127 E 57TH ST 90011

Certificate Information: 127 E 57TH ST 90011

Application / Permit
21014-10000-04864
Plan Check / Job No.
B21LA18018
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REAR ADDITION TO EXISTING SFD. ALL WORK PER WOOD FRAME PRESCRIPTIVE PROVISIONS.
Permit Issued
Issued on 11/2/2022
Issuing Office
Metro
Current Status
CofO Issued on 9/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/24/2021 APPLICANT
Assigned to Plan Check Engineer 9/27/2021 DANIEL SANJUAN
Building Plans Picked Up 9/29/2021 APPLICANT
Corrections Issued 12/3/2021 DANIEL SANJUAN
Applicant returned to address corrections 7/1/2022 JOSEPH RAFOLS
Plan Check Approved 7/11/2022 GEORGE ALVAREZ
Issued 11/2/2022 APPLICANT
CofO in Progress 9/23/2025 ALEJANDRO DE ARTOLA
Permit Finaled 9/25/2025 DEROLD HAUFF
CofO Issued 9/25/2025 DEROLD HAUFF
Permit Finaled 9/25/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/24/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 5/20/2022 TREVOR QUAN
CPC Cleared 7/1/2022 LIKYELESH ABERA

Contact Information

Contractor Gold Pacific Construction Inc; Lic. No.: 1024672-B 1134 W 68TH ST      LOS ANGELES, CA 90044

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/13/2025 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 5/22/2025 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 6/5/2025 Approved WAYNE REGESTER
Footing/Foundation/Slab 6/5/2025 Approved WAYNE REGESTER
Floor/Roof Diaphrgm/Shear Wall 7/1/2025 Approved JOHN QUINTANILLA
Green Building Rough 7/1/2025 Not Ready for Inspection JOHN QUINTANILLA
BUILDING-Rough-Frame 7/9/2025 Corrections Issued LUIS CASTRO
ELECTRICAL-Rough 7/9/2025 Conditional Approval LUIS CASTRO
HVAC-Rough 7/9/2025 Corrections Issued LUIS CASTRO
PLUMBING-Rough 7/9/2025 Corrections Issued LUIS CASTRO
ELECTRICAL-Rough 7/14/2025 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/14/2025 Partial Approval ALEJANDRO DE ARTOLA
HVAC-Rough 7/14/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 7/14/2025 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 7/18/2025 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/18/2025 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 7/18/2025 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 7/24/2025 Approved ALEJANDRO DE ARTOLA
Green Building Rough 7/24/2025 Approved ALEJANDRO DE ARTOLA
Insulation 7/24/2025 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 7/31/2025 Approved ALEJANDRO DE ARTOLA
Insulation 7/31/2025 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 7/31/2025 Corrections Issued ALEJANDRO DE ARTOLA
Wood Frame 7/31/2025 Approved ALEJANDRO DE ARTOLA
Wood Frame 8/1/2025 Partial Inspection ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 8/4/2025 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Final 8/26/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 8/26/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 8/26/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 8/26/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 8/26/2025 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 8/26/2025 SGSOV Approved ALEJANDRO DE ARTOLA
Smoke Detectors 8/26/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 9/4/2025 Approved ALEJANDRO DE ARTOLA
Final 9/4/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 9/11/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 9/11/2025 Corrections Issued ALEJANDRO DE ARTOLA
Smoke Detectors 9/11/2025 Approved ALEJANDRO DE ARTOLA
Final 9/22/2025 OK to Issue CofO ALEJANDRO DE ARTOLA
Green Building Final 9/22/2025 Approved ALEJANDRO DE ARTOLA