5463 S 5TH AVE 90043
Certificate Information: 5463 S 5TH AVE 90043
- Application / Permit
- 21014-10000-04724
- Plan Check / Job No.
- B21LA17477
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Addition and ADU conversion of an existing detached garage.
- Permit Issued
- Issued on 10/15/2021
- Issuing Office
- Current Status
- CofO Issued on 7/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/21/2021 | JOE VO |
| Corrections Issued | 9/21/2021 | JOE VO |
| Plan Check Approved | 10/12/2021 | JOE VO |
| Issued | 10/15/2021 | APPLICANT |
| CofO in Progress | 5/26/2022 | ANTHONY EGSON |
| Permit Finaled | 7/9/2022 | DEROLD HAUFF |
| CofO Issued | 7/9/2022 | DEROLD HAUFF |
| Permit Finaled | 7/9/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/30/2021 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 9/30/2021 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 10/1/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 10/1/2021 | STEVE MELGAR |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/17/2021 | Partial Inspection | ANTHONY EGSON |
| Pre-Inspection | 11/30/2021 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 12/7/2021 | Approved | SHAVONNE ESPINOZA |
| Excavation/Setback/Form/Re-Bar | 12/20/2021 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 12/20/2021 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2022 | Partial Approval | HORACE FULTZ |
| BUILDING-Rough-Frame | 1/21/2022 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 1/21/2022 | Approved | ANTHONY EGSON |
| HVAC-Rough | 1/21/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 1/21/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 1/27/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 1/28/2022 | Approved | ANTHONY EGSON |
| Insulation | 2/1/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 2/2/2022 | Approved | ANTHONY EGSON |
| Sewer | 2/2/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 2/14/2022 | Approved | ANTHONY EGSON |
| Shower Pan | 2/14/2022 | Approved | ANTHONY EGSON |
| Underground Mechanical | 3/15/2022 | Approved | HORACE FULTZ |
| ELECTRICAL-Final | 5/5/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 5/5/2022 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 5/5/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 5/5/2022 | Not Ready for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 5/5/2022 | SGSOV Approved | ANTHONY EGSON |
| Service/Power Release | 5/5/2022 | Corrections Issued | ANTHONY EGSON |
| Smoke Detectors | 5/5/2022 | Approved | ANTHONY EGSON |
| Final | 5/10/2022 | OK to Issue CofO | ANTHONY EGSON |
| ELECTRICAL-Final | 6/2/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 6/2/2022 | Approved | ANTHONY EGSON |