3026 S GREENFIELD AVE 90034
Certificate Information: 3026 S GREENFIELD AVE 90034
- Application / Permit
- 21014-10000-04768
- Plan Check / Job No.
- B21LA17675
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW ADDITION AT REAR AND INTERIOR REMODEL OF EXISTING KITCHEN IN EXISTING SINGLE FAMILY DWELLING. "COMPLY WITH DEPARTMENT ORDER effective date 07/20/2020. CEIS Case Number is 900288."
- Permit Issued
- Issued on 11/29/2021
- Issuing Office
- Current Status
- CofO Issued on 7/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/22/2021 | AUNG SOE |
| Corrections Issued | 9/28/2021 | AUNG SOE |
| Building Plans Picked Up | 10/7/2021 | APPLICANT |
| Plan Check Approved | 11/29/2021 | KEVIN MORALES |
| Issued | 11/29/2021 | APPLICANT |
| CofO in Progress | 4/24/2023 | JOHN TCHANG |
| Permit Finaled | 7/10/2023 | DANIEL SANCHEZ |
| CofO Issued | 7/10/2023 | DANIEL SANCHEZ |
| Permit Finaled | 7/10/2023 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Specific Plan | Cleared | 10/26/2021 | FREDDY GARCIA |
| Roof/Waste drainage to street | Cleared | 10/28/2021 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/2/2021 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 11/18/2021 | BRIAN MILLER |
| GPI Written Notices | Cleared | 11/23/2021 | AUNG SOE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adefeso,, Wole Dayo; Lic. No.: C63361 | 1620 CENTINELA AVE 3048 INGLEWOOD, CA 90302 |
Inspector Information
| PETER RUBIO, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN TCHANG, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| RYAN TAGUINES, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/19/2022 | Corrections Issued | JOHN TCHANG |
| Pre-Inspection | 4/26/2022 | Not Ready for Inspection | JOHN TCHANG |
| Deputy Drilled-In Anchors | 9/27/2022 | Approved | JOHN TCHANG |
| BUILDING-Rough-Frame | 3/23/2023 | Approved | JOHN TCHANG |
| Final | 3/23/2023 | Partial Approval | JOHN TCHANG |
| Footing/Foundation/Slab | 3/23/2023 | Approved | JOHN TCHANG |
| Green Building Final | 3/23/2023 | Approved | JOHN TCHANG |
| Green Building Rough | 3/23/2023 | Approved | JOHN TCHANG |
| SGSOV-Seismic Gas S/O Valve | 3/23/2023 | SGSOV Approved | JOHN TCHANG |
| Smoke Detectors | 3/23/2023 | Approved | JOHN TCHANG |