5408 1/2 W WESTHAVEN ST 90016
Certificate Information: 5408 1/2 W WESTHAVEN ST 90016
- Application / Permit
- 21014-10000-04782
- Plan Check / Job No.
- B21LA17737
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED CONVERSION OF GARAGE ACCESSORY DWELLING UNIT WITH ADDITION PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 3/18/2022
- Issuing Office
- Current Status
- CofO Issued on 3/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2021 | SINA KHOSRAVI |
| Corrections Issued | 9/30/2021 | SINA KHOSRAVI |
| Plan Check Approved | 1/16/2022 | KHUONG TRUONG |
| Issued | 3/18/2022 | APPLICANT |
| Building Plans Picked Up | 3/22/2022 | APPLICANT |
| CofO in Progress | 3/14/2023 | JOSE AVILA |
| Permit Finaled | 3/18/2023 | DEROLD HAUFF |
| CofO Issued | 3/18/2023 | DEROLD HAUFF |
| Permit Finaled | 3/18/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/18/2021 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 10/18/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 11/2/2021 | PAMELA TENEZA |
| Sewer availability | Cleared | 11/23/2021 | PAMELA TENEZA |
| Tenant Habitability Plan | Cleared | 12/9/2021 | RICARDO BOHORQUEZ |
| Construction near power lines | Cleared | 1/7/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Next Generation Builders; Lic. No.: 1069728-B | 1858 ECHO PARK AVE LOS ANGELES, CA 90026 |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/30/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 4/6/2022 | Partial Approval | JOSE AVILA |
| Underground Mechanical | 4/6/2022 | Approved | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 4/8/2022 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 4/8/2022 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 4/15/2022 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 4/15/2022 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 4/19/2022 | No Access for Inspection | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 4/28/2022 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 4/28/2022 | Approved | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 5/2/2022 | Approved | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 5/13/2022 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2022 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 5/18/2022 | Partial Approval | JOSE AVILA |
| HVAC-Rough | 5/18/2022 | Approved | JOSE AVILA |
| PLUMBING-Rough | 5/18/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 5/23/2022 | Conditional Approval | JOSE AVILA |
| Deputy Wood Construction | 5/24/2022 | Conditional Approval | RUBEN SALAS |
| Insulation | 5/25/2022 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 5/25/2022 | Approved | JOSE AVILA |
| Drywall Nailing | 5/31/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 7/14/2022 | Approved | JOSE AVILA |
| Final | 7/14/2022 | Corrections Issued | JOSE AVILA |
| Green Building Final | 7/14/2022 | Approved | JOSE AVILA |
| Green Building Rough | 7/14/2022 | Approved | JOSE AVILA |
| MERV13>=Final | 7/14/2022 | Approved | JOSE AVILA |
| MERV13>=Rough | 7/14/2022 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 7/14/2022 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 7/14/2022 | Approved | JOSE AVILA |
| Final | 7/21/2022 | Corrections Issued | JOSE AVILA |
| Final | 3/14/2023 | OK to Issue CofO | JOSE AVILA |