8006 S BLERIOT AVE 90045
Certificate Information: 8006 S BLERIOT AVE 90045
- Application / Permit
- 21014-10000-04870
- Plan Check / Job No.
- B21LA18081
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION (283 SF) AND REMODEL OF (E) SFD AND PROPOSED (174 SF) ATTACHED UNCOVERED DECK AT REAR.
- Permit Issued
- Issued on 1/28/2022
- Issuing Office
- Current Status
- CofO Issued on 11/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2021 | VIVIAN LAO |
| Corrections Issued | 11/9/2021 | VIVIAN LAO |
| Quality Review Completed | 11/19/2021 | GARO TELMI |
| Applicant returned to address corrections | 12/15/2021 | VIVIAN LAO |
| Plan Check Approved | 12/21/2021 | VIVIAN LAO |
| Issued | 1/28/2022 | APPLICANT |
| Building Plans Picked Up | 2/2/2022 | APPLICANT |
| CofO in Progress | 10/21/2022 | BOBBY KEY |
| Permit Finaled | 11/1/2022 | DANIEL ORRANTE |
| CofO Issued | 11/1/2022 | DANIEL ORRANTE |
| Permit Finaled | 11/1/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2021 | TRACY TATE |
| Roof/Waste drainage to street | Cleared | 11/17/2021 | TRACY TATE |
| Sewer availability | Cleared | 11/17/2021 | TRACY TATE |
| Miscellaneous | Cleared | 11/18/2021 | JENSON LEE |
Contact Information
| Architect | Miller,, Michael; Lic. No.: C26956 | 12756 MITCHELL AVE LOS ANGELES, CA 90066 |
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/7/2022 | Corrections Issued | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 2/10/2022 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 2/10/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 2/17/2022 | Partial Inspection | BOBBY KEY |
| Green Building Rough | 2/17/2022 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Rough | 3/14/2022 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2022 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 3/17/2022 | Approved | BOBBY KEY |
| PLUMBING-Rough | 3/21/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2022 | Approved | BOBBY KEY |
| Green Building Rough | 3/25/2022 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Rough | 3/25/2022 | Approved | BOBBY KEY |
| Insulation | 4/27/2022 | Partial Approval | RYAN SALAZAR |
| Interior/Exterior Lathing | 4/27/2022 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 5/11/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 5/11/2022 | Approved | BOBBY KEY |
| Green Building Rough | 5/11/2022 | Approved | BOBBY KEY |
| Insulation | 5/16/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 5/16/2022 | Not Ready for Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 5/19/2022 | Partial Approval | RICHARD STEINBACH |
| Shower Pan | 5/19/2022 | Approved | RICHARD STEINBACH |
| Service/Power Release | 8/18/2022 | Approved | CLAYTON GRAHAM |
| ELECTRICAL-Final | 10/11/2022 | Corrections Issued | BOBBY KEY |
| Final | 10/11/2022 | Corrections Issued | BOBBY KEY |
| Green Building Final | 10/11/2022 | Approved | BOBBY KEY |
| HVAC-Final | 10/11/2022 | Conditional Approval | BOBBY KEY |
| PLUMBING-Final | 10/11/2022 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 10/11/2022 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 10/11/2022 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Final | 10/21/2022 | Approved | BOBBY KEY |
| Final | 10/21/2022 | OK to Issue CofO | BOBBY KEY |
| HVAC-Final | 10/21/2022 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 10/21/2022 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 10/21/2022 | Approved | BOBBY KEY |