16125 W DICKENS ST 91436
Certificate Information: 16125 W DICKENS ST 91436
- Application / Permit
- 21014-10000-04875
- Plan Check / Job No.
- B21LA18107
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL AND GROUND FLOOR ADDITION (1125 SF) TO (E) SFD WITH ATTACHED ADDITION OF CALIFORNIA ROOM (205 SF) AT REAR AND TRELLIS AT FRONT.
- Permit Issued
- Issued on 4/19/2022
- Issuing Office
- Current Status
- CofO Issued on 8/31/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2021 | VIVIAN LAO |
| Corrections Issued | 11/3/2021 | VIVIAN LAO |
| Quality Review Completed | 11/19/2021 | GARO TELMI |
| Building Plans Picked Up | 11/29/2021 | APPLICANT |
| Applicant returned to address corrections | 1/4/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 1/12/2022 | VIVIAN LAO |
| Plan Check Approved | 3/21/2022 | VIVIAN LAO |
| Issued | 4/19/2022 | APPLICANT |
| CofO in Progress | 8/28/2023 | JOHN KIDWELL |
| Permit Finaled | 8/31/2023 | JOHN JANSON |
| CofO Issued | 8/31/2023 | JOHN JANSON |
| Permit Finaled | 8/31/2023 | JOHN JANSON |
Permit Application Clearance Information
| Sewer availability | Cleared | 12/16/2021 | JOSE DUARTE-DIAZ |
| Grading Pre-Inspection | Cleared | 12/20/2021 | ROBERT HUGHES |
| Eng Process Fee Ord 176,300 | Cleared | 12/22/2021 | JOSE DUARTE-DIAZ |
| Low Impact Development | Cleared | 3/3/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 3/3/2022 | JOHN LIN |
| GPI Written Notices | Cleared | 3/7/2022 | VIVIAN LAO |
Contact Information
| Contractor | Jay Kim Construction; Lic. No.: 925557-B | 1614 PLEASANT HILL DR CHINO HILLS, CA 91709 |
| Engineer | Hwang,, Junho; Lic. No.: S5592 | 815 FAIRVIEW AVE #205 SOUTH PASADENA, CA 91030 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/21/2022 | Approved | ROBERT GOLD |
| BUILDING-Rough-Frame | 8/31/2022 | Not Ready for Inspection | PETER FOLLING |
| Excavation/Setback/Form/Re-Bar | 8/31/2022 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 9/22/2022 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 9/22/2022 | Partial Approval | VINCENT HANLEY |
| Sewer | 9/22/2022 | Approved | VINCENT HANLEY |
| Insulation | 9/29/2022 | Partial Approval | JESUS PINEDA |
| BUILDING-Rough-Frame | 10/7/2022 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2022 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 10/7/2022 | Not Ready for Inspection | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2022 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 12/15/2022 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2022 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 1/19/2023 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Rough | 1/19/2023 | Approved | VINCENT HANLEY |
| Green Building Rough | 1/19/2023 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 1/19/2023 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 1/19/2023 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 1/31/2023 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2023 | Approved | VINCENT HANLEY |
| Green Building Rough | 1/31/2023 | Approved | VINCENT HANLEY |
| HVAC-Rough | 1/31/2023 | Approved | VINCENT HANLEY |
| Insulation | 2/2/2023 | Approved | JUSTIN HAWLEY |
| Shower Pan | 2/2/2023 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 2/16/2023 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 2/16/2023 | Partial Approval | JESUS PINEDA |
| Interior/Exterior Lathing | 3/7/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 6/26/2023 | Approved | JOHN KIDWELL |
| Service/Power Release | 6/26/2023 | Approved | JOHN KIDWELL |
| PLUMBING-Final | 7/7/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 8/25/2023 | Approved | JOHN KIDWELL |
| Final | 8/25/2023 | OK to Issue CofO | JOHN KIDWELL |
| Green Building Final | 8/25/2023 | Approved | JOHN KIDWELL |
| HVAC-Final | 8/25/2023 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 8/25/2023 | SGSOV Approved | JOHN KIDWELL |
| Smoke Detectors | 8/25/2023 | Approved | JOHN KIDWELL |