1053 W 82ND ST 90044
Certificate Information: 1053 W 82ND ST 90044
- Application / Permit
- 21014-10000-04833
- Plan Check / Job No.
- B21LA17949
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING GARAGE WITH FIRST AND SECOND FLOOR ADDITION TO NEW ADU PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 6/5/2023
- Issuing Office
- Current Status
- CofO Issued on 4/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2022 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 1/13/2022 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 1/21/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 1/26/2022 | APPLICANT |
| Applicant returned to address corrections | 7/22/2022 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 9/2/2022 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 6/5/2023 | MAHNAZ NOURHASHEMI |
| Issued | 6/5/2023 | APPLICANT |
| CofO in Progress | 4/1/2024 | MICHAEL LEWIS |
| Permit Finaled | 4/9/2024 | DEROLD HAUFF |
| CofO Issued | 4/9/2024 | DEROLD HAUFF |
| Permit Finaled | 4/9/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/8/2022 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 6/8/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/12/2022 | WALLIE JONG |
| Sewer availability | Cleared | 8/12/2022 | WALLIE JONG |
| Community Plan Implem. Overlay | Cleared | 5/9/2023 | RAFAEL FONTES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sarrami,, Gholamali F; Lic. No.: C43720 | 4942 HIGHLAND VIEW AVENUE LOS ANGELES, CA 90041 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 10/17/2023 | Corrections Issued | RONNIE MINDANAO |
| ELECTRICAL-Rough | 10/17/2023 | Approved | RONNIE MINDANAO |
| Green Building Rough | 10/17/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| PLUMBING-Rough | 10/17/2023 | Corrections Issued | RONNIE MINDANAO |
| Deputy Wood Construction | 10/26/2023 | Conditional Approval | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 11/30/2023 | Partial Inspection | MICHAEL LEWIS |
| HVAC-Rough | 11/30/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 11/30/2023 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 1/2/2024 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 1/2/2024 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 1/2/2024 | Corrections Issued | ENRIQUE MIRELES |
| Shower Pan | 1/2/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 1/8/2024 | Corrections Issued | MICHAEL LEWIS |
| Shower Pan | 1/8/2024 | Corrections Issued | MICHAEL LEWIS |
| Interior/Exterior Lathing | 1/12/2024 | Partial Inspection | MICHAEL LEWIS |
| Shower Pan | 1/12/2024 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 1/23/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 3/6/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 3/6/2024 | Corrections Issued | MICHAEL LEWIS |
| Final | 3/6/2024 | Corrections Issued | MICHAEL LEWIS |
| Footing/Foundation/Slab | 3/6/2024 | Approved | MICHAEL LEWIS |
| Green Building Final | 3/6/2024 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Final | 3/6/2024 | Approved | MICHAEL LEWIS |
| PLUMBING-Final | 3/6/2024 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 3/6/2024 | SGSOV Approved | MICHAEL LEWIS |
| Smoke Detectors | 3/6/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 3/26/2024 | Approved | MICHAEL LEWIS |
| Final | 3/26/2024 | OK to Issue CofO | MICHAEL LEWIS |
| Green Building Final | 3/26/2024 | Approved | MICHAEL LEWIS |