1812 S RIMPAU BLVD 90019
Certificate Information: 1812 S RIMPAU BLVD 90019
- Application / Permit
- 21014-10000-04674
- Plan Check / Job No.
- B21LA17273
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan CONVERT EXISTING GARAGE TO ADU W/ ADDITION PER LAMC 12.22 A.33(c) AND (d) AND PER WFPP
- Permit Issued
- Issued on 11/16/2021
- Issuing Office
- Current Status
- CofO Issued on 6/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/20/2021 | CRYSTEL MAALOUF |
| Corrections Issued | 9/20/2021 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 10/26/2021 | CRYSTEL MAALOUF |
| Plan Check Approved | 11/9/2021 | CRYSTEL MAALOUF |
| Issued | 11/16/2021 | APPLICANT |
| CofO in Progress | 6/7/2023 | CALEB MEISTER |
| Permit Finaled | 6/16/2023 | DEROLD HAUFF |
| CofO Issued | 6/16/2023 | DEROLD HAUFF |
| Permit Finaled | 6/16/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/4/2021 | CELINA MORENO |
| ZA Case | Cleared | 10/7/2021 | RUBEN VASQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/14/2021 | CELINA MORENO |
| Sewer availability | Cleared | 10/14/2021 | CELINA MORENO |
Contact Information
| Contractor | Sound Structures Inc; Lic. No.: 923028-B | 21017 HILLSIDE DRIVE TOPANGA, CA 90290 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/30/2021 | Not Ready for Inspection | STUART CHAPMAN |
| METHANE-Barrier | 11/30/2021 | Approved | STUART CHAPMAN |
| METHANE-Subgrade | 11/30/2021 | Approved | STUART CHAPMAN |
| Pre-Inspection | 11/30/2021 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 12/3/2021 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 2/15/2022 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2022 | Partial Approval | STUART CHAPMAN |
| Rough-Elec/Plmb/HVAC | 2/15/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Sewer | 2/15/2022 | Approved | STUART CHAPMAN |
| Underground Mechanical | 2/15/2022 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 3/29/2022 | Partial Approval | STUART CHAPMAN |
| METHANE-Rough | 3/29/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 3/30/2022 | Partial Approval | STUART CHAPMAN |
| Insulation | 4/14/2022 | Approved | STUART CHAPMAN |
| Insulation | 4/25/2022 | Approved | STUART CHAPMAN |
| Drywall Nailing | 6/17/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 8/16/2022 | Approved | STUART CHAPMAN |
| Gas Test | 2/2/2023 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 3/6/2023 | Approved | CALEB MEISTER |
| ELECTRICAL-Final | 3/6/2023 | Approved | CALEB MEISTER |
| Final | 3/6/2023 | Corrections Issued | CALEB MEISTER |
| HVAC-Final | 3/6/2023 | Approved | CALEB MEISTER |
| PLUMBING-Final | 3/6/2023 | Corrections Issued | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 3/6/2023 | SGSOV Approved | CALEB MEISTER |
| Smoke Detectors | 3/6/2023 | Approved | CALEB MEISTER |
| ELECTRICAL-Final | 4/12/2023 | Approved | CALEB MEISTER |
| Final | 4/12/2023 | Not Ready for Inspection | CALEB MEISTER |
| HVAC-Final | 4/12/2023 | Approved | CALEB MEISTER |
| PLUMBING-Final | 4/12/2023 | Approved | CALEB MEISTER |
| Final | 6/7/2023 | OK to Issue CofO | CALEB MEISTER |