24537 S LAKME AVE 90744
Certificate Information: 24537 S LAKME AVE 90744
- Application / Permit
- 21014-10000-04871
- Plan Check / Job No.
- B21LA18088
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Major remodel and addition to existing single family dweling. Fully sprinklered throughout. 1 OF 2
- Permit Issued
- Issued on 7/25/2023
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 8/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2021 | RICARDO RAMIREZ |
| Corrections Issued | 10/16/2021 | RICARDO RAMIREZ |
| Building Plans Picked Up | 10/25/2021 | APPLICANT |
| Applicant returned to address corrections | 12/20/2022 | JASON JANGADA |
| Applicant returned to address corrections | 12/29/2022 | JASON JANGADA |
| Applicant returned to address corrections | 1/3/2023 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 2/24/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 4/20/2023 | SERGIO SILVA |
| Applicant returned to address corrections | 7/6/2023 | SERGIO SILVA |
| Applicant returned to address corrections | 7/18/2023 | LAWRENCE QUIRANTE |
| Plan Check Approved | 7/20/2023 | KHUONG TRUONG |
| Issued | 7/25/2023 | APPLICANT |
| CofO in Progress | 8/25/2025 | EUGENE CASSIDY |
| Permit Finaled | 8/26/2025 | ANSON MAGLASANG |
| CofO Issued | 8/26/2025 | ANSON MAGLASANG |
| Permit Finaled | 8/26/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 3/11/2022 | MAYELA VILLA |
| Permit | Cleared | 9/29/2022 | ANA SORIANO |
| Sewer availability | Cleared | 9/29/2022 | ANA SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 10/4/2022 | ANA SORIANO |
| Roof/Waste drainage to street | Cleared | 11/1/2022 | ANA SORIANO |
| Low Impact Development | Cleared | 11/22/2022 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 6/27/2023 | ANA SORIANO |
| Low Impact Development (LID) | Cleared | 7/11/2023 | ORVAL HERNANDEZ-MARCI |
Contact Information
| Contractor | D P Construction; Lic. No.: 867245-B | 4443 W 164TH ST LAWNDALE, CA 90260 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Service/Power Release | 11/14/2023 | Approved | EUGENE CASSIDY |
| Service/Power Release | 11/15/2023 | No Access for Inspection | JAMES CHAVEZ |
| Excavation/Setback/Form/Re-Bar | 12/13/2023 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 12/13/2023 | Approved | EUGENE CASSIDY |
| METHANE-Barrier | 12/13/2023 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 12/13/2023 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 12/22/2023 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2023 | Partial Approval | EUGENE CASSIDY |
| Insulation | 12/27/2023 | Partial Approval | EUGENE CASSIDY |
| Deputy Wood Construction | 1/25/2024 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2024 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 2/13/2024 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2024 | Partial Approval | EUGENE CASSIDY |
| Gas Test | 2/13/2024 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 2/13/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Interior/Exterior Lathing | 2/13/2024 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 2/13/2024 | Approved | EUGENE CASSIDY |
| Wood Frame | 2/13/2024 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 3/8/2024 | Approved | EUGENE CASSIDY |
| Green Building Rough | 3/8/2024 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 3/8/2024 | Approved | EUGENE CASSIDY |
| METHANE-Rough | 3/8/2024 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 3/8/2024 | Approved | EUGENE CASSIDY |
| Insulation | 3/12/2024 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 3/21/2024 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 4/2/2024 | Partial Approval | JAMES CHAVEZ |
| Shower Pan | 4/2/2024 | Corrections Issued | JAMES CHAVEZ |
| Shower Pan | 4/5/2024 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Final | 6/26/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 6/26/2024 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 6/26/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Final | 6/26/2024 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 6/26/2024 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 6/26/2024 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 6/26/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 2/6/2025 | Approved | EUGENE CASSIDY |
| Final | 2/6/2025 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 2/6/2025 | Approved | EUGENE CASSIDY |
| HVAC-Final | 2/6/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 2/6/2025 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 2/6/2025 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 2/6/2025 | Approved | EUGENE CASSIDY |
| Final | 8/12/2025 | Corrections Issued | EUGENE CASSIDY |
| Final | 8/25/2025 | OK to Issue CofO | EUGENE CASSIDY |