1034 N BROAD AVE 90744
Certificate Information: 1034 N BROAD AVE 90744
- Application / Permit
- 21014-10000-04834
- Plan Check / Job No.
- B21LA17952
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- BEDROOM ADDITION WITH HALF BATH TO EXISTING S.F.D. ( see comments )
- Permit Issued
- Issued on 12/15/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2021 | LUKE GONZALES |
| Corrections Issued | 10/4/2021 | LUKE GONZALES |
| Applicant returned to address corrections | 11/12/2021 | RICARDO RAMIREZ |
| Plan Check Approved | 11/17/2021 | RICARDO RAMIREZ |
| Issued | 12/15/2021 | APPLICANT |
| Building Plans Picked Up | 12/21/2021 | APPLICANT |
| CofO in Progress | 8/30/2022 | EUGENE CASSIDY |
| Permit Finaled | 9/11/2022 | DEROLD HAUFF |
| CofO Issued | 9/11/2022 | DEROLD HAUFF |
| Permit Finaled | 9/11/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/26/2021 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 10/26/2021 | ERIK BEASLEY |
| Sewer availability | Cleared | 10/26/2021 | ERIK BEASLEY |
| "Q" conditions | Cleared | 10/27/2021 | LAUREN PADICK |
| Tenant Habitability Plan | Cleared | 10/29/2021 | ISMAEL HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/16/2021 | ERIK BEASLEY |
Contact Information
| Contractor | Mtr Builders Inc; Lic. No.: 1078627-B | 1311 WEST ANAHEIM STREET HARBOR CITY, CA 90710 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/30/2021 | Corrections Issued | JOHN KLARIN |
| METHANE-Barrier | 12/30/2021 | Not Ready for Inspection | JOHN KLARIN |
| METHANE-Subgrade | 12/30/2021 | Corrections Issued | JOHN KLARIN |
| Deputy Drilled-In Anchors | 1/3/2022 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 1/4/2022 | Approved | JOHN KLARIN |
| METHANE-Barrier | 1/4/2022 | Approved | JOHN KLARIN |
| METHANE-Subgrade | 1/4/2022 | Approved | JOHN KLARIN |
| Insulation | 1/6/2022 | Partial Approval | JOHN KLARIN |
| Wood Frame | 1/6/2022 | Partial Approval | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2022 | Partial Approval | JOHN KLARIN |
| Insulation | 1/10/2022 | Not Ready for Inspection | JOHN KLARIN |
| Interior/Exterior Lathing | 1/24/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Rough | 2/9/2022 | Approved | EUGENE CASSIDY |
| METHANE-Rough | 2/9/2022 | Approved | EUGENE CASSIDY |
| Wood Frame | 2/9/2022 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 2/23/2022 | Approved | EUGENE CASSIDY |
| Final | 4/13/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Final | 4/13/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 4/13/2022 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 4/13/2022 | Corrections Issued | EUGENE CASSIDY |
| Final | 4/19/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 4/19/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 4/19/2022 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 4/19/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 4/26/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 4/26/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 4/26/2022 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 4/26/2022 | Approved | EUGENE CASSIDY |
| Final | 6/23/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Final | 6/23/2022 | Approved | EUGENE CASSIDY |
| Final | 8/29/2022 | OK to Issue CofO | EUGENE CASSIDY |