1812 S RIMPAU BLVD 90019

Certificate Information: 1812 S RIMPAU BLVD 90019

Application / Permit
21014-10000-04674
Plan Check / Job No.
B21LA17273
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan CONVERT EXISTING GARAGE TO ADU W/ ADDITION PER LAMC 12.22 A.33(c) AND (d) AND PER WFPP
Permit Issued
Issued on 11/16/2021
Issuing Office
Current Status
CofO Issued on 6/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/16/2021 APPLICANT
Assigned to Plan Check Engineer 9/20/2021 CRYSTEL MAALOUF
Corrections Issued 9/20/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 10/26/2021 CRYSTEL MAALOUF
Plan Check Approved 11/9/2021 CRYSTEL MAALOUF
Issued 11/16/2021 APPLICANT
CofO in Progress 6/7/2023 CALEB MEISTER
Permit Finaled 6/16/2023 DEROLD HAUFF
CofO Issued 6/16/2023 DEROLD HAUFF
Permit Finaled 6/16/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/4/2021 CELINA MORENO
ZA Case Cleared 10/7/2021 RUBEN VASQUEZ
Eng Process Fee Ord 176,300 Cleared 10/14/2021 CELINA MORENO
Sewer availability Cleared 10/14/2021 CELINA MORENO

Contact Information

Contractor Sound Structures Inc; Lic. No.: 923028-B 21017 HILLSIDE DRIVE      TOPANGA, CA 90290

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/30/2021 Not Ready for Inspection STUART CHAPMAN
METHANE-Barrier 11/30/2021 Approved STUART CHAPMAN
METHANE-Subgrade 11/30/2021 Approved STUART CHAPMAN
Pre-Inspection 11/30/2021 Approved STUART CHAPMAN
Footing/Foundation/Slab 12/3/2021 Approved STUART CHAPMAN
ELECTRICAL-Rough 2/15/2022 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 2/15/2022 Partial Approval STUART CHAPMAN
Rough-Elec/Plmb/HVAC 2/15/2022 Not Ready for Inspection STUART CHAPMAN
Sewer 2/15/2022 Approved STUART CHAPMAN
Underground Mechanical 2/15/2022 Approved STUART CHAPMAN
BUILDING-Rough-Frame 3/29/2022 Partial Approval STUART CHAPMAN
METHANE-Rough 3/29/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 3/30/2022 Partial Approval STUART CHAPMAN
Insulation 4/14/2022 Approved STUART CHAPMAN
Insulation 4/25/2022 Approved STUART CHAPMAN
Drywall Nailing 6/17/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 8/16/2022 Approved STUART CHAPMAN
Gas Test 2/2/2023 Approved CALEB MEISTER
BUILDING-Rough-Frame 3/6/2023 Approved CALEB MEISTER
ELECTRICAL-Final 3/6/2023 Approved CALEB MEISTER
Final 3/6/2023 Corrections Issued CALEB MEISTER
HVAC-Final 3/6/2023 Approved CALEB MEISTER
PLUMBING-Final 3/6/2023 Corrections Issued CALEB MEISTER
SGSOV-Seismic Gas S/O Valve 3/6/2023 SGSOV Approved CALEB MEISTER
Smoke Detectors 3/6/2023 Approved CALEB MEISTER
ELECTRICAL-Final 4/12/2023 Approved CALEB MEISTER
Final 4/12/2023 Not Ready for Inspection CALEB MEISTER
HVAC-Final 4/12/2023 Approved CALEB MEISTER
PLUMBING-Final 4/12/2023 Approved CALEB MEISTER
Final 6/7/2023 OK to Issue CofO CALEB MEISTER