5463 S 5TH AVE 90043

Certificate Information: 5463 S 5TH AVE 90043

Application / Permit
21014-10000-04724
Plan Check / Job No.
B21LA17477
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition and ADU conversion of an existing detached garage.
Permit Issued
Issued on 10/15/2021
Issuing Office
Current Status
CofO Issued on 7/9/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/17/2021 APPLICANT
Assigned to Plan Check Engineer 9/21/2021 JOE VO
Corrections Issued 9/21/2021 JOE VO
Plan Check Approved 10/12/2021 JOE VO
Issued 10/15/2021 APPLICANT
CofO in Progress 5/26/2022 ANTHONY EGSON
Permit Finaled 7/9/2022 DEROLD HAUFF
CofO Issued 7/9/2022 DEROLD HAUFF
Permit Finaled 7/9/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/30/2021 STEVE MELGAR
Roof/Waste drainage to street Cleared 9/30/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 10/1/2021 STEVE MELGAR
Sewer availability Cleared 10/1/2021 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/17/2021 Partial Inspection ANTHONY EGSON
Pre-Inspection 11/30/2021 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 12/7/2021 Approved SHAVONNE ESPINOZA
Excavation/Setback/Form/Re-Bar 12/20/2021 Approved ANTHONY EGSON
Footing/Foundation/Slab 12/20/2021 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 1/6/2022 Partial Approval HORACE FULTZ
BUILDING-Rough-Frame 1/21/2022 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 1/21/2022 Approved ANTHONY EGSON
HVAC-Rough 1/21/2022 Approved ANTHONY EGSON
PLUMBING-Rough 1/21/2022 Approved ANTHONY EGSON
Interior/Exterior Lathing 1/27/2022 Approved ANTHONY EGSON
BUILDING-Rough-Frame 1/28/2022 Approved ANTHONY EGSON
Insulation 2/1/2022 Approved ANTHONY EGSON
BUILDING-Rough-Frame 2/2/2022 Approved ANTHONY EGSON
Sewer 2/2/2022 Approved ANTHONY EGSON
Drywall Nailing 2/14/2022 Approved ANTHONY EGSON
Shower Pan 2/14/2022 Approved ANTHONY EGSON
Underground Mechanical 3/15/2022 Approved HORACE FULTZ
ELECTRICAL-Final 5/5/2022 Not Ready for Inspection ANTHONY EGSON
Final 5/5/2022 Corrections Issued ANTHONY EGSON
HVAC-Final 5/5/2022 Approved ANTHONY EGSON
PLUMBING-Final 5/5/2022 Not Ready for Inspection ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 5/5/2022 SGSOV Approved ANTHONY EGSON
Service/Power Release 5/5/2022 Corrections Issued ANTHONY EGSON
Smoke Detectors 5/5/2022 Approved ANTHONY EGSON
Final 5/10/2022 OK to Issue CofO ANTHONY EGSON
ELECTRICAL-Final 6/2/2022 Approved ANTHONY EGSON
PLUMBING-Final 6/2/2022 Approved ANTHONY EGSON