2416 N MCCREADY AVE 90039
Certificate Information: 2416 N MCCREADY AVE 90039
- Application / Permit
- 21014-10000-04892
- Plan Check / Job No.
- B21LA18162
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- TWO STORY ADDITION AND KITCHEN REMODEL TO THE EXISTING SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 8/4/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2021 | ALBERT SERVIN |
| Corrections Issued | 10/29/2021 | ALBERT SERVIN |
| Quality Review Completed | 11/3/2021 | PETER KIM |
| Building Plans Picked Up | 11/15/2021 | APPLICANT |
| Plan Check Approved | 6/1/2022 | ALBERT SERVIN |
| Issued | 8/4/2022 | APPLICANT |
| CofO in Progress | 6/27/2025 | HAMIK HARTOUNIAN |
| Permit Finaled | 6/29/2025 | DEROLD HAUFF |
| CofO Issued | 6/29/2025 | DEROLD HAUFF |
| Permit Finaled | 6/29/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 3/16/2022 | ALBERT SERVIN |
| BHO/Hillside ordinance | Cleared | 5/18/2022 | JEANETTE VONG |
| BHO/Hillside ordinance | Cleared | 5/18/2022 | JEANETTE VONG |
| BHO/Hillside ordinance | Cleared | 5/18/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 5/18/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 5/18/2022 | JEANETTE VONG |
| Low Impact Development | Cleared | 7/25/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 8/1/2022 | TREVOR QUAN |
Contact Information
| Architect | Dutton,, John A; Lic. No.: C26818 | 1115 W SUNSET BLVD #108 LOS ANGELES, CA 90012 |
| Contractor | Owner-Builder | , |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
| Engineer | Rybak,, Richard; Lic. No.: GE2131 | 20312 TAU PLACE CHATSWORTH, CA 91311 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/18/2022 | Partial Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 10/19/2022 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 10/26/2022 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2022 | Partial Approval | THOMAS LOGRASSO |
| Green Building Rough | 11/7/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 11/17/2022 | Partial Approval | THOMAS LOGRASSO |
| Underground Mechanical | 11/17/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2022 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2022 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2023 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 2/9/2023 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 2/9/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 2/9/2023 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 2/15/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 2/16/2023 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Rough | 2/16/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Insulation | 4/5/2023 | Approved | KATHRYN BUTTERWORTH |
| Shower Pan | 5/5/2023 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 5/12/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Drywall Nailing | 5/16/2023 | Partial Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 5/16/2023 | Partial Approval | THOMAS LOGRASSO |
| Drywall Nailing | 6/26/2023 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 7/14/2023 | Partial Approval | THOMAS LOGRASSO |
| Gas Test | 9/18/2023 | Approved | BRENDAN MORELLI |
| HVAC-Final | 9/29/2023 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Final | 9/29/2023 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 10/4/2023 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Final | 10/4/2023 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 6/21/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 10/9/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 10/9/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 10/9/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 10/9/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 10/9/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 10/9/2024 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 10/9/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 1/16/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 1/16/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 1/16/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 1/16/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 1/16/2025 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 1/16/2025 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 1/16/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 6/27/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 6/27/2025 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Green Building Final | 6/27/2025 | Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 6/27/2025 | Approved | HAMIK HARTOUNIAN |