5038 E SHIPLEY GLEN DR 90042

Certificate Information: 5038 E SHIPLEY GLEN DR 90042

Application / Permit
21014-10000-04820
Plan Check / Job No.
B21LA17894
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE STORY ADDITION ON SOUTH AND WEST SIDE OF THE EXISTING BUILDING
Permit Issued
Issued on 12/15/2023
Issuing Office
Metro
Current Status
Issued on 12/15/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/27/2021 APPLICANT
Assigned to Plan Check Engineer 11/18/2021 YOUNG KIM
Corrections Issued 11/30/2021 YOUNG KIM
Quality Review Completed 12/10/2021 KEN GILL
Building Plans Picked Up 12/13/2021 APPLICANT
Applicant returned to address corrections 12/16/2021 YOUNG KIM
Applicant returned to address corrections 5/20/2022 YOUNG KIM
Applicant returned to address corrections 11/28/2022 YOUNG KIM
Plan Check Approved 2/8/2023 YOUNG KIM
Issued 12/15/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/17/2021 KHOUNG LE
BHO/Hillside ordinance Cleared 12/17/2021 KHOUNG LE
Sewer availability Cleared 12/23/2021 KHOUNG LE
Grading Pre-Inspection Cleared 12/29/2021 SERGIO VALENZUELA
Eng Process Fee Ord 176,300 Cleared 1/19/2022 KHOUNG LE
BHO/Hillside ordinance Cleared 2/17/2022 KHOUNG LE
Roof/Waste drainage to street Cleared 5/4/2022 JEANIE LAM
BHO/Hillside ordinance Cleared 5/17/2022 JEANIE LAM
BHO/Hillside ordinance Cleared 5/17/2022 JEANIE LAM
BHO/Hillside ordinance Cleared 5/17/2022 KHOUNG LE
GPI Written Notices Cleared 1/11/2023 YOUNG KIM

Contact Information

Contractor Owner-Builder       ,
Engineer Kiledjian,, George Zohrab; Lic. No.: C74761 11447 VIKING AVE      NORTHRIDGE, CA 91326

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/11/2024 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 1/12/2024 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 2/23/2024 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 2/23/2024 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 2/23/2024 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 2/28/2024 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 2/28/2024 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 2/28/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Wood Frame 2/28/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Deputy Wood Construction 3/1/2024 Conditional Approval HAMIK HARTOUNIAN
PLUMBING-Rough 3/4/2024 Not Ready for Inspection SCOTT FINNILA
Deputy Wood Construction 3/5/2024 Conditional Approval HAMIK HARTOUNIAN
PLUMBING-Rough 3/5/2024 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 3/8/2024 Corrections Issued HAMIK HARTOUNIAN
Deputy Wood Construction 3/26/2024 Conditional Approval HAMIK HARTOUNIAN
Deputy Wood Construction 4/1/2024 Conditional Approval BRENDAN MORELLI
Deputy Wood Construction 4/3/2024 Conditional Approval HAMIK HARTOUNIAN
Wood Frame 4/4/2024 Partial Inspection BRIAN SULLIVAN
Wood Frame 4/24/2024 Approved CRAIG VAUGHAN
Insulation 4/29/2024 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 4/29/2024 Partial Approval LILIANA PORTILLO
Shower Pan 4/29/2024 Approved LILIANA PORTILLO
Drywall Nailing 5/2/2024 Corrections Issued HAMIK HARTOUNIAN
Green Building Rough 5/2/2024 Corrections Issued HAMIK HARTOUNIAN
Interior/Exterior Lathing 5/2/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 5/6/2024 Partial Approval THOMAS LOGRASSO
Drywall Nailing 5/14/2024 Approved THOMAS LOGRASSO
Green Building Rough 5/14/2024 Approved THOMAS LOGRASSO
HVAC-Rough 5/14/2024 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 6/6/2024 Approved THOMAS LOGRASSO
Final 6/6/2024 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 6/6/2024 Not Ready for Inspection THOMAS LOGRASSO
Green Building Final 6/6/2024 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 6/6/2024 SGSOV Not Ready THOMAS LOGRASSO
Smoke Detectors 6/6/2024 Approved THOMAS LOGRASSO