1365 N AVENUE 46 90041

Certificate Information: 1365 N AVENUE 46 90041

Application / Permit
21014-10000-04679
Plan Check / Job No.
B21LA17289
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL AND ADDITION TO (E) SFD 1 OF 2
Permit Issued
Issued on 6/15/2023
Issuing Office
Metro
Current Status
CofO Issued on 11/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/18/2021 APPLICANT
Assigned to Plan Check Engineer 10/21/2021 ARSALAN SHABESTARI
Corrections Issued 10/28/2021 ARSALAN SHABESTARI
Quality Review Completed 11/5/2021 GARO TELMI
Building Plans Picked Up 11/29/2021 APPLICANT
Plan Check Approved 9/15/2022 ARSALAN SHABESTARI
Issued 6/15/2023 APPLICANT
CofO in Progress 10/31/2025 NICHOLAS LOPEZ
Permit Finaled 11/9/2025 DEROLD HAUFF
CofO Issued 11/9/2025 DEROLD HAUFF
Permit Finaled 11/9/2025 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 1/31/2022 JEANIE LAM
BHO/Hillside ordinance Cleared 1/31/2022 JEANIE LAM
BHO/Hillside ordinance Cleared 1/31/2022 JEANIE LAM
BHO/Hillside ordinance Cleared 1/31/2022 JEANIE LAM
BHO/Hillside ordinance Cleared 1/31/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 2/1/2022 JEANIE LAM
Sewer availability Cleared 2/1/2022 JEANIE LAM
Hydrant and Access approval Cleared 3/11/2022 CINDY JOSSELYN
Low Impact Development Cleared 5/10/2022 TA ANH
Roof/Waste drainage to street Cleared 5/14/2022 JEANETTE VONG
Excavation more than 5-ft deep Cleared 7/7/2022 CALOSHA APPROVED
GPI Written Notices Cleared 7/7/2022 ARSALAN SHABESTARI
Grading Pre-Inspection Cleared 7/7/2022 ARSALAN SHABESTARI

Contact Information

Contractor Dexterous Creative Contractors & Design Inc; Lic. No.: 1075451-B 97 16TH ST APT E      HERMOSA BEACH, CA 90254
Engineer Phillips,, Craig; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 6/29/2023 Corrections Issued HAMIK HARTOUNIAN
Piling/Pier/Caisson 7/7/2023 Approved HAMIK HARTOUNIAN
Deputy Reinf. Concrete 7/11/2023 Conditional Approval HAMIK HARTOUNIAN
Deputy Reinf. Concrete 7/20/2023 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 7/20/2023 Partial Approval HAMIK HARTOUNIAN
Deputy Reinf. Concrete 7/25/2023 Conditional Approval HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 8/11/2023 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 8/17/2023 Partial Approval HAMIK HARTOUNIAN
Deputy Shotcrete 8/31/2023 Conditional Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 8/31/2023 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 8/31/2023 Partial Approval HAMIK HARTOUNIAN
Deputy Reinf. Concrete 9/1/2023 Partial Approval HAMIK HARTOUNIAN
Deputy Shotcrete 9/8/2023 Conditional Approval HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 9/22/2023 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 9/22/2023 Conditional Approval HAMIK HARTOUNIAN
Deputy Steel/Welding 9/28/2023 Conditional Approval HAMIK HARTOUNIAN
Deputy Wood Construction 10/20/2023 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 12/15/2023 Corrections Issued HAMIK HARTOUNIAN
Wood Frame 1/10/2024 Conditional Approval HAMIK HARTOUNIAN
PLUMBING-Rough 1/24/2024 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 1/25/2024 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 2/12/2024 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 2/12/2024 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 2/14/2024 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 2/14/2024 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 2/14/2024 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 2/21/2024 Approved HAMIK HARTOUNIAN
HVAC-Rough 3/7/2024 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 3/8/2024 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 4/3/2024 Partial Approval BRIAN SULLIVAN
Green Building Rough 4/3/2024 Approved BRIAN SULLIVAN
Verify Sprinkler Sign Off 4/3/2024 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 4/5/2024 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 4/5/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Insulation 4/10/2024 Approved LILIANA PORTILLO
Interior/Exterior Lathing 4/10/2024 Not Ready for Inspection LILIANA PORTILLO
Interior/Exterior Lathing 4/12/2024 Partial Approval JOSEPH MCGARRY
Drywall Nailing 4/30/2024 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 6/13/2024 Partial Approval THOMAS LOGRASSO
Shower Pan 6/13/2024 Approved THOMAS LOGRASSO
ELECTRICAL-Final 11/21/2024 Corrections Issued THOMAS LOGRASSO
HVAC-Final 11/21/2024 Corrections Issued THOMAS LOGRASSO
PLUMBING-Final 11/21/2024 Corrections Issued THOMAS LOGRASSO
ELECTRICAL-Final 12/10/2024 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Final 12/13/2024 Approved THOMAS LOGRASSO
PLUMBING-Final 12/13/2024 Not Ready for Inspection THOMAS LOGRASSO
HVAC-Final 1/14/2025 Approved THOMAS LOGRASSO
PLUMBING-Final 1/14/2025 Approved THOMAS LOGRASSO
Final 8/5/2025 Corrections Issued NICHOLAS LOPEZ
Footing/Foundation/Slab 8/5/2025 Approved NICHOLAS LOPEZ
Green Building Final 8/5/2025 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 8/5/2025 SGSOV Approved NICHOLAS LOPEZ
Smoke Detectors 8/5/2025 Approved NICHOLAS LOPEZ
Final 10/30/2025 OK to Issue CofO NICHOLAS LOPEZ