1334 1/2 S REDONDO BLVD 90019

Certificate Information: 1334 1/2 S REDONDO BLVD 90019

Application / Permit
21014-10000-04826
Plan Check / Job No.
B21LA17943
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
GARAGE CONVERSION WITH AN ADDITION TO CREATE A DETACHED ADU PER ORDINANCE (1-STORY)
Permit Issued
Issued on 2/2/2022
Issuing Office
Current Status
CofO Issued on 10/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/24/2021 APPLICANT
Assigned to Plan Check Engineer 9/27/2021 CARLOS MONTES
Corrections Issued 9/27/2021 CARLOS MONTES
Applicant returned to address corrections 11/9/2021 CARLOS MONTES
Applicant returned to address corrections 12/28/2021 CARLOS MONTES
Applicant returned to address corrections 12/30/2021 CARLOS MONTES
Plan Check Approved 1/6/2022 CARLOS MONTES
Issued 2/2/2022 APPLICANT
CofO in Progress 10/13/2022 STUART CHAPMAN
Permit Finaled 10/14/2022 DEROLD HAUFF
Permit Finaled 10/14/2022 DEROLD HAUFF
CofO Issued 10/14/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/5/2021 STEVE MELGAR
Roof/Waste drainage to street Cleared 10/5/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 10/14/2021 STEVE MELGAR
Sewer availability Cleared 10/14/2021 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/14/2022 Approved STUART CHAPMAN
Sewer 4/21/2022 Approved STUART CHAPMAN
Underground Mechanical 4/21/2022 Partial Approval STUART CHAPMAN
Deputy Drilled-In Anchors 4/29/2022 Approved STUART CHAPMAN
Footing/Foundation/Slab 4/29/2022 Corrections Issued STUART CHAPMAN
METHANE-Barrier 4/29/2022 Approved STUART CHAPMAN
METHANE-Subgrade 4/29/2022 Approved STUART CHAPMAN
Footing/Foundation/Slab 5/24/2022 Approved SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/23/2022 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 6/30/2022 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 6/30/2022 Approved STUART CHAPMAN
HVAC-Rough 6/30/2022 Approved STUART CHAPMAN
PLUMBING-Rough 6/30/2022 Approved STUART CHAPMAN
BUILDING-Rough-Frame 7/15/2022 Approved STUART CHAPMAN
Green Building Rough 7/15/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 7/15/2022 Partial Approval STUART CHAPMAN
METHANE-Rough 7/15/2022 Approved STUART CHAPMAN
Underground Mechanical 7/15/2022 Partial Approval STUART CHAPMAN
Insulation 7/19/2022 Approved STUART CHAPMAN
Drywall Nailing 7/25/2022 Approved STUART CHAPMAN
Shower Pan 7/25/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 8/1/2022 Approved STUART CHAPMAN
ELECTRICAL-Final 9/9/2022 Corrections Issued STUART CHAPMAN
Service/Power Release 9/9/2022 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Final 9/23/2022 Partial Approval JULIAN AMAYA
Service/Power Release 9/23/2022 Approved JULIAN AMAYA
Final 9/27/2022 Corrections Issued STUART CHAPMAN
Green Building Final 9/27/2022 Approved STUART CHAPMAN
PLUMBING-Final 9/27/2022 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 9/27/2022 SGSOV Not Required STUART CHAPMAN
Smoke Detectors 9/27/2022 Approved STUART CHAPMAN
Final 10/6/2022 Corrections Issued STUART CHAPMAN
Service/Power Release 10/6/2022 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Final 10/13/2022 Approved STUART CHAPMAN
Final 10/13/2022 OK to Issue CofO STUART CHAPMAN
HVAC-Final 10/13/2022 Approved STUART CHAPMAN
Service/Power Release 10/13/2022 Approved STUART CHAPMAN