8006 S BLERIOT AVE 90045

Certificate Information: 8006 S BLERIOT AVE 90045

Application / Permit
21014-10000-04870
Plan Check / Job No.
B21LA18081
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION (283 SF) AND REMODEL OF (E) SFD AND PROPOSED (174 SF) ATTACHED UNCOVERED DECK AT REAR.
Permit Issued
Issued on 1/28/2022
Issuing Office
Current Status
CofO Issued on 11/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/27/2021 APPLICANT
Assigned to Plan Check Engineer 10/28/2021 VIVIAN LAO
Corrections Issued 11/9/2021 VIVIAN LAO
Quality Review Completed 11/19/2021 GARO TELMI
Applicant returned to address corrections 12/15/2021 VIVIAN LAO
Plan Check Approved 12/21/2021 VIVIAN LAO
Issued 1/28/2022 APPLICANT
Building Plans Picked Up 2/2/2022 APPLICANT
CofO in Progress 10/21/2022 BOBBY KEY
Permit Finaled 11/1/2022 DANIEL ORRANTE
CofO Issued 11/1/2022 DANIEL ORRANTE
Permit Finaled 11/1/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/17/2021 TRACY TATE
Roof/Waste drainage to street Cleared 11/17/2021 TRACY TATE
Sewer availability Cleared 11/17/2021 TRACY TATE
Miscellaneous Cleared 11/18/2021 JENSON LEE

Contact Information

Architect Miller,, Michael; Lic. No.: C26956 12756 MITCHELL AVE      LOS ANGELES, CA 90066
Contractor Owner-Builder       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/7/2022 Corrections Issued ANDREW NAVE
Excavation/Setback/Form/Re-Bar 2/10/2022 Approved BOBBY KEY
Footing/Foundation/Slab 2/10/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 2/17/2022 Partial Inspection BOBBY KEY
Green Building Rough 2/17/2022 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Rough 3/14/2022 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 3/14/2022 Partial Approval BOBBY KEY
ELECTRICAL-Rough 3/17/2022 Approved BOBBY KEY
PLUMBING-Rough 3/21/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 3/25/2022 Approved BOBBY KEY
Green Building Rough 3/25/2022 Not Ready for Inspection BOBBY KEY
HVAC-Rough 3/25/2022 Approved BOBBY KEY
Insulation 4/27/2022 Partial Approval RYAN SALAZAR
Interior/Exterior Lathing 4/27/2022 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 5/11/2022 Approved BOBBY KEY
Drywall Nailing 5/11/2022 Approved BOBBY KEY
Green Building Rough 5/11/2022 Approved BOBBY KEY
Insulation 5/16/2022 Approved BOBBY KEY
Interior/Exterior Lathing 5/16/2022 Not Ready for Inspection BOBBY KEY
Interior/Exterior Lathing 5/19/2022 Partial Approval RICHARD STEINBACH
Shower Pan 5/19/2022 Approved RICHARD STEINBACH
Service/Power Release 8/18/2022 Approved CLAYTON GRAHAM
ELECTRICAL-Final 10/11/2022 Corrections Issued BOBBY KEY
Final 10/11/2022 Corrections Issued BOBBY KEY
Green Building Final 10/11/2022 Approved BOBBY KEY
HVAC-Final 10/11/2022 Conditional Approval BOBBY KEY
PLUMBING-Final 10/11/2022 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 10/11/2022 SGSOV Not Ready BOBBY KEY
Smoke Detectors 10/11/2022 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Final 10/21/2022 Approved BOBBY KEY
Final 10/21/2022 OK to Issue CofO BOBBY KEY
HVAC-Final 10/21/2022 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 10/21/2022 SGSOV Approved BOBBY KEY
Smoke Detectors 10/21/2022 Approved BOBBY KEY