930 N BENTON WAY 90026

Certificate Information: 930 N BENTON WAY 90026

Application / Permit
21014-10000-04821
Plan Check / Job No.
B21LA17916
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO AN EXISTING SINGLE FAMILY DWELLING AND CONVERT EXISTING ATTIC SPACE INTO LIVIBALE AREA ALTERATION TO THE EXISTING FLOOR LAYOUT (BLDG TO BE SPRINKLERED)
Permit Issued
Issued on 7/18/2023
Issuing Office
Valley
Current Status
CofO Issued on 8/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/23/2021 APPLICANT
Assigned to Plan Check Engineer 10/28/2021 MINA HABIB
Corrections Issued 11/22/2021 MINA HABIB
Quality Review Completed 11/30/2021 FARUK SEZER
Building Plans Picked Up 12/22/2021 APPLICANT
Applicant returned to address corrections 6/15/2023 MINA HABIB
Applicant returned to address corrections 6/27/2023 MINA HABIB
Plan Check Approved 7/11/2023 MINA HABIB
Issued 7/18/2023 APPLICANT
CofO in Progress 8/20/2025 FREDDIE RIVERA
Permit Finaled 8/23/2025 DEROLD HAUFF
CofO Issued 8/23/2025 DEROLD HAUFF
Permit Finaled 8/23/2025 DEROLD HAUFF

Permit Application Clearance Information

Highway dedication Cleared 4/11/2023 TREVOR QUAN
Sewer availability Cleared 4/11/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 4/13/2023 TREVOR QUAN
Hydrant and Access approval Cleared 5/9/2023 KURT CORRAL
Frnt yard landscape/Water mgmt Cleared 5/16/2023 LOUIS ORTEGA
Low Impact Development Cleared 6/5/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 6/6/2023 JEANIE LAM
GPI Written Notices Cleared 7/11/2023 MINA HABIB
Grading Pre-Inspection Cleared 7/11/2023 MINA HABIB
Green Code Cleared 7/11/2023 MINA HABIB

Contact Information

Contractor Newhaven Builders; Lic. No.: 761971-B 600 LINCOLN AVE #90965      PASADENA, CA 91109
Engineer Lu,, Ining; Lic. No.: S3042 47 E LAS FLORES AVENUE      ARCADIA, CA 91006

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/19/2023 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 7/19/2023 Partial Inspection FREDDIE RIVERA
Deputy Drilled-In Anchors 7/20/2023 Conditional Approval FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 8/8/2023 Approved FREDDIE RIVERA
Footing/Foundation/Slab 8/8/2023 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 11/21/2023 Partial Approval FREDDIE RIVERA
ELECTRICAL-Final 1/16/2024 Corrections Issued FREDDIE RIVERA
Green Building Rough 1/16/2024 Partial Inspection FREDDIE RIVERA
PLUMBING-Rough 1/16/2024 Approved FREDDIE RIVERA
HVAC-Final 1/19/2024 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 1/23/2024 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Rough 1/23/2024 Approved FREDDIE RIVERA
Green Building Rough 1/23/2024 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 1/26/2024 Approved FREDDIE RIVERA
Insulation 2/1/2024 Corrections Issued FREDDIE RIVERA
Interior/Exterior Lathing 2/9/2024 Not Ready for Inspection JOSH MEISTER
Insulation 2/13/2024 Approved FREDDIE RIVERA
Interior/Exterior Lathing 2/13/2024 Approved FREDDIE RIVERA
Drywall Nailing 3/1/2024 Approved FREDDIE RIVERA
Final 3/21/2025 Corrections Issued FREDDIE RIVERA
Green Building Final 3/21/2025 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 3/21/2025 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 3/21/2025 Approved FREDDIE RIVERA
Final 6/9/2025 OK to Issue CofO FREDDIE RIVERA