2120 S SELBY AVE 90025
Certificate Information: 2120 S SELBY AVE 90025
- Application / Permit
- 21014-10000-04725
- Plan Check / Job No.
- B21LA17478
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. CONVERT (E) DETACHED GARAGE WITH NEW ADDITION TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d). NEW ATTACHED TRELLIS.
- Permit Issued
- Issued on 1/27/2022
- Issuing Office
- Current Status
- CofO Issued on 5/20/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/4/2021 | KEVIN MORALES |
| Corrections Issued | 10/4/2021 | KEVIN MORALES |
| Applicant returned to address corrections | 1/11/2022 | KEVIN MORALES |
| Plan Check Approved | 1/24/2022 | KEVIN MORALES |
| Issued | 1/27/2022 | APPLICANT |
| CofO in Progress | 5/17/2024 | SEAN HAUPT |
| Permit Finaled | 5/20/2024 | DANIEL ORRANTE |
| CofO Issued | 5/20/2024 | DANIEL ORRANTE |
| Permit Finaled | 5/20/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 10/20/2021 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 10/25/2021 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 11/30/2021 | VALERIA CEJA |
| Roof/Waste drainage to street | Cleared | 12/16/2021 | HISASHI KOBAYAKAWA |
| Construction near power lines | Cleared | 1/8/2022 | RIDWAN HARDY |
Contact Information
| Architect | Allen,, Patrick Sean; Lic. No.: C37534 | , |
| Contractor | Allen Design + Build Inc; Lic. No.: 1073018-B | 4474 W 133RD STREET HAWTHORNE, CA 90250 |
| Engineer | Canby,, John Christopher; Lic. No.: C21514 | 2370 MIDLOTHIAN DRIVE ALTADENA, CA 91001 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/17/2022 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 6/17/2022 | Partial Inspection | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 6/23/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 6/28/2022 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 7/6/2022 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 7/26/2022 | Not Ready for Inspection | JOHN KIDWELL |
| Footing/Foundation/Slab | 7/29/2022 | Approved | JOHN KIDWELL |
| METHANE-Rough | 10/11/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 10/12/2022 | Corrections Issued | EVAN COOPER |
| Pre-Inspection | 11/22/2022 | Approved | ASHLEY THOMPSON |
| Underground Mechanical | 1/31/2023 | Partial Approval | JULIAN AMAYA |
| ELECTRICAL-Rough | 2/14/2023 | Partial Approval | CLAYTON GRAHAM |
| PLUMBING-Rough | 3/1/2023 | No Access for Inspection | CLAYTON GRAHAM |
| PLUMBING-Rough | 3/3/2023 | Corrections Issued | CLAYTON GRAHAM |
| PLUMBING-Rough | 3/20/2023 | Corrections Issued | CLAYTON GRAHAM |
| Special/Order Compliance | 3/20/2023 | Partial Inspection | JESUS PINEDA |
| PLUMBING-Rough | 3/29/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| PLUMBING-Rough | 4/4/2023 | Corrections Issued | CLAYTON GRAHAM |
| HVAC-Rough | 4/7/2023 | Corrections Issued | CLAYTON GRAHAM |
| HVAC-Rough | 4/12/2023 | Approved | JEREMY TODD |
| PLUMBING-Rough | 4/12/2023 | Approved | JEREMY TODD |
| ELECTRICAL-Rough | 4/25/2023 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 5/2/2023 | Corrections Issued | JESUS PINEDA |
| BUILDING-Rough-Frame | 5/4/2023 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 5/4/2023 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 5/10/2023 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2023 | Approved | HERBERT GIRON |
| Green Building Rough | 5/10/2023 | Approved | HERBERT GIRON |
| Insulation | 5/10/2023 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 5/10/2023 | Partial Approval | HERBERT GIRON |
| METHANE-Rough | 5/10/2023 | Approved | HERBERT GIRON |
| Drywall Nailing | 5/16/2023 | Not Ready for Inspection | JEREMY TODD |
| Interior/Exterior Lathing | 5/16/2023 | Approved | JEREMY TODD |
| Drywall Nailing | 6/9/2023 | Approved | JESUS PINEDA |
| Shower Pan | 6/9/2023 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 6/14/2023 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 6/27/2023 | Corrections Issued | DAVID FEILER |
| Service/Power Release | 6/27/2023 | Not Ready for Inspection | DAVID FEILER |
| Service/Power Release | 7/21/2023 | Corrections Issued | JEREMY TODD |
| Final | 5/6/2024 | Corrections Issued | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 5/6/2024 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 5/6/2024 | Approved | SEAN HAUPT |
| Final | 5/16/2024 | OK to Issue CofO | SEAN HAUPT |