4769 E BALTIMORE ST 90042

Certificate Information: 4769 E BALTIMORE ST 90042

Application / Permit
21014-10000-04712
Plan Check / Job No.
B21LA17438
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-story addtion to existing 2-story single family dwelling
Permit Issued
Issued on 5/5/2022
Issuing Office
Current Status
CofO Issued on 6/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/16/2021 APPLICANT
Assigned to Plan Check Engineer 10/21/2021 TU HUA
Corrections Issued 10/28/2021 TU HUA
Quality Review Completed 11/4/2021 KEN GILL
Applicant returned to address corrections 2/23/2022 TU HUA
Plan Check Approved 4/20/2022 ADRIANA LOPEZ
Building Plans Picked Up 4/25/2022 APPLICANT
Issued 5/5/2022 APPLICANT
CofO in Progress 6/1/2023 CRAIG VAUGHAN
CofO in Progress 6/1/2023 CRAIG VAUGHAN
Permit Finaled 6/3/2023 DEROLD HAUFF
CofO Issued 6/3/2023 DEROLD HAUFF
Permit Finaled 6/3/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/19/2021 CHRISTOPHER ROCHA
Sewer availability Cleared 11/19/2021 CHRISTOPHER ROCHA
Low Impact Development Cleared 12/14/2021 KHAING AYE
Roof/Waste drainage to street Cleared 1/14/2022 CHRISTOPHER ROCHA
Hydrant and Access approval Cleared 2/17/2022 JOHN CONNEALLY
Grading Pre-Inspection Cleared 2/25/2022 ALEXANDER HELFER

Contact Information

Contractor Concept Renovations Inc; Lic. No.: 1016942-B 16001 VENTURA BLVD STE 125      ENCINO, CA 91436

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/15/2022 Approved CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 8/23/2022 Corrections Issued SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 9/7/2022 Corrections Issued SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 10/21/2022 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 10/27/2022 Not Ready for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 10/27/2022 Corrections Issued BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 10/31/2022 Corrections Issued RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 11/3/2022 Approved CRAIG VAUGHAN
Wood Frame 11/3/2022 Partial Approval CRAIG VAUGHAN
Insulation 11/8/2022 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 11/8/2022 Corrections Issued KATHRYN BUTTERWORTH
Drywall Nailing 11/17/2022 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 12/5/2022 Corrections Issued SCOTT FINNILA
Final 12/5/2022 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 12/5/2022 Corrections Issued SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 12/5/2022 SGSOV Not Ready SCOTT FINNILA
Smoke Detectors 12/5/2022 Not Ready for Inspection SCOTT FINNILA
BUILDING-Rough-Frame 12/28/2022 Partial Approval CRAIG VAUGHAN
Wood Frame 12/28/2022 Approved CRAIG VAUGHAN
Special/Order Compliance 1/9/2023 Partial Inspection JAVIER RAMOS SR
BUILDING-Rough-Frame 5/19/2023 Approved CRAIG VAUGHAN
Final 5/19/2023 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 5/19/2023 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 5/19/2023 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 5/19/2023 Approved CRAIG VAUGHAN
Final 5/31/2023 OK to Issue CofO CRAIG VAUGHAN