9719 W HEATHER ROAD 90210
Certificate Information: 9719 W HEATHER ROAD 90210
- Application / Permit
- 21014-10000-04731
- Plan Check / Job No.
- B21LA17495
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PARTIAL EXTERIOR DEMOLITION AND 2800 S.F. SFD ADDITION TO EXISTING HOUSE WITH NEW EXTERIOR PAVERS, IRRIGATION AND LANDSCAPING. 1 OF 4
- Permit Issued
- Issued on 4/5/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2021 | SAM CHANG |
| Corrections Issued | 10/20/2021 | SAM CHANG |
| Quality Review Completed | 10/25/2021 | EUGENE BARBEAU |
| Applicant returned to address corrections | 3/1/2022 | SAM CHANG |
| Applicant returned to address corrections | 3/18/2022 | SAM CHANG |
| Building Plans Picked Up | 3/29/2022 | APPLICANT |
| Applicant returned to address corrections | 7/18/2022 | SAM CHANG |
| Plan Check Approved | 11/17/2022 | SAM CHANG |
| Issued | 4/5/2023 | APPLICANT |
| CofO in Progress | 2/25/2025 | RAUL BARAJAS |
| Permit Finaled | 2/27/2025 | DEROLD HAUFF |
| CofO Issued | 2/27/2025 | DEROLD HAUFF |
| Permit Finaled | 2/27/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/20/2021 | SAM CHANG |
| BHO/Hillside ordinance | Cleared | 11/5/2021 | DINAH GARIN |
| Permit | Cleared | 11/5/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 11/9/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 11/9/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 11/9/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 11/10/2021 | DINAH GARIN |
| Sewer availability | Cleared | 11/10/2021 | DINAH GARIN |
| ZI | Cleared | 11/18/2021 | ANACANY HURTADO |
| Private street | Cleared | 12/1/2021 | ANACANY HURTADO |
| Green Code | Cleared | 3/18/2022 | SAM CHANG |
| GPI Written Notices | Cleared | 7/18/2022 | SAM CHANG |
| Low Impact Development | Cleared | 10/18/2022 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 10/21/2022 | SAUL GARCIA |
| Greywater Systems | Cleared | 11/17/2022 | SAM CHANG |
Contact Information
| Architect | Peterson,, Erik Brian; Lic. No.: C30460 | 15990 N GREENWAY HAYDEN LOOP C100 SCOTTSDALE, AZ 85260 |
| Contractor | Third Generation Construction Inc; Lic. No.: 893694-B | 13369 LOS OLIVOS ROAD SYLMAR, CA 91342 |
| Engineer | Barr,, Joseph Daniel; Lic. No.: C70708 | 1185 HERITAGE FARM RD HICKORY, NC 28601 |
| Engineer | Koma,, Shahram Javadi; Lic. No.: C69497 | 23241 VENTURA BLVD 300 WOODLAND HILLS, CA 91364 |
| Geologist | Miller,, Jonathan Steven; Lic. No.: EG2391 | 24736 CALVERT STREET WOODLAND HILLS, CA 91367 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/1/2023 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 6/8/2023 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 6/13/2023 | Conditional Approval | RUBEN SALAS |
| Footing/Foundation/Slab | 7/12/2023 | Partial Approval | RAUL BARAJAS |
| Deputy Steel/Welding | 7/20/2023 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 7/24/2023 | Conditional Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 8/18/2023 | Approved | RAUL BARAJAS |
| Deputy Reinf. Concrete | 8/22/2023 | Conditional Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2023 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 9/27/2023 | Partial Approval | RAUL BARAJAS |
| Sewer | 9/27/2023 | Partial Approval | RAUL BARAJAS |
| Deputy Wood Construction | 10/5/2023 | Conditional Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2023 | Approved | RAUL BARAJAS |
| Green Building Rough | 10/5/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Insulation | 10/5/2023 | Approved | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 10/5/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Deputy Steel/Welding | 10/10/2023 | Conditional Approval | RAUL BARAJAS |
| BUILDING-Rough-Frame | 11/20/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2023 | Approved | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 11/20/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 12/21/2023 | Conditional Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 1/3/2024 | Approved | RAUL BARAJAS |
| Green Building Rough | 1/3/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 1/3/2024 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 2/8/2024 | Corrections Issued | RAUL BARAJAS |
| PLUMBING-Rough | 2/13/2024 | Partial Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 2/29/2024 | Approved | RAUL BARAJAS |
| HVAC-Rough | 2/29/2024 | Conditional Approval | RAUL BARAJAS |
| Interior/Exterior Lathing | 2/29/2024 | Approved | RAUL BARAJAS |
| Insulation | 3/14/2024 | Approved | RAUL BARAJAS |
| Drywall Nailing | 3/22/2024 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 3/22/2024 | Approved | RAUL BARAJAS |
| HVAC-Final | 8/29/2024 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Final | 8/29/2024 | Partial Approval | RAUL BARAJAS |
| BUILDING-Rough-Frame | 12/18/2024 | Approved | RAUL BARAJAS |
| Final | 12/18/2024 | Corrections Issued | RAUL BARAJAS |
| Green Building Final | 12/18/2024 | Approved | RAUL BARAJAS |
| Green Building Rough | 12/18/2024 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 12/18/2024 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 12/18/2024 | Approved | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 12/18/2024 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 2/25/2025 | Approved | RAUL BARAJAS |
| Final | 2/25/2025 | OK to Issue CofO | RAUL BARAJAS |
| Green Building Final | 2/25/2025 | Approved | RAUL BARAJAS |
| HVAC-Final | 2/25/2025 | Approved | RAUL BARAJAS |