4051 E BAYWOOD ST 90039

Certificate Information: 4051 E BAYWOOD ST 90039

Application / Permit
21014-10000-04746
Plan Check / Job No.
B21LA17539
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL AND ADDITION TO (E) S.F.D.
Permit Issued
Issued on 10/28/2021
Issuing Office
Current Status
CofO Issued on 10/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/20/2021 APPLICANT
Assigned to Plan Check Engineer 9/22/2021 LAWRENCE QUIRANTE
Corrections Issued 9/23/2021 LAWRENCE QUIRANTE
Plan Check Approved 10/26/2021 RAHEL BEYENE
Issued 10/28/2021 APPLICANT
Building Plans Picked Up 11/1/2021 APPLICANT
CofO in Progress 9/15/2022 HAMIK HARTOUNIAN
Permit Finaled 10/1/2022 DEROLD HAUFF
CofO Issued 10/1/2022 DEROLD HAUFF
Permit Finaled 10/1/2022 DEROLD HAUFF

Permit Application Clearance Information

Supp. Use District POD/CDO/TDO Cleared 9/28/2021 DENZEL HENDERSON
Roof/Waste drainage to street Cleared 9/29/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 10/1/2021 CECILIO NAVARRO

Contact Information

Contractor N A N D C O Llc; Lic. No.: 1044615-B 4836 FULTON AVE      SHERMAN OAKS, CA 91423
Engineer Standley,, Craig Erick; Lic. No.: C87675 5330 ZELZAH AVE UNIT 7      ENCINO, CA 91316

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/19/2021 Conditional Approval HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 2/3/2022 Approved HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 2/3/2022 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 2/22/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 2/28/2022 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 2/28/2022 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 4/15/2022 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 4/22/2022 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 5/5/2022 Approved HAMIK HARTOUNIAN
HVAC-Rough 5/5/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 5/5/2022 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 5/5/2022 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 5/9/2022 Approved HAMIK HARTOUNIAN
HVAC-Rough 5/9/2022 Corrections Issued HAMIK HARTOUNIAN
Shower Pan 5/9/2022 Conditional Approval HAMIK HARTOUNIAN
HVAC-Rough 5/20/2022 Approved HAMIK HARTOUNIAN
Wood Frame 5/20/2022 Conditional Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 5/25/2022 Approved RYAN SALAZAR
BUILDING-Rough-Frame 6/6/2022 Approved HAMIK HARTOUNIAN
Insulation 6/6/2022 Approved HAMIK HARTOUNIAN
Drywall Nailing 6/13/2022 Approved RYAN SALAZAR
Gas Test 7/27/2022 Approved HAMIK HARTOUNIAN
Service/Power Release 7/27/2022 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 8/2/2022 Corrections Issued HAMIK HARTOUNIAN
Final 8/2/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Final 8/2/2022 Corrections Issued HAMIK HARTOUNIAN
Green Building Rough 8/2/2022 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 8/2/2022 SGSOV Not Ready HAMIK HARTOUNIAN
Service/Power Release 8/2/2022 Approved HAMIK HARTOUNIAN
Smoke Detectors 8/2/2022 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 9/15/2022 Approved HAMIK HARTOUNIAN
Final 9/15/2022 OK to Issue CofO HAMIK HARTOUNIAN
Green Building Final 9/15/2022 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 9/15/2022 SGSOV Approved HAMIK HARTOUNIAN