3961 S INGLEWOOD BLVD 90066
Certificate Information: 3961 S INGLEWOOD BLVD 90066
- Application / Permit
- 21014-10000-04773
- Plan Check / Job No.
- B21LA17696
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 1ST FLOOR ADDITION TO EXISTING 2 STORY SFD (77 SQFT). PER ZA CASE # 2021-2601-ZAA.
- Permit Issued
- Issued on 12/14/2021
- Issuing Office
- Current Status
- CofO Issued on 6/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2021 | STANLEY RAAP |
| Corrections Issued | 9/28/2021 | STANLEY RAAP |
| Plan Check Approved | 11/29/2021 | SHANGQIN XIE |
| Issued | 12/14/2021 | APPLICANT |
| Building Plans Picked Up | 12/17/2021 | APPLICANT |
| CofO in Progress | 3/3/2022 | JOHN MATTILLO |
| Permit Finaled | 6/14/2024 | CLAUDIO MORENO |
| CofO Issued | 6/14/2024 | CLAUDIO MORENO |
| Permit Finaled | 6/14/2024 | CLAUDIO MORENO |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/6/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/13/2021 | DINAH GARIN |
| ZA Case | Cleared | 11/16/2021 | LOUIS ORTEGA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Paniagua,, Cristobal; Lic. No.: C72894 | 1538 W 92ND ST LOS ANGELES, CA 90047 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/10/2022 | Conditional Approval | JOHN MATTILLO |
| Footing/Foundation/Slab | 2/3/2022 | Corrections Issued | JOHN MATTILLO |
| Footing/Foundation/Slab | 2/15/2022 | Approved | JOHN MATTILLO |
| BUILDING-Rough-Frame | 2/22/2022 | Approved | JOHN MATTILLO |
| Green Building Rough | 2/22/2022 | Approved | JOHN MATTILLO |
| Drywall Nailing | 2/24/2022 | Approved | JOHN MATTILLO |
| Interior/Exterior Lathing | 2/24/2022 | Approved | JOHN MATTILLO |
| Final | 3/3/2022 | Conditional Approval | JOHN MATTILLO |
| Green Building Final | 3/3/2022 | Approved | JOHN MATTILLO |
| SGSOV-Seismic Gas S/O Valve | 3/3/2022 | SGSOV Approved | JOHN MATTILLO |
| Smoke Detectors | 3/3/2022 | Approved | JOHN MATTILLO |