleared 1/19/2022 CINDY QI
Hydrant and Access approval Cleared 3/28/2022 DWAYNE LAURENT
Low Impact Development Cleared 5/12/2022 NICK RAYGOZA
Roof/Waste drainage to street Cleared 5/13/2022 CINDY QI
Construction near power lines Cleared 6/9/2022 RIDWAN HARDY

Contact Information

Contractor K & C Remodeling Inc; Lic. No.: 1081750-B 1287 MONTECITO DR      LOS ANGELES, CA 90031
Engineer Ha,, Seungil; Lic. No.: S4164 3454 W 1ST ST      LOS ANGELES, CA 90004
Geologist Kaligi,, Azad Adam; Lic. No.: GEO9287 445 S FIGEUROA ST 3100      LOS ANGELES, CA 90071

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/28/2022 Partial Approval ADAM ESCOTO
METHANE-Subgrade 7/28/2022 Not Ready for Inspection ADAM ESCOTO
Pre-Inspection 7/28/2022 Approved ADAM ESCOTO
Underground Mechanical 7/28/2022 Partial Approval ADAM ESCOTO
Deputy Methane Barrier 8/8/2022 Conditional Approval MICHAEL LEWIS
Deputy Methane Barrier 8/9/2022 Conditional Approval ALIZAH MAYAGOITIA
METHANE-Subgrade 8/15/2022 Approved MICHAEL LEWIS
Underground Mechanical 8/15/2022 Approved MICHAEL LEWIS
Deputy Methane Barrier 8/17/2022 Conditional Approval ALIZAH MAYAGOITIA
Deputy Methane Barrier 8/18/2022 Conditional Approval MICHAEL LEWIS
Deputy Methane Barrier 8/19/2022 Conditional Approval MICHAEL LEWIS
Footing/Foundation/Slab 8/25/2022 Approved MICHAEL LEWIS
METHANE-Barrier 8/25/2022 Approved MICHAEL LEWIS
METHANE-Rough 8/25/2022 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 9/7/2022 Partial Approval MICHAEL LEWIS
BUILDING-Rough-Frame 10/5/2022 Partial Approval JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 10/5/2022 Approved JEFFREY MEAD
Green Building Rough 10/5/2022 Not Ready for Inspection JEFFREY MEAD
ELECTRICAL-Rough 10/11/2022 Approved MICHAEL LEWIS
HVAC-Rough 10/11/2022 Partial Approval MICHAEL LEWIS
PLUMBING-Rough 10/11/2022 Approved MICHAEL LEWIS
Deputy Drilled-In Anchors 10/13/2022 Conditional Approval MICHAEL LEWIS
BUILDING-Rough-Frame 10/25/2022 Partial Approval KATHRYN BUTTERWORTH
Insulation 10/25/2022 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 10/25/2022 Partial Approval KATHRYN BUTTERWORTH
Shower Pan 10/25/2022 Approved KATHRYN BUTTERWORTH
Drywall Nailing 11/1/2022 Approved MICHAEL LEWIS
Interior/Exterior Lathing 11/1/2022 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 1/6/2023 Approved RICHARD DOCKUS
ELECTRICAL-Final 1/6/2023 Corrections Issued RICHARD DOCKUS
Final 1/6/2023 Corrections Issued RICHARD DOCKUS
Green Building Final 1/6/2023 Approved RICHARD DOCKUS
Green Building Rough 1/6/2023 Approved RICHARD DOCKUS
HVAC-Final 1/6/2023 Approved RICHARD DOCKUS
PLUMBING-Final 1/6/2023 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 1/6/2023 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 1/6/2023 Approved RICHARD DOCKUS
ELECTRICAL-Final 1/12/2023 Corrections Issued RICHARD DOCKUS
Final 1/12/2023 Not Ready for Inspection RICHARD DOCKUS
Gas Test 1/12/2023 Approved RICHARD DOCKUS
Final 1/24/2023 OK to Issue CofO RICHARD DOCKUS