3860 S WESTSIDE AVE 90008

Certificate Information: 3860 S WESTSIDE AVE 90008

Application / Permit
21014-10000-04785
Plan Check / Job No.
B21LA17754
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2ND FLOOR ADDITION TO (E) 1-STORY SFD WITH INTERIOR AND EXTERIOR STRUCTURAL REMODEL PER PROVIDED IN THE PLAN.
Permit Issued
Issued on 11/4/2022
Issuing Office
Current Status
Issued on 11/4/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/22/2021 APPLICANT
Assigned to Plan Check Engineer 10/28/2021 MAHNAZ NOURHASHEMI
Corrections Issued 11/2/2021 MAHNAZ NOURHASHEMI
Quality Review Completed 11/10/2021 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 11/22/2021 APPLICANT
Plan Check Approved 8/19/2022 MAHNAZ NOURHASHEMI
Issued 11/4/2022 APPLICANT

Permit Application Clearance Information

Hold Cleared 11/2/2021 JASON SHEETS
Eng Process Fee Ord 176,300 Cleared 5/3/2022 CHRISTOPHER ROCHA
Low Impact Development Cleared 7/19/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 7/27/2022 JEANIE LAM

Contact Information

Architect Williams,, Gregory Keith; Lic. No.: C22965 1216 N DETROIT STREET APT 5      WEST HOLLYWOOD, CA 90046
Contractor Owner-Builder       ,
Engineer Tuchscher,, James Todd; Lic. No.: C77649 5503 E 2ND ST      LONG BEACH, CA 90803

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/31/2023 Partial Approval ANTHONY EGSON
Footing/Foundation/Slab 2/15/2023 Partial Approval BRENDAN MORELLI
Footing/Foundation/Slab 3/9/2023 Partial Approval ANTHONY EGSON
Structural Steel Frame 3/9/2023 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 5/1/2023 Partial Approval ANTHONY EGSON
Wood Frame 5/3/2023 Partial Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 5/22/2023 Partial Approval ANTHONY EGSON
Footing/Foundation/Slab 5/22/2023 Approved ANTHONY EGSON
Green Building Rough 5/22/2023 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 8/28/2023 Partial Approval ANTHONY EGSON
Deputy Wood Construction 12/1/2023 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 12/5/2023 Corrections Issued ANTHONY EGSON
Wood Frame 12/5/2023 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 12/7/2023 Approved ANTHONY EGSON
PLUMBING-Rough 12/7/2023 Approved ANTHONY EGSON
BUILDING-Rough-Frame 12/11/2023 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 12/11/2023 Partial Approval ANTHONY EGSON
Green Building Rough 12/11/2023 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 12/19/2023 Partial Approval ANTHONY EGSON
BUILDING-Rough-Frame 1/11/2024 Corrections Issued ALIZAH MAYAGOITIA
ELECTRICAL-Rough 1/11/2024 Corrections Issued ALIZAH MAYAGOITIA
Green Building Rough 1/11/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Rough 1/11/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 1/11/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 1/18/2024 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 1/18/2024 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 1/18/2024 Not Ready for Inspection ANTHONY EGSON
HVAC-Rough 1/18/2024 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 1/18/2024 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 2/9/2024 Partial Approval STUART CHAPMAN
Deputy Wood Construction 2/27/2024 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 2/27/2024 Partial Approval ANTHONY EGSON
Green Building Rough 2/27/2024 Approved ANTHONY EGSON
Interior/Exterior Lathing 2/27/2024 Partial Approval ANTHONY EGSON
Insulation 3/15/2024 No Access for Inspection JOSEPH MCGARRY
BUILDING-Rough-Frame 3/19/2024 Partial Approval ANTHONY EGSON
Insulation 3/19/2024 Approved ANTHONY EGSON
Shower Pan 3/19/2024 Approved ANTHONY EGSON
Drywall Nailing 4/5/2024 Approved JOSH MEISTER
Interior/Exterior Lathing 4/9/2024 Approved JOSH MEISTER
ELECTRICAL-Final 7/16/2024 Corrections Issued ANTHONY EGSON
PLUMBING-Final 7/16/2024 Corrections Issued ANTHONY EGSON
ELECTRICAL-Final 7/24/2024 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Final 8/14/2024 Corrections Issued ANTHONY EGSON
ELECTRICAL-Final 8/28/2024 Approved ANTHONY EGSON
HVAC-Final 8/28/2024 Approved ANTHONY EGSON
Service/Power Release 9/9/2024 Approved ANTHONY EGSON