5408 1/2 W WESTHAVEN ST 90016

Certificate Information: 5408 1/2 W WESTHAVEN ST 90016

Application / Permit
21014-10000-04782
Plan Check / Job No.
B21LA17737
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED CONVERSION OF GARAGE ACCESSORY DWELLING UNIT WITH ADDITION PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 3/18/2022
Issuing Office
Current Status
CofO Issued on 3/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/28/2021 APPLICANT
Assigned to Plan Check Engineer 9/30/2021 SINA KHOSRAVI
Corrections Issued 9/30/2021 SINA KHOSRAVI
Plan Check Approved 1/16/2022 KHUONG TRUONG
Issued 3/18/2022 APPLICANT
Building Plans Picked Up 3/22/2022 APPLICANT
CofO in Progress 3/14/2023 JOSE AVILA
Permit Finaled 3/18/2023 DEROLD HAUFF
CofO Issued 3/18/2023 DEROLD HAUFF
Permit Finaled 3/18/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/18/2021 RENZ SORIANO
Roof/Waste drainage to street Cleared 10/18/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 11/2/2021 PAMELA TENEZA
Sewer availability Cleared 11/23/2021 PAMELA TENEZA
Tenant Habitability Plan Cleared 12/9/2021 RICARDO BOHORQUEZ
Construction near power lines Cleared 1/7/2022 RIDWAN HARDY

Contact Information

Contractor Next Generation Builders; Lic. No.: 1069728-B 1858 ECHO PARK AVE      LOS ANGELES, CA 90026
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/30/2022 Approved STUART CHAPMAN
PLUMBING-Rough 4/6/2022 Partial Approval JOSE AVILA
Underground Mechanical 4/6/2022 Approved JOSE AVILA
Excavation/Setback/Form/Re-Bar 4/8/2022 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 4/8/2022 Corrections Issued JOSE AVILA
Excavation/Setback/Form/Re-Bar 4/15/2022 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 4/15/2022 Corrections Issued JOSE AVILA
Excavation/Setback/Form/Re-Bar 4/19/2022 No Access for Inspection JOSE AVILA
Excavation/Setback/Form/Re-Bar 4/28/2022 Approved JOSE AVILA
Footing/Foundation/Slab 4/28/2022 Approved JOSE AVILA
Excavation/Setback/Form/Re-Bar 5/2/2022 Approved JOSE AVILA
Excavation/Setback/Form/Re-Bar 5/13/2022 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 5/16/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 5/18/2022 Partial Approval JOSE AVILA
HVAC-Rough 5/18/2022 Approved JOSE AVILA
PLUMBING-Rough 5/18/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 5/23/2022 Conditional Approval JOSE AVILA
Deputy Wood Construction 5/24/2022 Conditional Approval RUBEN SALAS
Insulation 5/25/2022 Approved JOSE AVILA
Interior/Exterior Lathing 5/25/2022 Approved JOSE AVILA
Drywall Nailing 5/31/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 7/14/2022 Approved JOSE AVILA
Final 7/14/2022 Corrections Issued JOSE AVILA
Green Building Final 7/14/2022 Approved JOSE AVILA
Green Building Rough 7/14/2022 Approved JOSE AVILA
MERV13>=Final 7/14/2022 Approved JOSE AVILA
MERV13>=Rough 7/14/2022 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 7/14/2022 SGSOV Approved JOSE AVILA
Smoke Detectors 7/14/2022 Approved JOSE AVILA
Final 7/21/2022 Corrections Issued JOSE AVILA
Final 3/14/2023 OK to Issue CofO JOSE AVILA